ER-Ports Rehab SIL (FY98)

Abstract*

The Ports Rehabilitation Project is designed to increase substantially the productivity and capacity of the two ports of Massawa and Assab. To this end, the project will provide the financial and technical assistance required to rehabilitate and upgrade the two ports, optimizing the use of existing facilities, and to raise the quality and level of services to international standards. The project components are: 1) civil works for Massawa, such as...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The revised Project Development Objective is to increase the productivity and capacity of Port Massawa.

Key Details

Project Details

  • P034154

  • Closed

  • Josphat Sasia

  • N/A

  • Eritrea

  • October 12, 1995

  • (as of board presentation)

    November 18, 1997

  • September 6, 1997

  • US$ 51.30 million

  • A

  • March 11, 2021

  • December 31, 2011

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 30.30
ITALY: MINSTRY OF FOREIGN AFFAIRS 21.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.30
IBRD + IDA Commitment 30.30
Lending Instrument
Grant Amount 21.00
Total Project Cost** 51.30

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 18, 1997 IDA-30050 Loan Commitment 30,300,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2011-09-24
Project Management Satisfactory 2011-09-24
Overall Implementation Progress (IP) Moderately Satisfactory 2011-09-24
Counterpart Funding Satisfactory 2011-09-24
Overall High 2011-09-24
Progress towards achievement of PDO Satisfactory 2011-09-24
Financial Management Satisfactory 2011-09-24
Monitoring and Evaluation Satisfactory 2011-09-24
Overall Safeguards Rating Satisfactory 2011-09-24

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-03-2013
OutcomesModerately Satisfactory
Risk to Development OutcomeHigh
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-09-2013PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Massawa Bulk Cargo tons/ship/dayValue8501100
    DateApril 30, 1997September 30, 2010December 31, 2011
    CommentNo ship docked during the quarter July-Sept 2010. No information is available after Sept. 2010.
  • Massawa Bagged CargoTons/ship/dayValue9001200
    DateApril 30, 1997September 30, 2010December 31, 2011
    CommentBelow end of project target because the equipment was not fully utilized arising from MPA#s inability to procure spare parts in atimely manner
  • Massawa Break-Bulk CargoTons/ship/dayValue260286
    DateApril 30, 1997March 31, 2010December 31, 2011
    CommentEnd of project target attained
  • Massawa Container CargoTEU/hourValue312
    DateApril 30, 1997September 30, 2010December 31, 2011
    CommentDecline arising from delays in procuring spare parts attributed to foreign exchange availability constraints
  • Massawa Berth Occupancy (%)Value70%67%
    DateApril 30, 1997March 31, 2010December 31, 2011
    CommentIncreased cargo destined for a number of projects underway
  • N/AValue
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Replace Shore Cranes(These cranes are critical to productivity: but are being procured through non-project bilateral trade arrangements following a misprocurement ruling)Value33
    DateApril 30, 1997October 8, 2008June 30, 2008
    CommentOriginally the Government of Netherlands was to provide 3 shore cranes thru bilateral arrangement; however this was scaled down to2). Therefore, it is 100%.Target achieved
  • Procure all other cargo handling equipment for Port MassawaValue0100%
    DateApril 30, 1997October 8, 2008June 30, 2008
    CommentCompleted
  • Complete Port Rehabilitation and Upgrade Works at Port MassawaValue0100%
    DateApril 30, 1997October 8, 2008June 30, 2008
    CommentCompleted
  • Complete improvement of Massawa causewaysValue0Two, Dahlak and Sigalet causeways
    DateDecember 7, 1999January 31, 2007January 31, 2007
    CommentCompleted
  • Repair old oil jetty at Hirgigo, MassawaValueOld oil jetty in a poor stateOld oil jetty repaired
    DateJune 15, 2006November 30, 2008November 30, 2008
    CommentCompleted
  • Construct a new oil jetty at Hirgigo, MassawaValue0New oil jetty constructed
    DateJune 15, 2006December 5, 2010December 31, 2011
    CommentNew oil jetty constructed to be constructed by Sept. 2012