Financier | Commitments |
---|---|
Montreal Protocol Investment Fund | 2.80 |
P038404
Closed
Varadarajan Atur
N/A
June 1, 1995
(as of board presentation)
October 5, 1995
December 11, 1995
US$ 24.50 million
N/A
1996
US$ 2.80 million
C
Not Applicable
December 31, 2007
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Montreal Protocol Investment Fund | 2.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.80 |
Total Project Cost** | 24.50 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2007-12-20 |
Summary Global Objective Rating | Satisfactory | 2007-12-20 |
Counterpart Funding | Highly Satisfactory | 2007-12-20 |
Monitoring and Evaluation | Satisfactory | 2007-12-20 |
Overall Implementation Progress (IP) | Highly Satisfactory | 2007-12-20 |
Overall Safeguards Rating | Satisfactory | 2007-12-20 |
Procurement | Highly Satisfactory | 2007-12-20 |
Financial Management | Satisfactory | 2007-12-20 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2008 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Highly Satisfactory |
Borrower Performance | Highly Satisfactory |
Government Performance | Highly Satisfactory |
Implementing Agency | Highly Satisfactory |
INDICATOR | ICR REVIEW: 09-05-2008 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Highly Satisfactory | N/a |
Borrower Performance | Highly Satisfactory | N/a |
Government Performance | Highly Satisfactory | N/a |
Implementing Agency | Highly Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |