Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 184.00 |
P010352
Closed
John Tillman
N/A
June 28, 1990
(as of board presentation)
June 28, 1990
February 26, 1991
US$ 300.70 million
N/A
1990
US$ 184.00 million
B
Not Applicable
June 30, 1998
BANK APPROVED
March 11, 2021
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 184.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 184.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 184.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 300.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 28, 1990 | IBRD-32410 | Loan Commitment | 184,000,000.00 |
INDICATOR | ICR REVIEW: 08-19-1999 | PROJECT PERFORMANCE ASSESSMENT REPORT: 02-09-2000 |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | Moderately Satisfactory |
Risk To Development Outcome | Not Rated | Not Rated |
Bank Performance | Satisfactory | Satisfactory |
Borrower Performance | Satisfactory | Satisfactory |
Government Performance | Unsatisfactory | Unsatisfactory |
Implementing Agency | Satisfactory | Not Rated |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | Not Rated | Not Rated |