Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
SWITZERLAND, Govt. of (Except for FOFEA) | 1.10 |
P008826
Closed
Ulrich Albert Hewer
N/A
October 31, 1994
(as of board presentation)
December 15, 1994
July 3, 1995
US$ 51.40 million
N/A
1995
US$ 41.10 million
C
Not Applicable
November 1, 1999
BANK APPROVED
August 11, 2022
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
SWITZERLAND, Govt. of (Except for FOFEA) | 1.10 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | 1.10 |
Total Project Cost** | 51.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 1994 | IBRD-38240 | Loan Commitment | 40,000,000.00 |
INDICATOR | ICR REVIEW: 08-17-2000 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Exemplary | N/a |
M&e Quality | Not Rated | N/a |