Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 7.90 |
Borrower/Recipient | 44.40 |
Inter-American Development Bank | 45.00 |
International Bank for Reconstruction and Development | 45.00 |
P035740
Closed
Arturo Ardila Gomez
N/A
October 17, 1995
(as of board presentation)
December 9, 2003
December 15, 2004
US$ 142.30 million
N/A
2004
US$ 97.90 million
B
March 11, 2021
April 30, 2011
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 7.90 |
Borrower/Recipient | 44.40 |
Inter-American Development Bank | 45.00 |
International Bank for Reconstruction and Development | 45.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 45.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 45.00 |
Lending Instrument | |
---|---|
Grant Amount | 52.90 |
Total Project Cost** | 142.30 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 1, 2014 | IBRD-72090 | Int Charges | 56,858.44 |
Nov 1, 2014 | IBRD-72090 | Loan Repay | 1,953,693.10 |
Dec 9, 2003 | IBRD-72090 | Loan Commitment | 45,000,000.00 |
Nov 1, 2013 | IBRD-72090 | Int Charges | 42.70 |
Nov 1, 2013 | IBRD-72090 | Int Charges | 82,477.90 |
Nov 1, 2013 | IBRD-72090 | Loan Repay | 2,154,455.80 |
May 1, 2014 | IBRD-72090 | Int Charges | 65,088.83 |
May 1, 2014 | IBRD-72090 | Loan Repay | 2,059,777.90 |
May 1, 2015 | IBRD-72090 | Int Charges | 51,215.47 |
May 1, 2015 | IBRD-72090 | Loan Repay | 1,849,181.00 |
May 1, 2016 | IBRD-72090 | Int Charges | 56,463.80 |
Nov 1, 2016 | IBRD-72090 | Int Charges | 72,396.84 |
Nov 1, 2016 | IBRD-72090 | Loan Repay | 1,538,524.20 |
May 1, 2016 | IBRD-72090 | Loan Repay | 1,643,774.80 |
Nov 1, 2015 | IBRD-72090 | Int Charges | 53,007.72 |
Nov 1, 2015 | IBRD-72090 | Loan Repay | 1,752,930.40 |
May 1, 2017 | IBRD-72090 | Int Charges | 81,829.93 |
May 1, 2017 | IBRD-72090 | Loan Repay | 1,433,868.60 |
Nov 1, 2017 | IBRD-72090 | Int Charges | 80,239.40 |
Nov 1, 2017 | IBRD-72090 | Loan Repay | 1,337,761.50 |
Nov 1, 2018 | IBRD-72090 | Int Charges | 95,911.54 |
Nov 1, 2018 | IBRD-72090 | Loan Repay | 1,127,164.60 |
May 1, 2018 | IBRD-72090 | Int Charges | 73,267.48 |
May 1, 2018 | IBRD-72090 | Loan Repay | 1,232,415.20 |
May 1, 2020 | IBRD-72090 | Int Charges | 40,521.07 |
May 1, 2020 | IBRD-72090 | Loan Repay | 817,246.40 |
Nov 1, 2019 | IBRD-72090 | Int Charges | 67,466.56 |
Nov 1, 2019 | IBRD-72090 | Loan Repay | 921,758.50 |
May 1, 2019 | IBRD-72090 | Int Charges | 86,599.98 |
May 1, 2019 | IBRD-72090 | Loan Repay | 1,031,934.70 |
Nov 1, 2020 | IBRD-72090 | Int Charges | 15,436.54 |
Nov 1, 2020 | IBRD-72090 | Loan Repay | 721,277.90 |
May 1, 2022 | IBRD-72090 | Int Charges | 2,271.84 |
May 1, 2022 | IBRD-72090 | Loan Repay | 415,859.56 |
Nov 1, 2021 | IBRD-72090 | Int Charges | 3,616.78 |
Nov 1, 2021 | IBRD-72090 | Loan Repay | 511,371.70 |
May 1, 2021 | IBRD-72090 | Loan Repay | 616,765.80 |
May 1, 2021 | IBRD-72090 | Int Charges | 5,309.30 |
May 1, 2023 | IBRD-72090 | Loan Repay | 200,762.73 |
May 1, 2023 | IBRD-72090 | Int Charges | 7,961.05 |
Nov 1, 2022 | IBRD-72090 | Int Charges | 6,559.08 |
Nov 1, 2022 | IBRD-72090 | Loan Repay | 305,418.34 |
Nov 1, 2023 | IBRD-72090 | Int Charges | 3,024.36 |
Nov 1, 2023 | IBRD-72090 | Loan Repay | 104,915.84 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Highly Satisfactory | 2011-05-20 |
Overall Implementation Progress (IP) | Satisfactory | 2011-05-20 |
Progress towards achievement of PDO | Satisfactory | 2011-05-20 |
Monitoring and Evaluation | Satisfactory | 2011-05-20 |
Procurement | Satisfactory | 2011-05-20 |
Project Management | Satisfactory | 2011-05-20 |
Financial Management | Moderately Satisfactory | 2011-05-20 |
Overall Safeguards Rating | Satisfactory | 2011-05-20 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-29-2012 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 06-28-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: 12-17-2015 |
---|---|---|
Outcome Rating | Moderately Satisfactory | Satisfactory |
Risk To Development Outcome | Moderate | Substantial |
Bank Performance | Moderately Satisfactory | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory | Moderately Satisfactory |
Government Performance | Moderately Satisfactory | Not Rated |
