Skip to Main Navigation

URBN TRNSPRT I

Abstract*

Through this project, the government of Mexico seeks to improve its urban transport sector in services, efficiency, costs, infrastructure and institutional capability. To that end, the project specifically involves (a) corridor improvements, (b) public transport, and (c) road maintenance. It further entails (d) traffic system management to improve traffic flow and safety. The proposed project would demonstrate the cost-effectiveness of an integrated...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

INVESTMENTS IN TRANSPORT INFRASTRUCTURE & TRAFFIC MANAGEMENT IN THESTATE OF MEXICO, AND MONTERREY.

Key Details

Project Details

  • P007615

  • Closed

  • Guillermo Ruan

  • N/A

  • Mexico

  • May 28, 1987

  • (as of board presentation)

    May 28, 1987

  • February 11, 1988

  • US$ 125.00 million

  • C

  • Not Applicable

  • June 30, 1998

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 125.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 125.00
IDA Commitment N/A
IBRD + IDA Commitment 125.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 143.20

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 28, 1987 IBRD-2824A Loan Commitment 1,661,074.20
May 28, 1987 IBRD-2824S Loan Commitment 25,664,256.00
May 28, 1987 IBRD-28240 Loan Commitment 97,674,672.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-19-1999PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.