Skip to Main Navigation

TA FOR TREASURY DATA

Development Objective

THE PROJECT AIMS TO STRENGTHEN THE GOT'S (TREASURY'S) SYSTEMS,INFORMATION, AND PROCESSES RELATED TO MACROECONOMIC MANAGEMENT.

Key Details

Project Details

  • P009097

  • Closed

  • Ismail Arslan

  • N/A

  • Turkiye

  • May 28, 1992

  • (as of board presentation)

    May 28, 1992

  • September 10, 1992

  • US$ 9.20 million

  • C

  • Not Applicable

  • June 30, 2000

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 9.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 9.20
IDA Commitment N/A
IBRD + IDA Commitment 9.20
Lending Instrument
Grant Amount N/A
Total Project Cost** 28.10

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 28, 1992 IBRD-34770 Loan Commitment 0.00
May 28, 1992 IBRD-3477A Loan Commitment 2,116,314.50
May 28, 1992 IBRD-3477S Loan Commitment 7,083,685.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-07-2001PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.