Implementing Agency | Moderately Satisfactory | Moderately Satisfactory |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | Substantial | Substantial |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of users satified with current transport service (general perception) | Value | 13.4% of users are satisfied with current transpor | According to a user survey, 82% of riders rate the | 60% of users of the new system are satisfied and c |
Date | April 29, 2005 | March 21, 2011 | April 30, 2011 | |
Comment | Data quality is improving but more robust data is needed for ICR. For example, other sources have reported that 68% of users ratethe Metropolitano as good or very good, still above the target value. |
Reduction in average travel times in traffic corridors intervened | Value | On average, it takes 120 minutes of travel time in | There has been a reduction of 34% in the travel ti | Travel time for users in traffic corridors interve |
Date | October 30, 2003 | April 28, 2011 | April 30, 2011 | |
Comment | Data quality is improving but more robust data is needed for ICR. |
Reduction of fatal and serious accidents in the main corridor of COSAC | Value | On average, there were 26 fatal or serious acciden | Fatal and serious accidents in the main corridor o | Fatal and serious accidents in the main corridor o |
Date | October 30, 2003 | April 27, 2011 | April 30, 2011 | |
Comment |
Reduction in air pollution emissions from the transport sector in El Metropolitano corridor | Value | Air pollution caused by the transport sector in El | Green House Gas (GHG) Emissions caused by the tran | Air pollution caused by the transport sector in El |
Date | October 30, 2003 | April 26, 2011 | April 30, 2011 | |
Comment | More robust data is needed as well as the estimation of reduction in air pollution. It is important to point out that about 11% ofMetropolitano riders would use private car or taxi in the without project scenario. |
Consolidated Lima Urban Transport Sector by improving planning, supervision and control, and management capacity of the participating institutions | Value | There was a lack of urban traffic and transport st | Protransporte's capacity to manage and operate the | There is a strategic plan to increase coverage of |
Date | October 30, 2003 | April 26, 2011 | April 30, 2011 | |
Comment |
% of low-income population benefited by the project, specially the low income population living in the peri-urban areas | Value | There is no formal transport system in place | A survey showed that 46.8% of users of the Metropo | 10% of low income population will benefit from the |
Date | October 30, 2003 | April 26, 2011 | April 30, 2011 | |
Comment | More robust data is need for ICR |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of kms of high capacity bus corridors completed | Value | High capacity bus corridors do not exist | 100% of high capacity bus corridors have been comp | 29.4 km of high capacity bus corridors completed |
Date | October 30, 2003 | April 28, 2011 | April 30, 2011 | |
Comment | Number of Km is 27 because the terminal in the south, Matellini, was reallocated for environmental reasons. It was originallyplanned to build the terminal over a swamp, where migratory ducks arrive during winter in the nothern hemisphere. |
Number of bus-stops and terminals completed | Value | Bus-stops and terminals do not exist | All stations and terminals have been completed. | 35 bus stops and North and South terminals in oper |
Date | October 30, 2003 | April 28, 2011 | April 30, 2011 | |
Comment |
Number of passengers using the new system | Value | There are no passengers using the BRT system since | 340,000 per weekday | 600,000 passengers on a typical weekday |
Date | October 30, 2003 | April 26, 2011 | April 30, 2011 | |
Comment | 304,000 ppd is with only 176 of the 312 trunk buses and 159 of the 232 feeder buses operating . Once the entire trunk fleet andallfeeder buses are operating it is expected to reach the 600,000 ppd. We estimate this goal will be reached on December 2011 forfourreasons: (i) The new administration has publicly committed to remove the traditional buses on parallel routes to theMetropolitano(about 40 routes); (ii) a new fare policy will create incentives for the feeder-trunk trips. Currently only 10% of thefeeder tripstransfer to the trunk corridor; (iii) Protransporte will implement by July 2011 a new route design to improve thequality of service; and (iv) currently demand is naturally increasing every month at a rate of 2% in the trunk corridor and 10% inthe feeder corridors |
