Financier | Commitments |
---|---|
JAPAN: JEXIMBANK (UNTIED FACILITY) | 200.00 |
International Bank for Reconstruction and Development | 300.00 |
P006012
Closed
Anil Kapur
N/A
January 5, 1993
(as of board presentation)
January 5, 1993
February 16, 1993
US$ 300.00 million
N/A
1993
US$ 500.00 million
N/A
Not Applicable
December 31, 1995
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
JAPAN: JEXIMBANK (UNTIED FACILITY) | 200.00 |
International Bank for Reconstruction and Development | 300.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 300.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | 200.00 |
Total Project Cost** | 300.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 5, 1993 | IBRD-35560 | Loan Commitment | 14,195,000.00 |
Jan 5, 1993 | IBRD-3556S | Loan Commitment | 285,804,992.00 |
INDICATOR | ICR REVIEW: 12-13-1996 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Not Rated | N/a |
Borrower Performance | Not Rated | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Not Rated | N/a |
Icr Quality | Not Rated | N/a |
M&e Quality | Not Rated | N/a |