Skip to Main Navigation

BJ-GEF Nat Parks Cnsv & Mgmt SIL (FY00)

Abstract*

The National Parks Conservation and Management Program Project, will ensure sustainable management, and conservation of regional, and global bio-diversity in Benin, including fragile ecosystems in the northern areas. It will specifically, establish sustainable wildlife management, and bio-diversity conservation capacity, at both national, and local levels. The components are: 1) to provide program management, through planning and monitoring at the...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The overall objective of the Program is to ensure the sustainable management of and conservation of regionally and globally important biodiversity, and globally fragile ecosystems in northern Benin, while improving the living conditions of local communtities through the establishment of effective co-management schemes. This objective is pursued through eight intermediate operational objectives, as described below.i) Develop the technical and managerial capacity of the local population , the Wildlife Reserves Management Center (CENAGREF), and other partners in protected area and wildlife management.(ii) Promote and support the participation of local populations in wildlife and park management and benefits sharing.(iii) Support community-based rural development activities in areas surrounding national parks and wildlife management areas, in order to improve the quality of life, and reduce the pressure on protected areas.(iv) Develop sustainable systems of natural resource management.(v) Improve the flow of information and support education on biodiversity conservation at both local and national levels.(vi) Develop ecological monitoring systems and support research related to wildlife and biodiversity management.(vii) Improve basic infrastructure within parks.(viii) Help create an international trust fund intended to finance future wildlife management and biodiversity conservation operations.

Key Details

Project Details

  • P037580

  • Closed

  • Remi Kini

  • N/A

  • Benin

  • November 16, 1999

  • (as of board presentation)

    March 30, 2000

  • July 6, 2000

  • US$ 21.06 million

  • B

  • Not Applicable

  • December 31, 2005

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
GERMANY: Deutsche Entwicklungsgesellschaft (DEG) 1.90
Borrower/Recipient 3.18
GERMANY: German Technical Assistance Corporation (GTZ) 7.80
Global Environment Facility (GEF) 6.76
FRANCE: French Agency for Development 0.70
EC: NON-ASSOCIATED COUNTRY PROGRAM 3.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 21.06
Total Project Cost** 24.24

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2005-12-21
Counterpart Funding Satisfactory 2005-12-21
Overall Implementation Progress (IP) Satisfactory 2005-12-21
Summary Global Objective Rating Satisfactory 2005-12-21
Project Management Moderately Satisfactory 2005-12-21
Financial Management Satisfactory 2005-12-21
Overall Safeguards Rating Moderately Satisfactory 2005-12-21
Procurement Moderately Satisfactory 2005-12-21

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-27-2006PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.