Financier | Commitments |
---|---|
IDA Credit | 30.30 |
ITALY: MINSTRY OF FOREIGN AFFAIRS | 21.00 |
P034154
Closed
Josphat Sasia
N/A
October 12, 1995
(as of board presentation)
November 18, 1997
September 6, 1997
US$ 51.30 million
N/A
1998
US$ 51.30 million
A
March 11, 2021
December 31, 2011
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 30.30 |
ITALY: MINSTRY OF FOREIGN AFFAIRS | 21.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 30.30 |
IBRD + IDA Commitment | 30.30 |
Lending Instrument | |
---|---|
Grant Amount | 21.00 |
Total Project Cost** | 51.30 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 18, 1997 | IDA-30050 | Loan Commitment | 30,300,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2011-09-24 |
Project Management | Satisfactory | 2011-09-24 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-09-24 |
Counterpart Funding | Satisfactory | 2011-09-24 |
Overall | High | 2011-09-24 |
Progress towards achievement of PDO | Satisfactory | 2011-09-24 |
Financial Management | Satisfactory | 2011-09-24 |
Monitoring and Evaluation | Satisfactory | 2011-09-24 |
Overall Safeguards Rating | Satisfactory | 2011-09-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-03-2013 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 12-09-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Massawa Bulk Cargo tons/ship/day | Value | 850 | 1100 | |
Date | April 30, 1997 | September 30, 2010 | December 31, 2011 | |
Comment | No ship docked during the quarter July-Sept 2010. No information is available after Sept. 2010. |
Massawa Bagged CargoTons/ship/day | Value | 900 | 1200 | |
Date | April 30, 1997 | September 30, 2010 | December 31, 2011 | |
Comment | Below end of project target because the equipment was not fully utilized arising from MPA#s inability to procure spare parts in atimely manner |
Massawa Break-Bulk CargoTons/ship/day | Value | 260 | 286 | |
Date | April 30, 1997 | March 31, 2010 | December 31, 2011 | |
Comment | End of project target attained |
Massawa Container CargoTEU/hour | Value | 3 | 12 | |
Date | April 30, 1997 | September 30, 2010 | December 31, 2011 | |
Comment | Decline arising from delays in procuring spare parts attributed to foreign exchange availability constraints |
Massawa Berth Occupancy (%) | Value | 70% | 67% | |
Date | April 30, 1997 | March 31, 2010 | December 31, 2011 | |
Comment | Increased cargo destined for a number of projects underway |
N/A | Value | |||
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Replace Shore Cranes(These cranes are critical to productivity: but are being procured through non-project bilateral trade arrangements following a misprocurement ruling) | Value | 3 | 3 | |
Date | April 30, 1997 | October 8, 2008 | June 30, 2008 | |
Comment | Originally the Government of Netherlands was to provide 3 shore cranes thru bilateral arrangement; however this was scaled down to2). Therefore, it is 100%. | Target achieved |
Procure all other cargo handling equipment for Port Massawa | Value | 0 | 100% | |
Date | April 30, 1997 | October 8, 2008 | June 30, 2008 | |
Comment | Completed |
Complete Port Rehabilitation and Upgrade Works at Port Massawa | Value | 0 | 100% | |
Date | April 30, 1997 | October 8, 2008 | June 30, 2008 | |
Comment | Completed |
Complete improvement of Massawa causeways | Value | 0 | Two, Dahlak and Sigalet causeways | |
Date | December 7, 1999 | January 31, 2007 | January 31, 2007 | |
Comment | Completed |
Repair old oil jetty at Hirgigo, Massawa | Value | Old oil jetty in a poor state | Old oil jetty repaired | |
Date | June 15, 2006 | November 30, 2008 | November 30, 2008 | |
Comment | Completed |
Construct a new oil jetty at Hirgigo, Massawa | Value | 0 | New oil jetty constructed | |
Date | June 15, 2006 | December 5, 2010 | December 31, 2011 | |
Comment | New oil jetty constructed to be constructed by Sept. 2012 |