Abstract*

The Fourth Urban Development Project will improve shelter and urban services in under served or squatter settlements and develop serviced land affordable to low-income households. The project consists of the upgrading, to be coordinated by the Urban Regrading and Renewal Agency (ARRU), of infrastructure and community facilities in under served settlements. It will also provide for the development of serviced sites by the Land Development Agency (AFH)...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Key Details

Project Details

  • P005668

  • Closed

  • Dalila Tadjerouni

  • N/A

  • Tunisia

  • N/A

  • (as of board presentation)

    July 3, 1986

  • April 17, 1987

  • US$ 0.00 million

  • C

  • Not Applicable

  • N/A

  • BANK APPROVED

  • N/A

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-31-1996PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceNot RatedN/a
Borrower PerformanceNot RatedN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyNot RatedN/a
Icr QualityNot RatedN/a
M&e QualityNot RatedN/a

Results Framework