The Second Beijing Environment Project aims at a visible and sustained alleviation of air and water pollution in Beijing. The project consists of nine components: 1) The first component will support the conversion of medium-sized heating boilers from coal to natural gas. 2) The Gas Boiler Market and Technology Development component will support activities to develop industry-wide technical capacity, remove market information gaps, facilitate and aggregate...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Visible and sustained alleviation of air and water pollution in Beijing by helping to: a) convert scattered coal-fired boilers to natural gas boilers; b) promote energy conservation in heating systems; c) construct key wastewater trunk interceptors and associated treatment facilities, and (d) strengthen environmental management institutions of Beijing.

Key Details

Project Details

  • P042109

  • Closed

  • Chongwu Sun

  • N/A

  • China

  • December 21, 1998

  • (as of board presentation)

    June 20, 2000

  • May 11, 2001

  • US$ 374.00 million

  • A

  • Not Applicable

  • January 31, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 349.00
Foreign Private Commercial Sources (unidentified) 182.50
Global Environment Facility (GEF) 25.00
Local Govts. (Prov., District, City) of Borrowing Country 186.00
Local Beneficiaries 355.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 349.00
IDA Commitment N/A
IBRD + IDA Commitment 349.00
Lending Instrument
Grant Amount 25.00
Total Project Cost** 1255.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 15, 2014 IBRD-45660 Loan Repay 11,011,078.00
Feb 15, 2014 IBRD-45660 Int Charges 627,978.80
Feb 15, 2014 IBRD-45660 Loan Repay 10,652,678.00
Aug 15, 2013 IBRD-45660 Int Charges 701,350.70
Aug 15, 2020 IBRD-45660 Int Charges 179,670.20
Jun 20, 2000 IBRD-45660 Loan Commitment 349,000,000.00
Aug 15, 2013 IBRD-45660 Loan Repay 10,312,346.00
Aug 15, 2020 IBRD-45660 Loan Repay 16,302,367.00
Feb 15, 2020 IBRD-45660 Loan Repay 15,783,921.00
Feb 15, 2020 IBRD-45660 Int Charges 411,631.44
Aug 15, 2019 IBRD-45660 Int Charges 769,146.25
Aug 15, 2019 IBRD-45660 Loan Repay 15,275,743.00
Feb 15, 2019 IBRD-45660 Int Charges 946,581.00
Feb 15, 2019 IBRD-45660 Loan Repay 14,785,831.00
Aug 15, 2018 IBRD-45660 Int Charges 964,869.94
Aug 15, 2018 IBRD-45660 Loan Repay 14,309,445.00
Feb 15, 2018 IBRD-45660 Int Charges 876,952.10
Feb 15, 2018 IBRD-45660 Loan Repay 13,846,684.00
Aug 15, 2017 IBRD-45660 Loan Repay 13,401,992.00
Aug 15, 2017 IBRD-45660 Int Charges 922,896.80
Aug 15, 2016 IBRD-45660 Int Charges 797,009.56
Aug 15, 2016 IBRD-45660 Loan Repay 12,549,039.00
Feb 15, 2017 IBRD-45660 Int Charges 954,121.50
Feb 15, 2017 IBRD-45660 Loan Repay 12,966,481.00
Feb 15, 2016 IBRD-45660 Int Charges 621,385.75
Feb 15, 2016 IBRD-45660 Loan Repay 12,145,321.00
Aug 15, 2015 IBRD-45660 Loan Repay 11,755,128.00
Aug 15, 2015 IBRD-45660 Int Charges 538,904.20
Feb 15, 2015 IBRD-45660 Int Charges 521,269.47
Feb 15, 2015 IBRD-45660 Loan Repay 11,374,020.00
Aug 15, 2014 IBRD-45660 Int Charges 520,622.12

