Abstract*

The Second Health Project for Uzbekistan aims to improve the quality and overall cost-effectiveness of health care services. The project has the following four components: Component 1) will extend further support for development of Primary Health Care (PHC) services. In concert with the Asian Development Bank, all Primary Care Centers (SVPs), as well as some remaining SVPs not covered under Health I, will be supplied with a package of equipment. More...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to improve the quality and overall cost-effectiveness of health care services in Uzbekistan. This will be achieved through: (a) completion of the primary care program in 8 regions (Samarkand, Sukhandarya, Namangan, Andijon, Djizzak, Ferghana, Navoiy, and Syr Darya) and other regions as agreed, and institutionalization of general practitioners nationally; (b) extending financing and management reforms related to efficiency and effectiveness of service delivery; (c) improving public health services, including surveillance, training in public health and control of communicable disease; and (d) building capacity in the Ministry of Health to better monitor and evaluate the reforms, and better manage the restructuring process.

Key Details

Project Details

  • P051370

  • Closed

  • Susanna Hayrapetyan

  • N/A

  • Uzbekistan

  • May 28, 2003

  • (as of board presentation)

    September 9, 2004

  • November 15, 2004

  • US$ 40.00 million

  • C

  • Not Applicable

  • December 31, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 78.09
IDA Credit 39.48
IDA GRANT FOR HIV/AIDS 0.52

