Skip to Main Navigation

BUREAU OF ECON POL

Development Objective

THE PROJECT WILL FINANCE THREE COMPONENTS: (I) POLICY STUDIES; (II)BUREAU OF ECONOMIC ANALYSIS; AND (III) IMPROVEMENT OF NATIONALACCOUNTS.

Key Details

Project Details

  • P044200

  • Closed

  • Vladimir Drebentsov

  • N/A

  • Russian Federation

  • March 27, 1996

  • (as of board presentation)

    June 5, 1997

  • December 18, 1997

  • US$ 22.60 million

  • C

  • Not Applicable

  • March 31, 2005

  • BANK APPROVED

  • February 26, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 22.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 22.60
IDA Commitment N/A
IBRD + IDA Commitment 22.60
Lending Instrument
Grant Amount N/A
Total Project Cost** 36.80

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 15, 2014 IBRD-41850 Int Charges 2,855.08
Mar 15, 2014 IBRD-41850 Loan Repay 959,624.70
Jun 5, 1997 IBRD-41850 Loan Commitment 22,600,000.00
Sep 15, 2013 IBRD-41850 Int Charges 6,166.62
Sep 15, 2013 IBRD-41850 Loan Repay 922,700.00
Mar 15, 2014 IBRD-41850 Loan Repay 2,855.08

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT:
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-14-2005PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNot RatedN/a

Results Framework

No data available.