Skip to Main Navigation

COMMUNAL IRRIG. II

Abstract*

The project objectives are to provide for continuity and improvements in implementation of the ongoing communal irrigation development efforts. The project includes: (a) construction of new and rehabilitation and improvement of existing communal irrigation systems, including provision of adequate service and access roads and simple Irrigator Association (IA) storage facilities and drying floors, and erosion control measures; (b) development of communal...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

PHASE II SUPPORT FOR NIA'S COMMUNAL IRRIGATION PROGRAM.

Key Details

Project Details

  • P004572

  • Closed

  • Syed Husain

  • N/A

  • Philippines

  • October 4, 1990

  • (as of board presentation)

    October 4, 1990

  • January 11, 1991

  • US$ 46.20 million

  • B

  • Not Applicable

  • December 31, 1999

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 46.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 46.20
IDA Commitment N/A
IBRD + IDA Commitment 46.20
Lending Instrument
Grant Amount N/A
Total Project Cost** 66.20

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 4, 1990 IBRD-32610 Loan Commitment 27,570,612.00
Oct 4, 1990 IBRD-3261A Loan Commitment 18,629,388.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-02-2000PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceNot RatedN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.