Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 32.00 |
P035997
Closed
Mohammed D. E. Feghoul
N/A
May 6, 1996
(as of board presentation)
July 31, 1997
October 17, 1997
US$ 44.00 million
N/A
1998
US$ 32.00 million
B
Not Applicable
June 30, 2005
BANK APPROVED
May 10, 2016
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 32.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 32.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 32.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 44.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2014 | IBRD-42140 | Int Charges | 4,168.63 |
Feb 15, 2014 | IBRD-42140 | Loan Repay | 1,486,100.00 |
Feb 15, 2014 | IBRD-42140 | Int Charges | 9,420.44 |
Aug 15, 2013 | IBRD-42140 | Loan Repay | 1,446,500.00 |
Aug 15, 2013 | IBRD-42140 | Int Charges | 14,826.39 |
Aug 15, 2014 | IBRD-42140 | Loan Repay | 1,535,418.90 |
Jul 31, 1997 | IBRD-42140 | Loan Commitment | 32,000,000.00 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2005-12-26 |
Counterpart Funding | Satisfactory | 2005-12-26 |
Procurement | Satisfactory | 2005-12-26 |
Progress towards achievement of PDO | Satisfactory | 2005-12-26 |
Project Management | Satisfactory | 2005-12-26 |
Financial Management | Satisfactory | 2005-12-26 |
Monitoring and Evaluation | Satisfactory | 2005-12-26 |
Overall Implementation Progress (IP) | Satisfactory | 2005-12-26 |
INDICATOR | ICR REVIEW: 03-14-2006 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Exemplary | N/a |
M&e Quality | Not Rated | N/a |