Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 463.00 |
IDA Credit | 92.00 |
Borrower/Recipient | 568.00 |
P050668
Closed
Atul Agarwal
N/A
September 24, 1999
(as of board presentation)
June 18, 2002
November 6, 2002
US$ 1123.00 million
N/A
2002
US$ 555.00 million
A
March 11, 2021
June 15, 2011
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 463.00 |
IDA Credit | 92.00 |
Borrower/Recipient | 568.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 463.00 |
IDA Commitment | 92.00 |
IBRD + IDA Commitment | 555.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1123.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2015 | IDA-36620 | Int Charges | 266,141.38 |
Dec 15, 2015 | IDA-36620 | Int Charges | 266,141.38 |
Mar 15, 2015 | IBRD-46650 | Int Charges | 615,869.10 |
Mar 15, 2015 | IBRD-46650 | Loan Repay | 11,235,396.00 |
Jun 15, 2015 | IDA-36620 | Loan Repay | 37,085.79 |
Jun 15, 2015 | IDA-36620 | Loan Repay | 1,949,281.80 |
Jun 15, 2015 | IDA-36620 | Int Charges | 224,406.40 |
Jun 15, 2015 | IDA-36620 | Int Charges | 224,406.40 |
Sep 15, 2014 | IBRD-46650 | Int Charges | 629,252.75 |
Sep 15, 2014 | IBRD-46650 | Loan Repay | 11,099,098.00 |
Dec 15, 2014 | IDA-36620 | Loan Repay | 7,805.28 |
Dec 15, 2014 | IDA-36620 | Loan Repay | 2,059,168.20 |
Dec 15, 2014 | IDA-36620 | Int Charges | 294,543.72 |
Dec 15, 2014 | IDA-36620 | Int Charges | 294,543.72 |
Jun 15, 2014 | IDA-36620 | Loan Repay | 1,088,739.90 |
Jun 15, 2014 | IDA-36620 | Int Charges | 314,373.66 |
Jun 15, 2014 | IDA-36620 | Int Charges | 314,373.66 |
Jun 15, 2014 | IDA-36620 | Int Charges | 7,264.26 |
Jun 15, 2014 | IDA-36620 | Int Charges | 7,264.26 |
Mar 15, 2014 | IBRD-46650 | Loan Repay | 10,962,800.00 |
Mar 15, 2014 | IBRD-46650 | Int Charges | 706,726.10 |
Dec 15, 2013 | IDA-36620 | Int Charges | 15,906.34 |
Dec 15, 2013 | IDA-36620 | Int Charges | 15,906.34 |
Dec 15, 2013 | IDA-36620 | Loan Repay | 1,087,573.00 |
Dec 15, 2013 | IDA-36620 | Int Charges | 310,858.62 |
Dec 15, 2013 | IDA-36620 | Int Charges | 310,858.62 |
Sep 15, 2013 | IBRD-46650 | Int Charges | 812,749.40 |
Sep 15, 2013 | IBRD-46650 | Loan Repay | 10,826,502.00 |
Jun 18, 2002 | IBRD-46650 | Loan Commitment | 463,000,000.00 |
Jun 18, 2002 | IDA-36620 | Loan Commitment | 79,000,000.00 |
Jun 15, 2024 | IDA-36620 | Int Charges | 122,055.01 |
Jun 15, 2024 | IDA-36620 | Int Charges | 122,055.01 |
Jun 15, 2024 | IDA-36620 | Loan Repay | 3,727,253.80 |
Jun 15, 2024 | IDA-36620 | Int Charges | 89,033.40 |
Jun 15, 2024 | IDA-36620 | Int Charges | 89,033.40 |
Dec 15, 2023 | IDA-36620 | Loan Repay | 61,199.38 |
Dec 15, 2023 | IDA-36620 | Loan Repay | 3,731,597.20 |
Dec 15, 2023 | IDA-36620 | Int Charges | 51,630.85 |
Dec 15, 2023 | IDA-36620 | Int Charges | 51,630.85 |
Jun 15, 2023 | IDA-36620 | Loan Repay | 3,775,371.20 |
Jun 15, 2023 | IDA-36620 | Int Charges | 155,734.08 |
Jun 15, 2023 | IDA-36620 | Int Charges | 155,734.08 |
Jun 15, 2023 | IDA-36620 | Int Charges | 161,005.12 |
Jun 15, 2023 | IDA-36620 | Int Charges | 161,005.12 |
Mar 15, 2023 | IBRD-46650 | Int Charges | 15,428.47 |
Dec 15, 2022 | IDA-36620 | Int Charges | 8,861.13 |
Dec 15, 2022 | IDA-36620 | Int Charges | 8,861.13 |
Dec 15, 2022 | IDA-36620 | Loan Repay | 28,948.34 |
Dec 15, 2022 | IDA-36620 | Loan Repay | 3,735,617.00 |
Sep 15, 2022 | IBRD-46650 | Int Charges | 112,430.35 |
Sep 15, 2022 | IBRD-46650 | Loan Repay | 13,526,681.00 |
Dec 15, 2021 | IDA-36620 | Int Charges | 185,179.70 |
Dec 15, 2021 | IDA-36620 | Int Charges | 185,179.70 |
Dec 15, 2021 | IDA-36620 | Int Charges | 8,803.13 |
