Oil Rehabilitation Project

Abstract*

The project will fund specific investments in oil production operations with the objectives of: retarding the rate of decline of oil production and exports in the near term; strengthening the managerial and technical capabilities as well as the financial viability of selected oil producing enterprises; and mobilizing additional financial resources for the sector through commitments to cofinancing and through the demonstration effect of the project...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

TO REHABILITATE, MAINTAIN AND OPERATE FACILITIES IN THE OIL AND GAS SECTOR.

Key Details

Project Details

  • P008809

  • Closed

  • William R. Porter

  • N/A

  • Russian Federation

  • June 17, 1993

  • (as of board presentation)

    June 17, 1993

  • November 15, 1993

  • US$ 866.00 million

  • A

  • January 15, 2013

  • December 31, 1999

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
NETHERLANDS, Govt. of THE (Except for MOFA/Min of Dev. Coop 6.00
European Bank for Reconstruction and Development 250.00
International Bank for Reconstruction and Development 610.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 610.00
IDA Commitment N/A
IBRD + IDA Commitment 610.00
Lending Instrument
Grant Amount 256.00
Total Project Cost** 866.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 17, 1993 IBRD-36233 Loan Commitment 10,000,000.00
Jun 17, 1993 IBRD-36230 Loan Commitment 272,000,000.00
Jun 17, 1993 IBRD-36232 Loan Commitment 170,000,000.00
Jun 17, 1993 IBRD-36231 Loan Commitment 158,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-21-2000PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a