Operation of high capacity buses: through buses, fare collection and control system in place | Value | Unplanned and unregulated route system in operatio | 176 articulated buses, out of 312 are operating an | Whole system covered by the Project in operation a |
Date | October 30, 2003 | April 26, 2011 | April 30, 2011 | |
Comment | The operation of the full fleet is related with the demand increase. See previous indicator and the measures taken to reach thetargeted demand. |
Recovery and improvement of public spaces and green areas | Value | There are no areas of recovery and improvement of | About 50,000 square meter of public space recovere | 100,000 square meters of public space recuperated |
Date | October 30, 2003 | April 28, 2011 | April 30, 2011 | |
Comment | Date needs to be refined for ICR. |
Air quality monitoring and report system in place | Value | Monitoring of air quality do not exist | There are 16 reports per month. The implementation | Monitoring results available in Annual report to |
Date | October 30, 2003 | April 28, 2011 | April 30, 2011 | |
Comment |
Institutional strengthening of municipal transport agencies | Value | No member of municipal staff has been trained in u | 58 members of the MML have been trained. | At least 50 municipal staff trained in urban tran |
Date | October 30, 2003 | April 26, 2011 | April 30, 2011 | |
Comment | Team obtained a $40,000 capacity building grant that will help train more staff. |
Social Impact Mitigation | Value | 5,942 worker from public transport were estimated | Thanks to careful studies to reorganize the old op | At least 2,500 affected workers from public transp |
Date | October 30, 2003 | January 12, 2011 | April 30, 2011 | |
Comment |
At least one concessionaire for the high-capacity segregated busways has offered buses for scrapping | Value | |||
Date | March 26, 2009 | April 16, 2010 | June 30, 2010 | |
Comment | Not yet achieved (achievement still possible). |
At least 250 aged and polluting public transport vehicles retired through PROTRANSPORTE's owns scrapping scheme | Value | |||
Date | March 26, 2009 | April 16, 2010 | June 30, 2010 | |
Comment | Not yet achieved (achievement still possible). |
At least 250 of displaced bus operators by the first BRT system in Lima have been retrained / received technical and economic support to opt for new employments or new business outside the sector | Value | |||
Date | March 26, 2009 | April 16, 2010 | June 30, 2010 | |
Comment | Not yet achieved (achievement still possible). |
32.5 km of bikeways rehabilitated 27.5 km of bikeways rehabilitated with project funds | Value | |||
Date | January 1, 2005 | April 16, 2010 | April 30, 2011 | |
Comment | Fully achieved. |
6.1 Kms of bikeways extension to connect Lima's two main universities | Value | |||
Date | January 1, 2005 | April 16, 2010 | June 30, 2010 | |
Comment | Fully achieved. |
At least 3,000 people (local auth., civil servants, community leaders, civil society, general pop.) informed about sustainable transport options and their effect on air quality, GHG & environment | Value | |||
Date | January 1, 2005 | April 16, 2010 | June 30, 2010 | |
Comment | Fully achieved. |
5 provincial and 38 district municipalities as well as FONAM have benefited from institutional strengthening programs | Value | |||
Date | January 1, 2005 | April 16, 2010 | June 30, 2010 | |
Comment | Fully achieved. |
Doubling of the number of bicycle trips in the Project financed bikeway in comparison to the base line | Value | |||
Date | January 1, 2005 | April 16, 2010 | June 30, 2010 | |
Comment | Only partially achieved. |
Study to consolidate the integrated public transport system in Metropolitan Lima considered satisfactory by PROTRANSPORTE/Bank | Value | |||
Date | March 26, 2009 | April 16, 2010 | June 30, 2010 | |
Comment | Study still ongoing. |
3 staff of PROTRANSPORTE trained in areas related to public transport integration (participation in the study and formal training through the study) | Value | |||
Date | March 26, 2009 | April 16, 2010 | April 30, 2011 | |
Comment | Fully achieved. |