Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.73 |
DENMARK: Danish Intl. Dev. Assistance (DANIDA) | 1.20 |
JAPAN: JAPAN INTERNATIONAL COOPERATION AGENCY (JICA) | 2.00 |
P004613
Closed
Gilbert Magno Braganza
N/A
June 28, 1995
(as of board presentation)
November 26, 1996
March 20, 1997
US$ 85.20 million
N/A
1997
US$ 53.93 million
B
Not Applicable
June 30, 2005
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.73 |
DENMARK: Danish Intl. Dev. Assistance (DANIDA) | 1.20 |
JAPAN: JAPAN INTERNATIONAL COOPERATION AGENCY (JICA) | 2.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 50.73 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 50.73 |
Lending Instrument | |
---|---|
Grant Amount | 3.20 |
Total Project Cost** | 85.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 26, 1996 | IBRD-41100 | Loan Commitment | 58,000,000.00 |
Jul 15, 2016 | IBRD-41100 | Loan Repay | 1,833,900.00 |
Jul 15, 2016 | IBRD-41100 | Int Charges | 21,995.24 |
Jan 15, 2017 | IBRD-41100 | Loan Repay | 1,884,649.80 |
Jan 15, 2017 | IBRD-41100 | Int Charges | 12,811.43 |
Jul 15, 2014 | IBRD-41100 | Loan Repay | 1,630,200.00 |
Jul 15, 2014 | IBRD-41100 | Int Charges | 29,141.96 |
Jan 15, 2015 | IBRD-41100 | Int Charges | 25,953.01 |
Jan 15, 2015 | IBRD-41100 | Loan Repay | 1,679,500.00 |
Jul 15, 2015 | IBRD-41100 | Loan Repay | 1,728,800.00 |
Jul 15, 2015 | IBRD-41100 | Int Charges | 22,897.39 |
Jan 15, 2016 | IBRD-41100 | Loan Repay | 1,781,500.00 |
Jan 15, 2016 | IBRD-41100 | Int Charges | 21,083.51 |
Jul 15, 2013 | IBRD-41100 | Loan Repay | 1,403,411.60 |
Jul 15, 2013 | IBRD-41100 | Loan Repay | 131,388.33 |
Jul 15, 2013 | IBRD-41100 | Int Charges | 48,055.38 |
Jan 15, 2014 | IBRD-41100 | Int Charges | 37,785.76 |
Jan 15, 2014 | IBRD-41100 | Loan Repay | 1,580,900.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2005-05-30 |
Procurement | Satisfactory | 2005-05-30 |
Counterpart Funding | Moderately Satisfactory | 2005-05-30 |
Project Management | Satisfactory | 2005-05-30 |
Financial Management | Satisfactory | 2005-05-30 |
Overall Safeguards Rating | Satisfactory | 2005-05-30 |
Monitoring and Evaluation | Satisfactory | 2005-05-30 |
Overall Implementation Progress (IP) | Satisfactory | 2005-05-30 |
INDICATOR | ICR REVIEW: 10-10-2006 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Not Rated | N/a |