Skip to Main Navigation

ID-IND'L TECHNOLOGY DEV

Abstract*

The objective of the Industrial Technology Development Project is to enhance the competitiveness of Indonesian industry, particularly of small and medium industries (SMIs), by: 1) providing public and private technology support services; 2) facilitating the access to public and private technology service providers; 3) strengthening public technology support institutions; and 4) improving the formulation and coordination of industrial technology policies...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

SUPPORTING POLICIES AND INFRASTRUCTURE FOR TECHNOLOGIAL INNOVATIONIN THE INDUSTRIAL SECTOR.

Key Details

Project Details

  • P003978

  • Closed

  • Lily Uy Hale

  • N/A

  • Indonesia

  • March 6, 1995

  • (as of board presentation)

    December 21, 1995

  • March 18, 1996

  • US$ 47.00 million

  • C

  • Not Applicable

  • December 31, 2001

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 47.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 47.00
IDA Commitment N/A
IBRD + IDA Commitment 47.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 60.90

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2015 IBRD-3972S Int Charges 16,519.95
Mar 15, 2016 IBRD-3972S Loan Repay 356,217.44
Mar 15, 2016 IBRD-3972S Int Charges 8,303.42
Mar 15, 2014 IBRD-3972S Loan Repay 309,535.62
Mar 15, 2014 IBRD-3972S Int Charges 38,601.44
Sep 15, 2013 IBRD-3972S Int Charges 46,306.70
Sep 15, 2013 IBRD-3972S Loan Repay 299,481.10
Dec 21, 1995 IBRD-3972S Loan Commitment 6,919,126.50
Dec 21, 1995 IBRD-3972A Loan Commitment 40,080,872.00
Dec 21, 1995 IBRD-39720 Loan Commitment 47,000,000.00
Sep 15, 2014 IBRD-3972S Loan Repay 321,026.50
Sep 15, 2014 IBRD-3972S Int Charges 31,938.58
Mar 15, 2015 IBRD-3972S Loan Repay 332,517.38
Mar 15, 2015 IBRD-3972S Int Charges 23,967.56
Sep 15, 2015 IBRD-3972S Loan Repay 344,008.25

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-05-2005PROJECT PERFORMANCE ASSESSMENT REPORT: 08-21-2002
Outcome RatingModerately Satisfactory Moderately Satisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceSatisfactorySatisfactory
Borrower PerformanceSatisfactorySatisfactory
Government PerformanceSatisfactorySatisfactory
Implementing AgencyNot RatedSatisfactory
Icr QualityNot RatedSatisfactory
M&e QualityNot RatedNot Rated

Results Framework

No data available.