The Low Income Sanitation Technical Assistance Project, aims at achieving integrated, and demand-driven water supply, and sanitation services delivery to the urban poor, within the participating local government agencies. The project components call for: 1) Project management, promotion, and studies, to strengthen project coordination capacity, and administration within the Federal Government, and improve the wellbeing of targeted populations in the...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To achieve integrated and demand-driven water supply and sanitation (WSS) service delivery within participating local government agencies under the framework of the PROSANEAR national low-income sanitation program.

Key Details

Project Details

  • P039199

  • Closed

  • Martin Gambrill

  • N/A

  • Brazil

  • March 13, 1998

  • (as of board presentation)

    January 6, 2000

  • December 19, 2000

  • US$ 30.30 million

  • B

  • Not Applicable

  • December 15, 2007

  • BANK APPROVED

  • May 1, 2015

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 17.00
International Bank for Reconstruction and Development 30.30

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 30.30
IDA Commitment N/A
IBRD + IDA Commitment 30.30
Lending Instrument
Grant Amount N/A
Total Project Cost** 47.30

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2014 IBRD-45320 Loan Repay 2,425.75
May 15, 2015 IBRD-45320 Int Charges 393.77
May 15, 2015 IBRD-45320 Loan Repay 30,512.35
May 15, 2014 IBRD-45320 Loan Repay 653,599.56
May 15, 2014 IBRD-45320 Int Charges 95.10
May 15, 2014 IBRD-45320 Loan Repay 2,455.00
May 15, 2014 IBRD-45320 Int Charges 16,608.51
Nov 15, 2013 IBRD-45320 Int Charges 15,961.50
Nov 15, 2013 IBRD-45320 Int Charges 9,235.70
Nov 15, 2013 IBRD-45320 Loan Repay 650,464.94
Jan 6, 2000 IBRD-45320 Loan Commitment 30,300,000.00
Nov 15, 2014 IBRD-45320 Int Charges 7,585.84
Nov 15, 2014 IBRD-45320 Loan Repay 585,386.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2007-12-05
Monitoring and Evaluation Satisfactory 2007-12-05
Progress towards achievement of PDO Satisfactory 2007-12-05
Procurement Satisfactory 2007-12-05
Overall Implementation Progress (IP) Moderately Satisfactory 2007-12-05
Project Management Moderately Unsatisfactory 2007-12-05
Financial Management Moderately Unsatisfactory 2007-12-05
Overall Safeguards Rating Satisfactory 2007-12-05

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-16-2008
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-29-2008PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

No data available.