The main objective of the Selingue Power Rehabilitation Project is to repair and rehabilitate the Selingue facility to ensure that the major source of electricity supply is not destroyed. Other objectives of the project are to: 1) maintain the electricity demand-supply balance by increasing the thermal capacity of the system and implementing an energy efficiency program; 2) improve the capacity of Energie du Mali (EDM) to properly operate, maintain...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

MAIN OBJECTIVE IS TO REPAIR AND REHABILITATE THE SELINGUE HYDRO POWERFACILITY. OTHER OBJECTIVES INCLUDE: (I) MAINTAIN ELECTICITY DEMAND/SUPPLY BALANCE; (II) IMPROVE EDM'S CAPACITY TO OPERATE AND MAINTAINITS POWER GENERATION FACILITIES; (III) PREPARE A LONG TERM INSTITUTIONAL AND REGULATORY FRAMEWORK FOR POWER SECTOR.

Key Details

Project Details

  • P034617

  • Closed

  • Kwawu Gaba

  • N/A

  • Mali

  • April 17, 1995

  • (as of board presentation)

    April 25, 1996

  • August 13, 1996

  • US$ 33.80 million

  • B

  • Not Applicable

  • June 30, 2002

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 27.30
EC: European Investment Bank 6.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 27.30
IBRD + IDA Commitment 27.30
Lending Instrument
Grant Amount 6.50
Total Project Cost** 42.10

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 25, 1996 IDA-28500 Loan Commitment 27,300,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-09-2003PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework