Skip to Main Navigation

Southeast Coast Sewerage & Drainage Project

Abstract*

The project will provide sewerage and drainage systems for Larnaca, and sewerage systems for the communities of Ayia Napa and Paralimni. Only the first phase (coastal areas) of a sewerage system for Larnaca will be included. The project will consist of: (i) central sewage collection, treatment, and disposal systems; (ii) the distribution of treated effluent for re-use; (iii) upgrading the existing stormwater drainage system in Larnaca; and (iv) technical...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

IMPROVE SANITATION AND DRAINAGE IN THREE COMMUNITIES AND NEIGHBORINGTOURIST AREAS AND REUSE OF WATER FOR IRRIGATION OF HOTEL GROUNDS ANDPARKS.

Key Details

Project Details

  • P008375

  • Closed

  • Takao Ikegami

  • N/A

  • Cyprus

  • August 30, 1991

  • (as of board presentation)

    August 30, 1991

  • May 1, 1992

  • US$ 73.00 million

  • A

  • January 15, 2013

  • June 30, 1999

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
EC: Council of Europe Resettlement (Social) Fund (CERF) 24.00
International Bank for Reconstruction and Development 32.00
EC: European Investment Bank 17.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 32.00
IDA Commitment N/A
IBRD + IDA Commitment 32.00
Lending Instrument
Grant Amount 41.00
Total Project Cost** 120.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 30, 1991 IBRD-33980 Loan Commitment 14,700,000.00
Aug 30, 1991 IBRD-33990 Loan Commitment 11,300,000.00
Aug 30, 1991 IBRD-34000 Loan Commitment 6,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-19-2000PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualityExemplaryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.