Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 54.00 |
P004914
Closed
Luis Guillermo Hakim
N/A
June 24, 1988
(as of board presentation)
June 24, 1988
September 6, 1989
US$ 89.50 million
N/A
1988
US$ 54.00 million
C
Not Applicable
June 30, 1997
BANK APPROVED
July 16, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 54.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 54.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 54.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 89.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 24, 1988 | IBRD-29770 | Loan Commitment | 27,415,300.00 |
Jun 24, 1988 | IBRD-2977S | Loan Commitment | 19,957,046.00 |
Jun 24, 1988 | IBRD-2977A | Loan Commitment | 6,627,653.50 |
INDICATOR | ICR REVIEW: 06-23-1998 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Unsatisfactory | N/a |
Government Performance | Unsatisfactory | N/a |
Implementing Agency | Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Not Rated | N/a |