Skip to Main Navigation

ECONOMIC RECOVERY CR

Development Objective

CREDIT IS DESIGNED TO SUPPORT THE POST-DEVALUATION REFORM PROGRAM FOR 1994 WHOSE MAIN OBJECTIVES ARE PRIVATE SECTOR GROWTH AND THE ALLEVIA- TION OF POVERTY. THE BURKINABE GOVERNMENT HAS ALREADY TAKEN A SERIES OF KEY MACRO-ECONOMIC AND STRUCTURAL MEASURES TO REGAIN AND CONSO- LIDATE COMPETITIVENESS.

Key Details

Project Details

  • P035593

  • Closed

  • Hans-Martin Boehmer

  • N/A

  • Burkina Faso

  • March 29, 1994

  • (as of board presentation)

    March 29, 1994

  • June 24, 1994

  • US$ 49.80 million

  • N/A

  • Not Applicable

  • June 30, 1995

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 25.00
International Monetary Fund (IMF) 24.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 25.00
IBRD + IDA Commitment 25.00
Lending Instrument
Grant Amount 24.80
Total Project Cost** 25.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 29, 1994 IDA-25900 Loan Commitment 25,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-28-1996PROJECT PERFORMANCE ASSESSMENT REPORT: 02-08-2000
Outcome RatingHighly Satisfactory Satisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceNot RatedSatisfactory
Borrower PerformanceNot RatedSatisfactory
Government PerformanceSatisfactorySatisfactory
Implementing AgencyNot RatedNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityNot RatedNot Rated

Results Framework

No data available.