Dec 15, 2021 | IDA-36620 | Int Charges | 8,803.13 |
Dec 15, 2021 | IDA-36620 | Loan Repay | 987,625.25 |
Mar 15, 2022 | IBRD-46650 | Int Charges | 90,573.86 |
Mar 15, 2022 | IBRD-46650 | Loan Repay | 13,360,912.00 |
Jun 15, 2022 | IDA-36620 | Loan Repay | 12,979.12 |
Jun 15, 2022 | IDA-36620 | Loan Repay | 928,876.50 |
Jun 15, 2022 | IDA-36620 | Int Charges | 173,065.98 |
Jun 15, 2022 | IDA-36620 | Int Charges | 173,065.98 |
Sep 15, 2021 | IBRD-46650 | Int Charges | 143,407.14 |
Sep 15, 2021 | IBRD-46650 | Loan Repay | 13,195,144.00 |
Jun 15, 2021 | IDA-36620 | Int Charges | 185,577.22 |
Jun 15, 2021 | IDA-36620 | Int Charges | 22,764.45 |
Jun 15, 2021 | IDA-36620 | Int Charges | 22,764.45 |
Jun 15, 2021 | IDA-36620 | Loan Repay | 1,017,772.94 |
Jun 15, 2021 | IDA-36620 | Int Charges | 185,577.22 |
Mar 15, 2021 | IBRD-46650 | Int Charges | 205,631.92 |
Mar 15, 2021 | IBRD-46650 | Loan Repay | 13,033,060.00 |
Dec 15, 2020 | IDA-36620 | Int Charges | 20,887.61 |
Dec 15, 2020 | IDA-36620 | Int Charges | 20,887.61 |
Dec 15, 2020 | IDA-36620 | Loan Repay | 1,016,931.40 |
Dec 15, 2020 | IDA-36620 | Int Charges | 175,556.02 |
Dec 15, 2020 | IDA-36620 | Int Charges | 175,556.02 |
Sep 15, 2020 | IBRD-46650 | Int Charges | 408,114.30 |
Sep 15, 2020 | IBRD-46650 | Loan Repay | 12,874,659.00 |
Jun 15, 2020 | IDA-36620 | Int Charges | 20,808.82 |
Jun 15, 2020 | IDA-36620 | Int Charges | 20,808.82 |
Jun 15, 2020 | IDA-36620 | Loan Repay | 1,950,937.10 |
Jun 15, 2020 | IDA-36620 | Int Charges | 177,496.40 |
Jun 15, 2020 | IDA-36620 | Int Charges | 177,496.40 |
Dec 15, 2019 | IDA-36620 | Loan Repay | 11,259.70 |
Dec 15, 2019 | IDA-36620 | Loan Repay | 1,946,381.60 |
Dec 15, 2019 | IDA-36620 | Int Charges | 184,671.98 |
Dec 15, 2019 | IDA-36620 | Int Charges | 184,671.98 |
Mar 15, 2020 | IBRD-46650 | Int Charges | 1,006,702.60 |
Mar 15, 2020 | IBRD-46650 | Loan Repay | 12,716,259.00 |
Sep 15, 2019 | IBRD-46650 | Int Charges | 1,478,688.90 |
Sep 15, 2019 | IBRD-46650 | Loan Repay | 12,557,858.00 |
Jun 15, 2019 | IDA-36620 | Int Charges | 212,776.60 |
Jun 15, 2019 | IDA-36620 | Int Charges | 212,776.60 |
Jun 15, 2019 | IDA-36620 | Loan Repay | 1,926,890.00 |
Jun 15, 2019 | IDA-36620 | Loan Repay | 29,676.36 |
Mar 15, 2019 | IBRD-46650 | Int Charges | 1,584,503.40 |
Mar 15, 2019 | IBRD-46650 | Loan Repay | 12,403,141.00 |
Dec 15, 2018 | IDA-36620 | Loan Repay | 68,473.05 |
Dec 15, 2018 | IDA-36620 | Loan Repay | 1,881,954.90 |
Dec 15, 2018 | IDA-36620 | Int Charges | 219,423.16 |
Dec 15, 2018 | IDA-36620 | Int Charges | 219,423.16 |
Jun 15, 2018 | IDA-36620 | Loan Repay | 1,143.99 |
Jun 15, 2018 | IDA-36620 | Loan Repay | 1,994,629.20 |
Jun 15, 2018 | IDA-36620 | Int Charges | 232,008.62 |
Jun 15, 2018 | IDA-36620 | Int Charges | 232,008.62 |
Sep 15, 2018 | IBRD-46650 | Int Charges | 1,629,317.50 |
Sep 15, 2018 | IBRD-46650 | Loan Repay | 12,252,108.00 |
Mar 15, 2018 | IBRD-46650 | Int Charges | 1,222,955.10 |
Mar 15, 2018 | IBRD-46650 | Loan Repay | 12,101,075.00 |
Dec 15, 2017 | IDA-36620 | Int Charges | 38,391.18 |
Dec 15, 2017 | IDA-36620 | Int Charges | 38,391.18 |
Dec 15, 2017 | IDA-36620 | Loan Repay | 2,000,030.50 |
Dec 15, 2017 | IDA-36620 | Int Charges | 240,003.62 |
Dec 15, 2017 | IDA-36620 | Int Charges | 240,003.62 |
Sep 15, 2017 | IBRD-46650 | Loan Repay | 6,152,434.50 |
Sep 15, 2017 | IBRD-46650 | Int Charges | 1,330,692.00 |
Sep 15, 2017 | IBRD-46650 | Loan Repay | 5,801,290.50 |
Mar 15, 2017 | IBRD-46650 | Int Charges | 1,259,149.90 |
Mar 15, 2017 | IBRD-46650 | Loan Repay | 11,806,376.00 |
Jun 15, 2017 | IDA-36620 | Int Charges | 204,401.12 |
