Abstract*

The objectives of the project are: (a) to promote equality of educational opportunity at the middle school level by improving access and participation; and (b) to enhance the teaching-learning environment by contributing to the improvement of basic education quality, nationwide. To achieve these objectives, the project will finance: (a) the construction, equipping and furnishing of about 250 middle schools in rural areas, each accommodating some 360...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

TO INCREASE ACCESS TO LOWER SECONDARY CYCLE (GRADES 7-9) IN RURALAREAS AND IMPROVE QUALITY.

Key Details

Project Details

  • P005460

  • Closed

  • Mourad Ezzine

  • N/A

  • Morocco

  • February 26, 1991

  • (as of board presentation)

    February 26, 1991

  • March 19, 1992

  • US$ 190.00 million

  • C

  • Not Applicable

  • June 30, 1998

  • BANK APPROVED

  • July 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 145.00
African Development Bank 45.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 145.00
IDA Commitment N/A
IBRD + IDA Commitment 145.00
Lending Instrument
Grant Amount 45.00
Total Project Cost** 139.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 26, 1991 IBRD-32950 Loan Commitment 77,105,504.00
Feb 26, 1991 IBRD-3295S Loan Commitment 41,982,840.00
Feb 26, 1991 IBRD-3295A Loan Commitment 25,911,660.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-30-1999PROJECT PERFORMANCE ASSESSMENT REPORT: 06-27-2001
Outcome RatingUnsatisfactory Unsatisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceUnsatisfactoryUnsatisfactory
Borrower PerformanceUnsatisfactoryUnsatisfactory
Government PerformanceUnsatisfactorySatisfactory
Implementing AgencyUnsatisfactoryNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityNot RatedNot Rated

Results Framework