Skip to Main Navigation

JO: ODS PHASEOUT II

Development Objective

The global development objective of the Montreal Protocol is to assist the Government of Jordan through a combination of policy support, institutional capacity building and technical and financial assistance to the industry to meet its obligation under the Montreal Protocol to completely phase-out the import of ODS by January 2010 with the interim steps of freeze of import at 1996 level by 2000, 50% reduction by 2005, and 85% reduction by 2007. For halons, freeze only starts by 2002, but the milestones set in the foregoing applies. The overall objective of the Project is to assist the Recipient in phasing out the use of ODS within its territory through, inter alia: (a) the introduction of appropriate policy measures; (b) the institutional strengthening of responsible governmental entities; and (c) the implementation of specific cost-effective priority investments to reduce consumption of ozone depleting substances in the manufacturing and servicing sectors. The Project will allow Jordan to develop local institutional capacity to manage a global programs similar to Montreal Protocol, develop and implement supporting policies and regulations to achieve the overall objectives and to develop investment activities to assist the industry in converting to non-ODS technologies consistent with World Bank requirements and policies and guidelines of the Multilateral Fund for the implementation of the MP.

Key Details

Project Details

  • P049706

  • Closed

  • Tracy Hart

  • N/A

  • Jordan

  • October 6, 1996

  • (as of board presentation)

    October 6, 1996

  • October 6, 1995

  • US$ 3.80 million

  • C

  • May 22, 2013

  • December 31, 2012

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Montreal Protocol Investment Fund 3.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 3.80
Total Project Cost** 3.80

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2012-12-15
Project Management Satisfactory 2012-12-15
Counterpart Funding Satisfactory 2012-12-15
Overall Implementation Progress (IP) Satisfactory 2012-12-15
Summary Global Objective Rating Satisfactory 2012-12-15
Financial Management Satisfactory 2012-12-15
Monitoring and Evaluation Satisfactory 2012-12-15

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2013
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-29-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceHighly SatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencyHighly SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Policy measures introduced.Value0%100% achieved.100% achieved.
    DateJanuary 1, 2000November 9, 2012December 31, 2012
    Commentno baseline availableThe GoJ has not issued any import permits for CFC and halon meaning that it has completely phased out "Annex A" substances underthe MP.Complete phase-out of CFC and halon.
  • Cost-effective priority investmentsValue0.0013.0014.00
    DateNovember 9, 2012December 31, 2012
    Comment0 investment projects13 investment projects (including the halon R&R center) have been physically and financially completed Only one remain: chillerreplacement, which is in RFQ phase and expected to be completed prior to end of CY13.14 Investment subprojects will have completed ensuring total CFC and halon phaseout.