Jun 15, 2017 | IDA-36620 | Int Charges | 204,401.12 |
Jun 15, 2017 | IDA-36620 | Loan Repay | 61,998.35 |
Jun 15, 2017 | IDA-36620 | Loan Repay | 1,892,969.80 |
Dec 15, 2016 | IDA-36620 | Int Charges | 241,608.64 |
Dec 15, 2016 | IDA-36620 | Int Charges | 241,608.64 |
Dec 15, 2016 | IDA-36620 | Int Charges | 945.15 |
Dec 15, 2016 | IDA-36620 | Int Charges | 945.15 |
Dec 15, 2016 | IDA-36620 | Loan Repay | 1,894,969.80 |
Jun 15, 2016 | IDA-36620 | Loan Repay | 39,550.70 |
Jun 15, 2016 | IDA-36620 | Loan Repay | 1,949,376.90 |
Jun 15, 2016 | IDA-36620 | Int Charges | 260,054.70 |
Jun 15, 2016 | IDA-36620 | Int Charges | 260,054.70 |
Sep 15, 2016 | IBRD-46650 | Int Charges | 1,060,907.40 |
Sep 15, 2016 | IBRD-46650 | Loan Repay | 11,659,026.00 |
Mar 15, 2016 | IBRD-46650 | Int Charges | 778,373.44 |
Mar 15, 2016 | IBRD-46650 | Loan Repay | 11,519,044.00 |
Sep 15, 2015 | IBRD-46650 | Int Charges | 685,710.75 |
Sep 15, 2015 | IBRD-46650 | Loan Repay | 11,375,378.00 |
Dec 15, 2015 | IDA-36620 | Int Charges | 50,816.73 |
Dec 15, 2015 | IDA-36620 | Int Charges | 50,816.73 |
Dec 15, 2015 | IDA-36620 | Loan Repay | 1,971,417.50 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2011-06-27 |
Financial Management | Moderately Satisfactory | 2011-06-27 |
Monitoring and Evaluation | Moderately Satisfactory | 2011-06-27 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2011-06-27 |
Counterpart Funding | Satisfactory | 2011-06-27 |
Project Management | Moderately Satisfactory | 2011-06-27 |
Procurement | Moderately Satisfactory | 2011-06-27 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-15-2011 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Moderately Satisfactory |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 04-30-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: 06-15-2016 |
---|---|---|
Outcome Rating | Moderately Satisfactory | Moderately Satisfactory |
Risk To Development Outcome | Moderate | Modest |
Bank Performance | Moderately Satisfactory | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory | Moderately Satisfactory |
Government Performance | Moderately Satisfactory | Not Rated |
Implementing Agency | Moderately Satisfactory | Moderately Satisfactory |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | Substantial | Substantial |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
To reduce peak hour overcrowding - average loads in trains reduced | Value | 4500 to 5400 | 4016 | about 3700 |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target partially achieved. Despite the increase in train services, the reduction in overcrowding has not been completely achieveddue to the increase in number of passengers. |
To reduce working ratio (costs excluding depreciaition and interest/income) for suburban railway services | Value | 0.88 | 0.88 | 0.85 |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target not achieved. The non reduction of working ratio results from the absence of any change in fare in last several years andsignificant increase in operating cost during the project implementation period. |
To increase peak hour average frequency of suburban train services | Value | 13 | 16.1 | 16 |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target achieved. More trains put in service. |
To reduce journey times on JVLR | Value | 30 min | 29 min | 24 min |
Date | February 15, 2002 | January 31, 2011 | June 15, 2011 | |
Comment | The work is in progress so full potential not achieved. |
To increase cost recovery of bus services (income/cost) | Value | < 90% | 73.6% | >100% |
