The First Petroleum Project's primary objectives are to: (i) help the Government and SONATRACH in their efforts to attract investments in exploration and development by foreign oil companies; (ii) help improve the efficiency of the petroleum services subsector (particularly drilling operations); (iii) help optimize the production of its oil fields through enhanced oil recovery schemes; and (iv) address environmental problems related to drilling and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

PROJECT TO FOCUS ON ASSISTANCE TO SONATRACH IN THREE MAIN AREAS:(1) EXPLORATION PROMOTION; (2) TECHNICAL TRAINING, AND (3) SECONDARYOIL RECOVERY.

Key Details

Project Details

  • P004952

  • Closed

  • Rene G. Mendonca

  • N/A

  • Algeria

  • July 30, 1991

  • (as of board presentation)

    July 30, 1991

  • April 2, 1992

  • US$ 100.00 million

  • B

  • Not Applicable

  • June 30, 1997

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 237.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 30, 1991 IBRD-3395S Loan Commitment 76,079,080.00
Jul 30, 1991 IBRD-33950 Loan Commitment 23,920,918.00
Jun 26, 1992 COFN-02790 Loan Commitment 76,800,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-05-1998PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a