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2010-06-27
Counterpart Funding Satisfactory 2010-06-27
Project Management Satisfactory 2010-06-27
Procurement Satisfactory 2010-06-27
Overall Safeguards Rating Satisfactory 2010-06-27
Progress towards achievement of PDO Satisfactory 2010-06-27
Financial Management Satisfactory 2010-06-27
Monitoring and Evaluation Satisfactory 2010-06-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-06-2011
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-18-2013PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Ambient concentration of major pollutantsValueSO2: 120ug/m3SO2: 47ug/m360UG/M3
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment Ambient concentrations are now below EOP target.
  • Concentration of major pollutants downstream of Xiaohongmen WWTP (COD, OD, NH3-N) and rate of wastewater treatment in Liangshuihe RiverValueCOD: 236.67 mg/lBOD: 88.89 mg/lWastewater treatmeCOD: 81.79 mg/l; BOD: 19.5 mg/l; Wastewater treaTo meet Class V water quality standradTreatment Ra
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment The COD and BOD concentrations are both below specified discharge standards.
  • Number of days a year with air quality worse than Class II in BeijingValue188110 days120
    DateDecember 31, 2000December 31, 2009December 31, 2009
    Comment This achievement exceeded the EOP target.
  • Carbon dioxide released from heating systemsValueMetric tons of CO2 equivalent507 t/aTo be calulated
    DateDecember 31, 1998December 31, 2008March 31, 2009
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Coal consumption for heatingValue2.403 million t/a4.1 million t/a5 million t/a
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment With rapid city expansion and fast housing development in Beijing, absolute coal consumption for heating has increased comparedwith the baseline. Also the num ber above, 4.1 million t/a, is the informationfor the whole city, as it is diff icult to ascertain the percentage for the citycenter where the project is locat ed. (Note: This indicator is not withincontrol of the project.)
  • Costs of gas boilers, services, and operationsValue100 (index)8070
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment
  • Emissions from heating boilersValueDust: 6,780 t/a SO2: 15,170 t/a
    DateDecember 31, 2009
    Comment
  • Quality and timeliness of air quality data and analysis, regulatory responsesValue8 automatic air quality monitoring stations, doingBeijing has 27 automatic stations responsible for Summary and analysis available for regulation, pla
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment The monitoring stations are functioning well and are providing AQ information to the public on a daily basis.
  • Treated wastewater volume and quality in Liangshui RiverValuezero>Class V water quality standardVolume: 285 million m3/a;Quality: COD: 120 mg/880,000 m3/dTo meet Class V water quality standard
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment According to the baseline information, wastewater capacity in Liangshuihe River was zero and water quality of the river was worsethan Class V. Now after instal lation of project investments, wastewatertreatment capacity is sufficient for t he river basin.
  • Cost per wastewater collected and treated, operating cash flowValueno data0.9 Yuan RMB/ton (unit cost for treatment, 0.99 yunot projected
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment The wastewater tariff has been increased periodically during project implementaion. According to BDG, current level is sufficientto cover their operations.
  • Number and capacity of natural gas boilers installedValuezero10,877 sets; 16,717 MW heat supply space: 152,662000 boilers below 20tn/h
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment This is the current capacity of natural gas boilers installed, compared to the baseline of zero at Board approval.
  • MIS and GIS systems installed and staff trained for BDGValuezeroMIS and GIS systems installation is finished, stafThe system in operation
    DateDecember 31, 1998December 31, 2009March 31, 2009
    Comment Since installment and operation of MIS and GIS system in BDG, management of WWTPs and other facilities is more effective.
  • Length of sewers and capacity of sewage treatment installed in Liangshui RiverValuezeroAbout 46 km interceptors built in Liangshuihe RiveTo support full operation of WWTP
    DateJune 30, 2000December 31, 2009March 31, 2009
    Comment Loan funded 46 km interceptors together with sewer network funded by counterpart which together support full operation of WWTPs inLiangshuihe River.
  • Length of interceptors built in Liangshui River and Qinghe RiverValuezero26.4 km in Qinghe River and 46 km in Liangshuihe RTo support full operation of WWTP connected
    DateJune 30, 2000December 31, 2009March 31, 2009
    Comment The designed targets are fully met. Loan-funded interceptors together with sewer network funded by counterpart fully supportoperation of the WWTPs in the Liang shuihe and Qinghe Rivers.
  • Staff-months of studies and training; equipment procuredValuezero100 staff trained for BDG; 5 man-months training 100 staff to be trained
    DateJune 30, 2000December 31, 2009March 31, 2009
    Comment
  • Coal consumption for heatingValue2.403 million t/a4.075 million t/a5 million t/a
    DateDecember 31, 1998December 31, 2007March 31, 2009
    Comment
  • Costs of gas boilers, services, and operationsValue100 (index)8070
    DateDecember 31, 1998December 31, 2008March 31, 2009
    Comment
  • Emissions from heating boilersValueDust: 7200 t/aSO2: 21,634 t/aDust: 6780 t/aSO2: 15170 t/aDust: SO2: 108 t/a
    DateDecember 31, 1998December 31, 2007March 31, 2009
    Comment
  • Quality and timeliness of air quality data and analysis, regulatory responsesValue8 automatic air quality monitoring stations, doing27 automatic stations responsible for AQ infomatioSummary and analysis available for regulation, pla
    DateDecember 31, 1998December 31, 2008March 31, 2009
    Comment
  • Treated wastewater volume and quality in Liangshui RiverValuezeroVolume: 284.70 million m3/aQuality: COD: 120 mFinal achievement is same as 'progress to date'
    DateDecember 31, 1998December 31, 2008March 31, 2009
    Comment
  • Cost per wastewater collected and treated, operating cash flowValueno data0.9 Yuan RMB/ton (unit cost for treatment, 0.9834 Final achievement is same as 'progress to date'
    DateDecember 31, 1998December 31, 2008March 31, 2009
    Comment
  • Number and capacity of natural gas boilers installedValuezero10877 sets;16717 MW heat supply space 152,660,00Final achievement is same as 'progress to date'
    DateDecember 31, 1998December 31, 2008March 31, 2009
    Comment
  • MIS and GIS systems installed and staff trained for BDGValuezeroMIS and GIS systems installation finished and dataSet up complete MIS and GIS to provide support in
    DateDecember 31, 1998December 31, 2008March 31, 2009
    Comment
  • Length of sewers and capacity of sewage treatment installed in Liangshui RiverValuezero46.344 km in Liangshuihe River 780,000 m3/d in LiWorks completed; Final achievement is same as prog
    DateJune 30, 2000December 31, 2008March 31, 2009
    Comment
  • Length of interceptors built in Liangshui River and Qinghe RiverValuezero26.409 km in Qinghe River and 46.344 km in LiangshFinal achievement is same as progress to date
    DateJune 30, 2000December 31, 2007March 31, 2009
    Comment
  • Staff-months of studies and training; equipment procuredValuezero140 staff trained for BDG;5.73 man-months traininfinal achievement is same as progress to date
    DateJune 30, 2000December 31, 2007March 31, 2009
    Comment
  • Ambient concentration of major pollutantsValue265.000.00120.00
    DateDecember 31, 1999December 31, 2009
    Comment Because there was no agreement with the borrower about which parameters should be used as indicators, no baseline was establishedand no data was collected duri ng implementation on this particular indicator.