Skip to Main Navigation

POWER TRANSM & REHAB

Abstract*

The main objectives of the Power Transmission and Rehabilitation Project are to alleviate power shortages in Luzon, through: (a) a transmission system expansion and reinforcement program needed to bring power to Manila from the fast track generation plants; and (b) the rehabilitation of the Bataan thermal generating plant. It will also improve the performance of the energy sector with an Energy Sector Plan covering policies, institutions and implementing...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

HELP IN SOLVING A SERIOUS ENERGY SUPPLY CRISIS UNDER EMERGENCYCIRCUMSTANCES WHILE IMPROVING THE FINANCES OF THE POWER CORPORATIONAND ESTABLISHING AN ACTION PLAN FOR THE ENERGY SECTOR.

Key Details

Project Details

  • P004610

  • Closed

  • Mohammad Farhandi

  • N/A

  • Philippines

  • June 22, 1993

  • (as of board presentation)

    June 22, 1993

  • December 6, 1993

  • US$ 110.50 million

  • B

  • Not Applicable

  • December 31, 1997

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
JAPAN: Ministry of Finance - PHRD Grants 0.50
International Bank for Reconstruction and Development 110.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 110.00
IDA Commitment N/A
IBRD + IDA Commitment 110.00
Lending Instrument
Grant Amount 0.50
Total Project Cost** 86.40

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 15, 2014 IBRD-36260 Loan Repay 16,559.00
Jun 22, 1993 IBRD-36260 Loan Commitment 110,000,000.00
Sep 15, 2013 IBRD-36260 Loan Repay 39,458.22
Sep 15, 2013 IBRD-36260 Loan Repay 2,771,072.00
Sep 15, 2013 IBRD-36260 Int Charges 102,577.42
Mar 15, 2014 IBRD-36260 Int Charges 604.37

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-25-1998PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.