Skip to Main Navigation

Eighth Highway Project

Abstract*

The project is principally aimed at strengthening the Ministry of Public Works and Communications' (MOPC's) organization and promoting team-work at its highest level, thus, improving its capacity to deliver good roads and a well maintained network. The project includes three components. The first component, civil works includes: (i) road improvements; (ii) road rehabilitation; and (iii) a pilot unpaved-road stabilization program to treat 80 km of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

ROAD CONSTRUCTION AND REHABILITATION, SUPPORT FOR INSTITUTIONAL DEVELOPMENT; STUDIES; ENGINEERING DESIGNS.

Key Details

Project Details

  • P007913

  • Closed

  • Paulus A. Guitink

  • N/A

  • Paraguay

  • December 21, 1993

  • (as of board presentation)

    December 21, 1993

  • July 20, 1994

  • US$ 65.00 million

  • B

  • Not Applicable

  • April 30, 2004

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 65.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 65.00
IDA Commitment N/A
IBRD + IDA Commitment 65.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 144.30

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2013 IBRD-36850 Loan Repay 4,026,976.80
Dec 21, 1993 IBRD-36850 Loan Commitment 65,000,000.00
Dec 15, 2013 IBRD-36850 Int Charges 62,185.35

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-21-2002PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualityExemplaryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.