Irrigation and Drainage Sector Project

Abstract*

The project will help the government to: sustain the irrigation and drainage sector through adequate levels of investments; decentralize irrigation funding and management through institutional reforms; fully utilize existing irrigation schemes by finishing uncompleted works; improve water use efficiency; strengthen the institutional capacity of the National Water Commission (CNA) and user organizations; monitor and help prevent environmental and natural...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

TO PROVIDE SUPPORT AND FINANCIAL ASSISTANCE TO THE GOVERNMENT'SPROGRAM TO STRENGTHEN SECTORAL POLICIES AND INSTITUTIONS IN MEXICO'SIRRIGATION/DRAINAGE SECTOR.

Key Details

Project Details

  • P007667

  • Closed

  • Jose Simas

  • N/A

  • Mexico

  • December 3, 1991

  • (as of board presentation)

    December 3, 1991

  • June 18, 1992

  • US$ 600.00 million

  • B

  • January 15, 2013

  • June 30, 2000

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Inter-American Development Bank 200.00
International Bank for Reconstruction and Development 400.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 400.00
IDA Commitment N/A
IBRD + IDA Commitment 400.00
Lending Instrument
Grant Amount 200.00
Total Project Cost** 1245.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 3, 1991 IBRD-3419S Loan Commitment 220,206,432.00
Dec 3, 1991 IBRD-3419A Loan Commitment 100,629,976.00
Dec 3, 1991 IBRD-34190 Loan Commitment 79,163,600.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-22-2005PROJECT PERFORMANCE ASSESSMENT REPORT: 06-19-2001
Outcome RatingSatisfactory Highly Satisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceSatisfactoryHighly Satisfactory
Borrower PerformanceSatisfactoryHighly Satisfactory
Government PerformanceSatisfactoryNot Rated
Implementing AgencyNot RatedHighly Satisfactory
Icr QualityNot RatedSatisfactory
M&e QualityNot RatedNot Rated

Results Framework

No data available.