Financier | Commitments |
---|---|
IDA Credit | 191.00 |
P045051
Closed
Mariam Claeson
N/A
June 15, 1999
(as of board presentation)
June 15, 1999
November 9, 1999
US$ 230.00 million
N/A
1999
US$ 191.00 million
C
Not Applicable
March 31, 2006
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
IDA Credit | 191.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 191.00 |
IBRD + IDA Commitment | 191.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 230.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 1, 2016 | IDA-32420 | Int Charges | 591,531.60 |
Jun 1, 2016 | IDA-32420 | Int Charges | 591,531.60 |
Jun 1, 2018 | IDA-32420 | Int Charges | 21,131.87 |
Jun 1, 2018 | IDA-32420 | Int Charges | 21,131.87 |
Jun 1, 2018 | IDA-32420 | Loan Repay | 4,981,472.00 |
Jun 1, 2018 | IDA-32420 | Int Charges | 523,054.53 |
Jun 1, 2018 | IDA-32420 | Int Charges | 523,054.53 |
Dec 1, 2017 | IDA-32420 | Int Charges | 520,974.12 |
Dec 1, 2017 | IDA-32420 | Int Charges | 520,974.12 |
Dec 1, 2017 | IDA-32420 | Int Charges | 111,855.46 |
Dec 1, 2017 | IDA-32420 | Int Charges | 111,855.46 |
Dec 1, 2017 | IDA-32420 | Loan Repay | 4,985,021.50 |
Dec 1, 2019 | IDA-32420 | Loan Repay | 40,610.08 |
Dec 1, 2019 | IDA-32420 | Loan Repay | 9,608,113.00 |
Dec 1, 2019 | IDA-32420 | Int Charges | 372,235.16 |
Jun 1, 2019 | IDA-32420 | Loan Repay | 48,565.82 |
Jun 1, 2019 | IDA-32420 | Loan Repay | 4,792,382.00 |
Jun 1, 2019 | IDA-32420 | Int Charges | 471,992.38 |
Jun 1, 2019 | IDA-32420 | Int Charges | 471,992.38 |
Dec 1, 2018 | IDA-32420 | Loan Repay | 141,297.77 |
Dec 1, 2018 | IDA-32420 | Loan Repay | 4,719,363.50 |
Dec 1, 2018 | IDA-32420 | Int Charges | 492,141.94 |
Dec 1, 2018 | IDA-32420 | Int Charges | 492,141.94 |
Dec 1, 2020 | IDA-32420 | Int Charges | 41,121.08 |
Dec 1, 2020 | IDA-32420 | Int Charges | 41,121.08 |
Dec 1, 2020 | IDA-32420 | Loan Repay | 5,021,496.50 |
Dec 1, 2020 | IDA-32420 | Int Charges | 324,858.50 |
Dec 1, 2020 | IDA-32420 | Int Charges | 324,858.50 |
Jun 1, 2020 | IDA-32420 | Int Charges | 79,952.57 |
Jun 1, 2020 | IDA-32420 | Int Charges | 79,952.57 |
Jun 1, 2020 | IDA-32420 | Loan Repay | 9,637,127.00 |
Jun 1, 2020 | IDA-32420 | Int Charges | 376,141.88 |
Jun 1, 2020 | IDA-32420 | Int Charges | 376,141.88 |
Dec 1, 2019 | IDA-32420 | Int Charges | 372,235.16 |
Dec 1, 2021 | IDA-32420 | Int Charges | 350,395.62 |
Jun 1, 2021 | IDA-32420 | Int Charges | 71,376.10 |
Jun 1, 2021 | IDA-32420 | Int Charges | 71,376.10 |
Jun 1, 2021 | IDA-32420 | Loan Repay | 2,880,817.20 |
Jun 1, 2021 | IDA-32420 | Int Charges | 272,113.70 |
Jun 1, 2021 | IDA-32420 | Int Charges | 272,113.70 |
Jun 1, 2021 | IDA-32420 | Loan Repay | 2,197,008.50 |
Dec 1, 2022 | IDA-32420 | Loan Repay | 117,187.11 |
Dec 1, 2022 | IDA-32420 | Loan Repay | 9,164,508.00 |
Dec 1, 2021 | IDA-32420 | Int Charges | 105,297.62 |
Dec 1, 2021 | IDA-32420 | Int Charges | 105,297.62 |
Dec 1, 2021 | IDA-32420 | Loan Repay | 4,917,834.00 |
Dec 1, 2021 | IDA-32420 | Int Charges | 350,395.62 |
Jun 1, 2022 | IDA-32420 | Loan Repay | 4,694,102.50 |
Jun 1, 2022 | IDA-32420 | Int Charges | 320,008.70 |
Jun 1, 2022 | IDA-32420 | Int Charges | 320,008.70 |
Jun 1, 2022 | IDA-32420 | Loan Repay | 46,766.40 |
Jun 1, 2024 | IDA-32420 | Loan Repay | 9,301,822.00 |
Jun 1, 2024 | IDA-32420 | Int Charges | 191,850.03 |
Jun 1, 2024 | IDA-32420 | Int Charges | 191,850.03 |
Jun 1, 2024 | IDA-32420 | Int Charges | 123,589.54 |
Jun 1, 2024 | IDA-32420 | Int Charges | 123,589.54 |
Jun 15, 1999 | IDA-32420 | Loan Commitment | 191,000,000.00 |
Jun 1, 2023 | IDA-32420 | Loan Repay | 1,300.84 |
Jun 1, 2023 | IDA-32420 | Loan Repay | 9,347,082.00 |
Jun 1, 2023 | IDA-32420 | Int Charges | 262,886.70 |
Jun 1, 2023 | IDA-32420 | Int Charges | 262,886.70 |
Jun 1, 2023 | IDA-32420 | Int Charges | 297,938.25 |
Jun 1, 2023 | IDA-32420 | Int Charges | 297,938.25 |
Dec 1, 2023 | IDA-32420 | Loan Repay | 9,249,483.00 |
Dec 1, 2023 | IDA-32420 | Loan Repay | 113,622.31 |
Dec 1, 2023 | IDA-32420 | Int Charges | 103,821.93 |
Dec 1, 2023 | IDA-32420 | Int Charges | 103,821.93 |
