Skip to Main Navigation

Istria Water Supply & Sewerage Project

Development Objective

THE PROJECT WOULD ELINIMATE WATER SHORTAGES AND POLLUTION THREATENING TOURISM DEV'T. AN IMPORTANT FOREIGN EXCHANGE EARNER. THE PROJECT INCLUDES WATER TREATMENT, TRANSMISSION, EQUIPMENT AND SEWERAGE WORKS.

Key Details

Project Details

  • P039002

  • Closed

  • Manuel G. Marino

  • N/A

  • Croatia

  • May 23, 1989

  • (as of board presentation)

    May 23, 1989

  • May 31, 1990

  • US$ 0.00 million

  • C

  • Not Applicable

  • June 30, 2000

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** 148.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 23, 1989 IBRD-30690 Loan Commitment 28,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-30-2001PROJECT PERFORMANCE ASSESSMENT REPORT: 12-10-2003
Outcome RatingUnsatisfactory Moderately Satisfactory
Risk To Development OutcomeNot RatedNot Rated
Bank PerformanceSatisfactorySatisfactory
Borrower PerformanceSatisfactorySatisfactory
Government PerformanceSatisfactorySatisfactory
Implementing AgencySatisfactoryNot Rated
Icr QualitySatisfactoryNot Rated
M&e QualityNot RatedNot Rated

Results Framework

No data available.