Date | February 15, 2002 | January 31, 2011 | June 15, 2011 | |
Comment | Target not achieved. The value is for year 2009-10 and it is low because establishment cost increased on account of increase indearness allowance to employees and increased Voluntary Retirement Scheme payments due to reduction of 530 staff positions. As perthe budget estimate document, it is expected that the target will be 85% for 2010-11. |
To increase percentage of PAH living in houses of at least 225 sq feet | Value | 9% | 98% | 100% |
Date | February 15, 2002 | January 31, 2011 | June 15, 2011 | |
Comment | Target essentially achieved. Few cases still not completed |
To reduce journey time on SCLR | Value | 20 min | 38 min | 16 min |
Date | February 15, 2002 | January 31, 2011 | June 15, 2011 | |
Comment | Target not achieved. As the work is still in progress, the current time is through alternate route |
To increase the technical capacity in MCGM to manage traffic as per the modified MCGM act. | Value | No Traffic Management Unit (TMU) in MCGM | Review completed by MCGM | TMU completely staffed and functional of its own |
Date | December 14, 2001 | January 31, 2010 | June 15, 2011 | |
Comment |
Develop capacity for management of resettlement implementation | Value | Project R&R unit created with few staff in MMRDA. | New position of Chief (R&R) created in MMRDA. Live | Reasonably well functional R&R division in MMRDA w |
Date | December 14, 2001 | January 31, 2010 | June 15, 2011 | |
Comment |
To reduce incidence and severity of pedestrian road traffic accidents | Value | 100.00 | 0.00 | 90.00 |
Date | May 21, 2002 | June 15, 2011 | ||
Comment | Target not achieved. During the project restructuring this component substantially reduced to only two pedestrian crossings whichhave been completed. This number was 30 as per the PAD. |
To increase train availability at peak | Value | 91.00 | 91.50 | 94.00 |
Date | May 21, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target not achieved. Some of the old train sets are still operating in the system requiring more maintenance. The value shouldimprove once these old train sets are replaced. |
To reduce delays at ATC controlled junctions | Value | 617 pcu hrs/hour (phase I)2900 pc hrs/hour (phase | Avg 23.4% reduction in delays in the new adaptive | Reduction by 25% pc hours/hour |
Date | June 9, 2011 | June 15, 2011 | ||
Comment | Target essentially achieved. |
To increase the technical capacity of transport planning, road maintenance and road safety | Value | Limited Capacity | ||
Date | May 21, 2002 | June 9, 2011 | ||
Comment | Target partially achieved. |
To increase % of PAH having access to individual tap water and toilets | Value | 1.00 | 98.00 | 100.00 |
Date | May 21, 2002 | January 31, 2010 | June 15, 2011 | |
Comment | Target essentially achieved. Few cases are still not completed. |
To strengthen the ambient air quality monitoring and reporting system | Value | No reliable reports | Plan implemented as per study recommendations | |
Date | May 21, 2002 | January 31, 2010 | June 15, 2011 | |
Comment | Target partially completed. The study completed and implementation in progress. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Complete DC to AC conversion in the suburban railway system (line km) | Value | Nil | 645 | 645 |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target essentially achieved. 147 of 645 line kms is completed but yet to be commissioned. |
Increase size of train fleet | Value | 200 x 9 car rakes | 285 x 9 car rakes | 251 x 9 |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target exceeded. More train sets procured. |
