ODS Phaseout 2 Project under Montreal Protocol

Development Objective

Assist ODS-using industries in Turkey to effectively and efficiently phase-out ODS use through the adoption of appropriate non-ODS technologies and related measures. The phase-out is to be implemented in compliance with the Montreal Protocol, as ratified by the Republic of Turkey, and in accordance with the recommended ODS phase-out strategy and Action Plan that has been outlined in the Country Program and National Ozone Policy. The Project consists of three components:(i) ,,To develop and implement policy and regulatory frameworks for ODS phase-out.(ii),,To support ODS phase-out investment projects.(iii),,To develop public and industry awareness of ODS phase-out.

Key Details

Project Details

  • P038404

  • Closed

  • Varadarajan Atur

  • N/A

  • Turkiye

  • June 1, 1995

  • (as of board presentation)

    October 5, 1995

  • December 11, 1995

  • US$ 2.80 million

  • C

  • Not Applicable

  • December 31, 2007

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Montreal Protocol Investment Fund 2.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.80
Total Project Cost** 24.50

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2007-12-20
Summary Global Objective Rating Satisfactory 2007-12-20
Counterpart Funding Highly Satisfactory 2007-12-20
Monitoring and Evaluation Satisfactory 2007-12-20
Overall Implementation Progress (IP) Highly Satisfactory 2007-12-20
Overall Safeguards Rating Satisfactory 2007-12-20
Procurement Highly Satisfactory 2007-12-20
Financial Management Satisfactory 2007-12-20

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2008
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceHighly Satisfactory
Borrower PerformanceHighly Satisfactory
Government PerformanceHighly Satisfactory
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-05-2008PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceHighly SatisfactoryN/a
Borrower PerformanceHighly SatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencyHighly SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework