Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 60.70 |
P040174
Closed
Taimur Samad
N/A
August 10, 1998
(as of board presentation)
October 22, 1998
December 21, 1999
US$ 152.90 million
N/A
1999
US$ 60.70 million
B
January 15, 2013
June 30, 2006
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 60.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 60.70 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 60.70 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 152.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 22, 1998 | IBRD-44000 | Loan Commitment | 60,700,000.00 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2006-05-16 |
Progress towards achievement of PDO | Satisfactory | 2006-05-16 |
Procurement | Satisfactory | 2006-05-16 |
Counterpart Funding | Moderately Satisfactory | 2006-05-16 |
Project Management | Satisfactory | 2006-05-16 |
Financial Management | Satisfactory | 2006-05-16 |
Monitoring and Evaluation | Satisfactory | 2006-05-16 |
Overall Implementation Progress (IP) | Satisfactory | 2006-05-16 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-30-2007 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 06-20-2007 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |