Skip to Main Navigation

MA-RAILWAY RESTR & PRIV

Abstract*

The main objective of the Railway Restructuring Project is to support the preparation and implementation of a restructuring program that will lead to an efficient commercially oriented railway operation. The project will also contribute to financing the railway's rehabilitation and modernization program. The main components of the project are: a) an investment program for the rehabilitation and modernization of rail infrastructure and equipment concentrating...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The main objective of the project is to suppor t the preparation and implementation of a restructuring program that would lead to an efficient, commercially -oriented railway operation. The project will also contribute to financing the railway's rehabilitation and modernization program, consisting primarily of: (a) the rehabilitation of track and of electric traction faci lities (catenary, substations) on selected sections of the network; (b) the improvement of signaling and tele communication systems; (c) investment in rolling stock (acquisition of nine electric locomotives, and 100 spe cialized wagons); (d) studies and consulting services to prepare and implement the restructuring program, pre pare and implement the reform of the railway pension system, and to support the improvement of railway manage ment systems; and (e) a program of acquisition of computer equipment needed for the implementation of new management systems.

Key Details

Project Details

  • P043725

  • Closed

  • Michel Bellier

  • N/A

  • Morocco

  • February 5, 1996

  • (as of board presentation)

    December 19, 1996

  • July 22, 1997

  • US$ 254.60 million

  • B

  • Not Applicable

  • November 30, 2004

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
African Development Bank 82.60
EC: European Investment Bank 87.00
International Bank for Reconstruction and Development 85.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 85.00
IDA Commitment N/A
IBRD + IDA Commitment 85.00
Lending Instrument
Grant Amount 169.60
Total Project Cost** 521.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2016 IBRD-41281 Loan Repay 1,125,727.90
Nov 15, 2014 IBRD-41281 Loan Repay 1,107,425.10
Nov 15, 2014 IBRD-41280 Int Charges 3,358.53
Nov 15, 2014 IBRD-41280 Loan Repay 233,000.00
Nov 15, 2014 IBRD-41281 Int Charges 18,287.95
Nov 15, 2015 IBRD-41280 Int Charges 2,665.46
Nov 15, 2015 IBRD-41280 Loan Repay 247,400.00
Nov 15, 2015 IBRD-41281 Int Charges 5,257.05
Nov 15, 2015 IBRD-41281 Loan Repay 1,032,363.50
May 15, 2015 IBRD-41280 Int Charges 2,885.33
May 15, 2015 IBRD-41280 Loan Repay 239,900.00
May 15, 2015 IBRD-41281 Int Charges 8,690.98
May 15, 2015 IBRD-41281 Loan Repay 1,048,236.80
May 15, 2014 IBRD-41280 Int Charges 4,201.34
May 15, 2014 IBRD-41280 Loan Repay 226,200.00
May 15, 2014 IBRD-41281 Int Charges 44.28
May 15, 2014 IBRD-41281 Int Charges 18,233.86
May 15, 2014 IBRD-41281 Loan Repay 1,172,002.60
Nov 15, 2013 IBRD-41280 Int Charges 5,428.61
Nov 15, 2013 IBRD-41280 Loan Repay 219,900.00
Nov 18, 2013 IBRD-41281 Int Charges 17,888.93
Nov 18, 2013 IBRD-41281 Loan Repay 1,117,977.60
Nov 15, 2016 IBRD-41280 Int Charges 1,650.60
Nov 15, 2016 IBRD-41280 Loan Repay 264,709.50
Nov 15, 2016 IBRD-41281 Int Charges 850.11
Nov 15, 2016 IBRD-41281 Loan Repay 1,108,859.80
May 15, 2016 IBRD-41280 Int Charges 2,337.49
May 15, 2016 IBRD-41280 Loan Repay 254,800.00
May 15, 2016 IBRD-41281 Int Charges 3,131.77
Dec 19, 1996 IBRD-41280 Loan Commitment 42,500,000.00
Dec 19, 1996 IBRD-41281 Loan Commitment 42,500,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Not Applicable 2005-05-05
Procurement Satisfactory 2005-05-05
Counterpart Funding Highly Satisfactory 2005-05-05
Financial Management Satisfactory 2005-05-05
Overall Implementation Progress (IP) Satisfactory 2005-05-05
Progress towards achievement of PDO Satisfactory 2005-05-05
Project Management Satisfactory 2005-05-05
Monitoring and Evaluation Highly Satisfactory 2005-05-05

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-29-2005PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceHighly SatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.