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 118.09

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2019 IDA-39790 Int Charges 120,108.57
Mar 15, 2020 IDA-39790 Loan Repay 454,351.90
Mar 15, 2020 IDA-39790 Int Charges 118,822.97
Mar 15, 2020 IDA-39790 Int Charges 118,822.97
Mar 15, 2020 IDA-39790 Loan Repay 4,867.26
Mar 15, 2019 IDA-39790 Int Charges 302.53
Mar 15, 2019 IDA-39790 Int Charges 302.53
Mar 15, 2019 IDA-39790 Loan Repay 463,950.78
Mar 15, 2019 IDA-39790 Int Charges 123,526.87
Mar 15, 2019 IDA-39790 Int Charges 123,526.87
Sep 15, 2013 IDA-39790 Int Charges 3,391.32
Sep 15, 2013 IDA-39790 Int Charges 3,391.32
Sep 15, 2013 IDA-39790 Int Charges 146,439.05
Sep 15, 2013 IDA-39790 Int Charges 146,439.05
Mar 15, 2015 IDA-39790 Loan Repay 437,118.72
Mar 15, 2015 IDA-39790 Loan Repay 19,684.66
Mar 15, 2015 IDA-39790 Int Charges 135,327.98
Mar 15, 2015 IDA-39790 Int Charges 135,327.98
Sep 15, 2014 IDA-39790 Int Charges 1,615.22
Sep 15, 2014 IDA-39790 Int Charges 1,615.22
Sep 15, 2014 IDA-39790 Loan Repay 499,731.06
Sep 15, 2014 IDA-39790 Int Charges 149,919.31
Sep 15, 2014 IDA-39790 Int Charges 149,919.31
Mar 15, 2014 IDA-39790 Int Charges 2,056.49
Mar 15, 2014 IDA-39790 Int Charges 2,056.49
Mar 15, 2014 IDA-39790 Int Charges 153,358.19
Mar 15, 2014 IDA-39790 Int Charges 153,358.19
Mar 15, 2016 IDA-39790 Loan Repay 464,410.60
Mar 15, 2016 IDA-39790 Int Charges 129,682.66
Mar 15, 2016 IDA-39790 Int Charges 129,682.66
Mar 15, 2016 IDA-39790 Int Charges 5,481.19
Mar 15, 2016 IDA-39790 Int Charges 5,481.19
Sep 15, 2015 IDA-39790 Int Charges 131,926.48
Sep 15, 2015 IDA-39790 Int Charges 131,926.48
Sep 15, 2015 IDA-39790 Loan Repay 24,459.96
Sep 15, 2015 IDA-39790 Loan Repay 445,535.28
Mar 15, 2017 IDA-39790 Int Charges 126,478.84
Sep 15, 2017 IDA-39790 Loan Repay 473,722.60
Sep 15, 2017 IDA-39790 Loan Repay 707.68
Sep 9, 2004 IDA-39790 Loan Commitment 39,480,000.00
Mar 15, 2024 IDA-39790 Loan Repay 429,006.44
Mar 15, 2024 IDA-39790 Int Charges 101,497.48
Mar 15, 2024 IDA-39790 Int Charges 101,497.48
Mar 15, 2024 IDA-39790 Loan Repay 14,698.37
Sep 15, 2020 IDA-39790 Loan Repay 73,890.64
Sep 15, 2020 IDA-39790 Loan Repay 1,384.11
Sep 15, 2020 IDA-39790 Loan Repay 11,793.26
Sep 15, 2020 IDA-39790 Loan Repay 7.75
Sep 15, 2020 IDA-39790 Loan Repay 384,965.38
Sep 15, 2020 IDA-39790 Int Charges 111,031.48
Sep 15, 2020 IDA-39790 Int Charges 111,031.48
Mar 15, 2021 IDA-39790 Loan Repay 475,986.38
Mar 15, 2021 IDA-39790 Int Charges 119,591.55
Sep 15, 2021 IDA-39790 Loan Repay 5,048.40
Mar 15, 2022 IDA-39790 Loan Repay 457,318.40
Mar 15, 2022 IDA-39790 Int Charges 75.79
Mar 15, 2022 IDA-39790 Int Charges 75.79
Mar 15, 2022 IDA-39790 Int Charges 112,029.71
Mar 15, 2022 IDA-39790 Int Charges 112,029.71
Mar 15, 2022 IDA-39790 Loan Repay 2,290.60
Sep 23, 2021 IDA-39790 Loan Repay 467,807.22
Sep 23, 2021 IDA-39790 Int Charges 117,025.67
Sep 23, 2021 IDA-39790 Int Charges 117,025.67
Mar 15, 2021 IDA-39790 Int Charges 119,591.55
Mar 15, 2021 IDA-39790 Int Charges 9,417.05
Mar 15, 2021 IDA-39790 Int Charges 9,417.05
Sep 15, 2023 IDA-39790 Loan Repay 432,340.16
Sep 15, 2023 IDA-39790 Int Charges 102,163.56
Sep 15, 2023 IDA-39790 Int Charges 102,163.56
Sep 15, 2023 IDA-39790 Loan Repay 7,072.89
Mar 15, 2023 IDA-39790 Loan Repay 437,635.03
Mar 15, 2023 IDA-39790 Int Charges 104,796.92
Mar 15, 2023 IDA-39790 Int Charges 104,796.92
Mar 15, 2023 IDA-39790 Loan Repay 5,949.84
Sep 15, 2022 IDA-39790 Loan Repay 11,841.90
Sep 15, 2022 IDA-39790 Loan Repay 419,637.38
Sep 15, 2022 IDA-39790 Int Charges 103,555.01
Sep 15, 2022 IDA-39790 Int Charges 103,555.01
Sep 9, 2004 IDA-H1240 Loan Commitment 520,000.00
Mar 15, 2017 IDA-39790 Int Charges 126,478.84
Mar 15, 2017 IDA-39790 Int Charges 2,656.49
Mar 15, 2017 IDA-39790 Int Charges 2,656.49
Mar 15, 2017 IDA-39790 Loan Repay 449,702.62
Sep 15, 2016 IDA-39790 Int Charges 4,436.74
Sep 15, 2016 IDA-39790 Int Charges 4,436.74
Sep 15, 2016 IDA-39790 Loan Repay 466,599.80
Sep 15, 2016 IDA-39790 Int Charges 130,224.64
Sep 15, 2016 IDA-39790 Int Charges 130,224.64
Sep 15, 2018 IDA-39790 Loan Repay 467,396.20
Sep 15, 2018 IDA-39790 Int Charges 125,892.18
Sep 15, 2018 IDA-39790 Int Charges 125,892.18
Sep 15, 2018 IDA-39790 Int Charges 8,528.04
Sep 15, 2018 IDA-39790 Int Charges 8,528.04
Mar 15, 2018 IDA-39790 Loan Repay 484,253.38
Mar 15, 2018 IDA-39790 Int Charges 123,728.74
Mar 15, 2018 IDA-39790 Int Charges 123,728.74
Mar 15, 2018 IDA-39790 Int Charges 14,485.96
Mar 15, 2018 IDA-39790 Int Charges 14,485.96
Sep 15, 2017 IDA-39790 Int Charges 117,462.30
Sep 15, 2017 IDA-39790 Int Charges 117,462.30
Sep 15, 2019 IDA-39790 Loan Repay 456,306.88
Sep 15, 2019 IDA-39790 Loan Repay 1,249.54
Sep 15, 2019 IDA-39790 Int Charges 120,108.57

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2011-12-27
Project Management Satisfactory 2011-12-27
Monitoring and Evaluation Satisfactory 2011-12-27
Overall Implementation Progress (IP) Moderately Satisfactory 2011-12-27
Financial Management Satisfactory 2011-12-27
Progress towards achievement of PDO Moderately Satisfactory 2011-12-27
Procurement Moderately Satisfactory 2011-12-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2012
OutcomesModerately Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-10-2013PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of women who receive antenatal care in the early stage of pregnancy (up to 12-week pregnancy period)Value79.1%87.7%85%
    DateSeptember 9, 2004November 30, 2011December 31, 2011
    CommentTarget exceeded.
  • