Skip to Main Navigation

ANTALYA WS & SANITATION

Abstract*

The objectives of the Antalya Water Supply and Sanitation Project are to: a) meet at least cost the demand for water supply, sewerage and stormwater drainage; b) develop new institutional arrangements for management of municipal water supply, sewerage and stormwater drainage, and to introduce private sector participation in the operation of the services; c) implement appropriate cost recovery policies; d) postpone the need to develop costly new water...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

THE PROJECT WOULD HELP FINANCE RENOVATING, REHABILITATING AND EXTEND- ING THE EXISTING WATER SUPPLY SYSTEM; PROVIDING A NEW SEWAGE NETWORK AND A PRELIMINARY WASTE WATER TREATMENT PLANT; IMPROVING THE OPERATION OF SEPTIC TANKS; UPGRADING THE STORMWATER DRAINAGE SYSTEM AND ESTABLI- SHING A COMPREHENSIVE MASTER PLAN.

Key Details

Project Details

  • P009093

  • Closed

  • Alptekin Orhon

  • N/A

  • Turkiye

  • April 6, 1995

  • (as of board presentation)

    May 25, 1995

  • December 22, 1995

  • US$ 145.00 million

  • B

  • Not Applicable

  • June 30, 2003

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
EC: European Investment Bank 45.00
International Bank for Reconstruction and Development 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount 45.00
Total Project Cost** 244.60

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 25, 1995 IBRD-38930 Loan Commitment 0.00
May 25, 1995 IBRD-38936 Loan Commitment 100,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-29-2004PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.