GAS TRANSMISSION

Abstract*

The objective of the Bongkot Gas Transmission Project is to increase the gas supply capabilities of Thailand by: (a) expanding the gas transmission system; (b) strengthening the institutional functioning of the Petroleum Authority of Thailand (PTT); and (c) making more efficient use of capital resources in the gas sector through annual review of PTT's investment program. The project consists of the following components: (1) a long submarine pipeline...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

TO UTILIZE NATURAL GAS RESERVES IN THE SOUTH OF GULF OF THAILAND TOMEET THE INCREASING ENERGY DEMAND IN CENTRAL AND SOUTHERN REGIONS.

Key Details

Project Details

  • P004767

  • Closed

  • Mohammad Farhandi

  • N/A

  • Thailand

  • July 7, 1992

  • (as of board presentation)

    July 7, 1992

  • December 8, 1992

  • US$ 215.00 million

  • A

  • Not Applicable

  • December 31, 1995

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
JAPAN: JEXIMBANK (UNTIED FACILITY) 52.00
Asian Development Bank 58.00
International Bank for Reconstruction and Development 105.00
US: Export-Import Bank of the United States (EXIMBANK) 7.30
Foreign Private Commercial Sources (unidentified) 56.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 105.00
IDA Commitment N/A
IBRD + IDA Commitment 105.00
Lending Instrument
Grant Amount 110.00
Total Project Cost** 348.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 7, 1992 IBRD-3508S Loan Commitment 87,407,520.00
Jul 7, 1992 IBRD-35080 Loan Commitment 17,592,482.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-06-1996PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceNot RatedN/a
Borrower PerformanceNot RatedN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyNot RatedN/a
Icr QualityNot RatedN/a
M&e QualityNot RatedN/a

Results Framework

No data available.