Dec 1, 2013 | IDA-32420 | Loan Repay | 2,688,742.80 |
Dec 1, 2013 | IDA-32420 | Int Charges | 728,286.90 |
Dec 1, 2013 | IDA-32420 | Int Charges | 728,286.90 |
Dec 1, 2013 | IDA-32420 | Loan Repay | 8,616.21 |
Dec 1, 2014 | IDA-32420 | Int Charges | 675,006.30 |
Dec 1, 2014 | IDA-32420 | Int Charges | 675,006.30 |
Dec 1, 2014 | IDA-32420 | Loan Repay | 10,612.29 |
Dec 1, 2014 | IDA-32420 | Loan Repay | 5,132,293.00 |
Jun 1, 2015 | IDA-32420 | Loan Repay | 76,005.92 |
Jun 1, 2015 | IDA-32420 | Loan Repay | 4,802,682.00 |
Jun 1, 2015 | IDA-32420 | Int Charges | 587,959.25 |
Jun 1, 2015 | IDA-32420 | Int Charges | 587,959.25 |
Jun 1, 2014 | IDA-32420 | Int Charges | 720,632.44 |
Jun 1, 2014 | IDA-32420 | Loan Repay | 3,726.41 |
Jun 1, 2014 | IDA-32420 | Loan Repay | 2,702,874.20 |
Jun 1, 2014 | IDA-32420 | Int Charges | 720,632.44 |
Dec 1, 2016 | IDA-32420 | Loan Repay | 24,912.82 |
Dec 1, 2016 | IDA-32420 | Loan Repay | 4,730,680.00 |
Dec 1, 2016 | IDA-32420 | Int Charges | 552,837.60 |
Dec 1, 2016 | IDA-32420 | Int Charges | 552,837.60 |
Dec 1, 2015 | IDA-32420 | Int Charges | 33,719.03 |
Dec 1, 2015 | IDA-32420 | Int Charges | 33,719.03 |
Dec 1, 2015 | IDA-32420 | Loan Repay | 4,827,946.00 |
Dec 1, 2015 | IDA-32420 | Int Charges | 597,458.25 |
Dec 1, 2015 | IDA-32420 | Int Charges | 597,458.25 |
Jun 1, 2017 | IDA-32420 | Loan Repay | 166,627.60 |
Jun 1, 2017 | IDA-32420 | Loan Repay | 4,699,480.00 |
Jun 1, 2017 | IDA-32420 | Int Charges | 438,249.90 |
Jun 1, 2017 | IDA-32420 | Int Charges | 438,249.90 |
Jun 1, 2016 | IDA-32420 | Loan Repay | 104,857.83 |
Jun 1, 2016 | IDA-32420 | Loan Repay | 4,824,572.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2006-04-09 |
Project Management | Moderately Satisfactory | 2006-04-09 |
Financial Management | Satisfactory | 2006-04-09 |
Monitoring and Evaluation | Moderately Satisfactory | 2006-04-09 |
Progress towards achievement of PDO | Satisfactory | 2006-04-09 |
Counterpart Funding | Satisfactory | 2006-04-09 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2006-04-09 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-03-2006 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 12-15-2006 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduce the rate of growth of HIV infections in India. (The reduction in the rate of HIV spread would be reflected in the stabilization of the annual percentage increase of HIV prevalence.) | Value | 0.7% | 0.8% | <5% in high prevalence states<3% in low prevalenc |
Date | November 9, 1999 | September 15, 2005 | March 31, 2006 | |
Comment |
Strengthen India's capacity to respond to the epidemic. (to be measured by several indicators). | Value | Mapping, Targeted intervention expansion, expansio | Mapping in all states completed, 1033 targeted in | Mapping in 38 states and territories completed, 15 |
Date | November 9, 1999 | December 31, 2005 | March 31, 2006 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Completion of participatory mapping of groups at high risk. | Value | 0 | 38 | 38 |
Date | November 9, 1999 | September 26, 2004 | March 31, 2006 | |
Comment |
Number of targeted interventions implemented to reach high risk groups. | Value | 157 | 1033 | 1500 |
Date | November 9, 1999 | December 30, 2005 | January 31, 2006 | |
Comment |
Percentage of population aware of HIV/AIDS | Value | 76 percent overall, range 22-99% | urban 89%rural 82%(BBC World Service Trust) | 100% |
Date | July 31, 2000 | December 31, 2005 | March 31, 2006 | |
Comment |
Number of sites offering Voluntary Counseling and Testing (VCT) | Value | 62 | 1114 | 684 |
Date | November 9, 1999 | December 31, 2005 | January 31, 2006 | |
Comment |
Number of STD clinics established. | Value | 504 | 922 | 757 |
Date | November 9, 1999 | February 1, 2006 | March 31, 2006 | |
Comment |
Number of Prevention of Parent to Child Transmission Centers established | Value | 0 | 377 | 600 (revised to 444 by 2009 in dialogue with UNICE |
Date | November 9, 1999 | December 31, 2004 | March 31, 2006 | |
Comment |