Abstract*

The Caracas Slum-Upgrading Project aims to improve quality of life for the inhabitants of a selected number of barrios in Caracas, Venezuela, by developing and implementing a community-driven, sustainable, and replicable infrastructure improvement program. The project has three components. The first, urban upgrading, finances the design and execution of Communities Neighborhood Improvement Plans (NIP) and includes designing and executing pedestrian...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to improve the quality of life of the inhabitants of a selected number of barrios (representing 15 percent of total barrio population) in the Metropolitan Area of Caracas (MAC), through the development and implementation of a community driven, sustainable and replicable infrastructure improvement program.The objective remains unchanged, although with the partial loan cancellation the number of direct beneficiaries is 40% of what was originally projected.

Key Details

Project Details

  • P040174

  • Closed

  • Taimur Samad

  • N/A

  • US$ 60.70 million

  • B

  • January 15, 2013

  • June 30, 2006

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 60.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 60.70
IDA Commitment N/A
IBRD + IDA Commitment 60.70
Lending Instrument
Grant Amount N/A
Total Project Cost** 152.90

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 22, 1998 IBRD-44000 Loan Commitment 60,700,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2006-05-16
Progress towards achievement of PDO Satisfactory 2006-05-16
Procurement Satisfactory 2006-05-16
Counterpart Funding Moderately Satisfactory 2006-05-16
Project Management Satisfactory 2006-05-16
Financial Management Satisfactory 2006-05-16
Monitoring and Evaluation Satisfactory 2006-05-16
Overall Implementation Progress (IP) Satisfactory 2006-05-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-30-2007
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-20-2007PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework