Skip to Main Navigation

PTRL DIST & SEC MGMT

Abstract*

The objective of the project is to improve the efficiency of Korea's energy sector and enhance the reliability of petroleum supply. The project consists of three parts. The first is an approximately 1000 km pipeline system to transport petroleum products. The network will include an east-north trunkline connecting two eastern refineries near Pusan to Taejon; a west-north trunkline connecting the Honam refinery at Yeochon to Taejon; and two parallel...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

THE OBJECTIVE OF THE PROJ IS TO ENHANCE THE EFFICIENCY & RELIABILITYOF PETROLEUM PRODUCTS, TRANSPORTATION & DISTRIBUTION IN THE COUNTRY& TO IMPROVE THE ENVIRONMENT BY REDUCING THE AIR POLLUTION & ROADACCIDENT. THE PROJ CONSIST OF 1000 KM OF VARIOUS SIZE PIPELINE.

Key Details

Project Details

  • P004170

  • Closed

  • Mohammad Farhandi

  • N/A

  • Korea, Republic of

  • June 3, 1993

  • (as of board presentation)

    June 3, 1993

  • September 13, 1993

  • US$ 120.00 million

  • A

  • Not Applicable

  • December 31, 1998

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 120.00
Foreign Private Commercial Sources (unidentified) 461.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 120.00
IDA Commitment N/A
IBRD + IDA Commitment 120.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 809.70

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 3, 1993 IBRD-36130 Loan Commitment 120,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-12-1999PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.