The Third Power Project supports a financial restructuring designed to ensure a satisfactory financial autonomy and performance of SONELGAZ (Societe Nationale de l'Electricite et du Gaz). It will strengthen the existing power system by: (a) the construction of transmission lines to interconnect the power station under construction at Jijel to SONELGAZ's bulk supply systems; (b) the construction and/or extension of seven transformer substations; and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

CONSTRUCTION OF 450KM OF 220 KV TRANSMISSION LINES AND SEVEN POWERTRANSFORMER SUBSTATIONS. TRAINING & TECH. ASST. FOR VARIOUS STUDIES.

Key Details

Project Details

  • P004904

  • Closed

  • Rene G. Mendonca

  • N/A

  • Algeria

  • June 29, 1988

  • (as of board presentation)

    June 29, 1988

  • March 29, 1990

  • US$ 160.00 million

  • C

  • Not Applicable

  • June 30, 1997

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 160.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 160.00
IDA Commitment N/A
IBRD + IDA Commitment 160.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 313.80

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 26, 1989 COFN-02110 Loan Commitment 86,500,000.00
Jun 29, 1988 IBRD-2981S Loan Commitment 62,296,504.00
Jun 29, 1988 IBRD-29810 Loan Commitment 97,703,496.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-31-1998PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework