Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 230.00 |
P045788
Closed
Wenlai Zhang
N/A
June 6, 1997
(as of board presentation)
June 23, 1998
March 18, 1999
US$ 658.70 million
N/A
1998
US$ 230.00 million
A
Not Applicable
June 30, 2007
BANK APPROVED
March 11, 2021
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 230.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 230.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 230.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 658.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2018 | IBRD-43560 | Loan Repay | 10,624,100.00 |
Sep 15, 2017 | IBRD-43560 | Int Charges | 295,056.97 |
Sep 15, 2017 | IBRD-43560 | Loan Repay | 10,320,100.00 |
Mar 15, 2017 | IBRD-43560 | Int Charges | 337,221.66 |
Mar 15, 2017 | IBRD-43560 | Loan Repay | 10,025,600.00 |
Sep 15, 2016 | IBRD-43560 | Int Charges | 322,102.10 |
Sep 15, 2016 | IBRD-43560 | Loan Repay | 9,735,900.00 |
Sep 15, 2015 | IBRD-43560 | Int Charges | 240,729.62 |
Sep 15, 2015 | IBRD-43560 | Loan Repay | 9,185,700.00 |
Mar 15, 2016 | IBRD-43560 | Int Charges | 256,431.56 |
Mar 15, 2016 | IBRD-43560 | Loan Repay | 9,456,000.00 |
Mar 15, 2015 | IBRD-43560 | Int Charges | 227,024.52 |
Mar 15, 2015 | IBRD-43560 | Loan Repay | 8,920,200.00 |
Sep 15, 2014 | IBRD-43560 | Int Charges | 242,554.10 |
Sep 15, 2014 | IBRD-43560 | Loan Repay | 8,664,300.00 |
Mar 15, 2014 | IBRD-43560 | Int Charges | 285,663.62 |
Mar 15, 2014 | IBRD-43560 | Loan Repay | 8,418,200.00 |
Sep 15, 2013 | IBRD-43560 | Int Charges | 341,755.94 |
Sep 15, 2018 | IBRD-43560 | Int Charges | 151,110.28 |
Jun 23, 1998 | IBRD-43560 | Loan Commitment | 230,000,000.00 |
Sep 15, 2013 | IBRD-43560 | Loan Repay | 8,176,900.00 |
Sep 15, 2018 | IBRD-43560 | Loan Repay | 10,950,020.00 |
Mar 15, 2018 | IBRD-43560 | Int Charges | 200,669.28 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2007-06-25 |
Procurement | Satisfactory | 2007-06-25 |
Project Management | Satisfactory | 2007-06-25 |
Financial Management | Satisfactory | 2007-06-25 |
Overall Safeguards Rating | Satisfactory | 2007-06-25 |
Counterpart Funding | Satisfactory | 2007-06-25 |
Monitoring and Evaluation | Satisfactory | 2007-06-25 |
Overall Implementation Progress (IP) | Satisfactory | 2007-06-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-27-2007 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 06-17-2009 | PROJECT PERFORMANCE ASSESSMENT REPORT: 03-03-2008 |
---|---|---|
Outcome Rating | Satisfactory | Highly Satisfactory |
Risk To Development Outcome | Negligible To Low | Negligible To Low |
Bank Performance | Satisfactory | Satisfactory |
Borrower Performance | Satisfactory | Satisfactory |
Government Performance | Satisfactory | Satisfactory |
Implementing Agency | Not Rated | Satisfactory |
Icr Quality | Not Rated | Satisfactory |
M&e Quality | Substantial | Substantial |