Increase in number of dual voltage trains | Value | Nil | 196 | 179 |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target exceeded. More train sets procured. |
Increased length of suburban railway tracks (line km) | Value | Nil | 93 kms added | 93 kms to be added |
Date | May 15, 2000 | June 9, 2011 | June 15, 2011 | |
Comment | Target achieved. |
Increase length of urban arterial roads | Value | 0 lane km | 43 lane km | 45 lane km |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | target essentially achieved. Work is in progress |
Construct new pedestrian grade seperators schemes | Value | 0 | 2 schemes implemented | 2 schemes implemented |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target achieved. |
Equip Area Traffic Control in about 250 junctions | Value | 0 junctions | 217 + 33 junctions | 250 junctions |
Date | February 15, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target essentially achieved. 217 junctions equipped with adaptive mode which are operational (53 in milestone 1 and 164 inmilestone 2)+33 junctions have beeninstalled under fixed time mode and in operation. 3 junctions are under calibration (currentlyworking on fixed mode). |
Procure new low emission, user friendly buses for Mumbai under the project | Value | 0 | 644 | 644 |
Date | February 15, 2002 | January 31, 2010 | June 15, 2011 | |
Comment |
Provide permanent houses/shops with adequate amenities to the project affected households | Value | 400 | 17,420 families permanently rehoused | 2,071 commercial shops and 17,420 families permane |
Date | August 30, 2002 | January 31, 2011 | June 15, 2011 | |
Comment |
Ensure that housing societies are registered and functioning | Value | 0 | 181 societies registered | 188 societies functioning |
Date | February 15, 2002 | January 31, 2011 | June 15, 2011 | |
Comment |
Improve signaling and telecom systems for the suburban railways systems | Value | 0.00 | 3.00 | 3.00 |
Date | May 21, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target achieved. |
Construct new maintenance facility for suburban train fleet | Value | 0.00 | 7.00 | 8.00 |
Date | May 21, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target essentially achieved. The work at 8th upgradation at Virar Car Shed is in advanced stage of completion |
Increase technical capacity through implementation of the results of 12 studies | Value | 0 | 11 studies undertaken and results completed | |
Date | May 21, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target achieved. |
Implement separate accounting and financial management systems established for MRVC | Value | 0 | Separate systems for MRVC established | |
Date | May 21, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target achieved. |
Develop annual business plan for BEST | Value | No annual Business Plan | Business Plan developed as part of annual budget p | |
Date | May 21, 2002 | January 31, 2010 | June 15, 2011 | |
Comment | Target achieved. |
Establish satisfactory maintenance management system in MCGM by 2005 | Value | No management systems in MCGM | System established | |
Date | May 21, 2002 | June 9, 2011 | June 15, 2011 | |
Comment | Target essentially achieved. |
Upgrade CTS in MMRDA | Value | Nil | CTS upgraded | |
Date | May 21, 2002 | January 31, 2010 | June 15, 2011 | |
Comment | Target achieved. |
Implement MMRDA communication strategy | Value | Strategy does not exist | Strategy implemented | |
Date | May 21, 2002 | January 31, 2011 | June 15, 2011 | |
Comment | Target achieved. |