Skip to Main Navigation

KABUPATEN ROADS III

Abstract*

The principal objectives of the Third Kabupaten Roads Development Project are to improve access to the main economic centers in 73 kabupatens (districts) in nine provinces (West Java, West Kalimantan and all provinces of Sumatra except Riau) and to increase the capability of all agencies in the country dealing with kabupaten roads. The project includes the following main components: (a) a road network improvement component, subdivided into three subcomponents:...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

CONTINUE TO IMPROVE THE INSTITUTIONAL AND TECHNICAL FRAMEWORK FORPLANNING AND IMPLEMENTING KABUPATEN ROAD PROJECTS WITH SPECIAL EMPHA-SIS ON MAINTENANCE AND TRAINING. IMPROVE THE QUALITY OF THE NETWORKIN ABOUT 65 KABUPATENS.

Key Details

Project Details

  • P003949

  • Closed

  • Jacques M. Tollie

  • N/A

  • Indonesia

  • June 17, 1992

  • (as of board presentation)

    June 17, 1992

  • September 28, 1992

  • US$ 215.00 million

  • B

  • Not Applicable

  • June 30, 1997

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 215.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 215.00
IDA Commitment N/A
IBRD + IDA Commitment 215.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 499.20

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 17, 1992 IBRD-34900 Loan Commitment 5,976,011.00
Jun 17, 1992 IBRD-3490S Loan Commitment 209,023,984.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-19-1998PROJECT PERFORMANCE ASSESSMENT REPORT: 04-22-1998
Outcome RatingSatisfactory Satisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceSatisfactorySatisfactory
Borrower PerformanceSatisfactorySatisfactory
Government PerformanceSatisfactorySatisfactory
Implementing AgencyNot RatedSatisfactory
Icr QualityNot RatedSatisfactory
M&e QualityNot RatedNot Rated

Results Framework

No data available.