Skip to Main Navigation

PORT SECTOR

Abstract*

The project objectives are to: (a) improve operational efficiency in the ports: (b) assist the government in strengthening the economic viability of its investments in the port subsector; and (c) encourage policies and institutional measures. The project consists of an investment component and an institutional development component. The investment component finances: (a) selected subprojects of the Office of Port Operations (ODEP's) investment program...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

PROJECT WOULD SUPPORT FURTHER DEVELOPMENT OF PORT SECTOR INCLUDING CONTAINER HANDLING IN CASABLANCA, RO-RO TRAFFIC IN TANGIER, COAL TRAFFIC IN JORF LASFAR, MARINE SECURITY EQUIPMENT BREDGING AND RELATED INSTITUTIONAL MEASURES.

Key Details

Project Details

  • P005433

  • Closed

  • Michel A. Loir

  • N/A

  • Morocco

  • December 20, 1990

  • (as of board presentation)

    December 20, 1990

  • January 6, 1992

  • US$ 132.00 million

  • B

  • Not Applicable

  • June 30, 1998

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 132.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 132.00
IDA Commitment N/A
IBRD + IDA Commitment 132.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 251.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 20, 1990 IBRD-3283A Loan Commitment 8,089,870.00
Dec 20, 1990 IBRD-3283S Loan Commitment 17,746,630.00
Dec 20, 1990 IBRD-32840 Loan Commitment 99,000,000.00
Dec 20, 1990 IBRD-32830 Loan Commitment 7,163,500.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-29-1999PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.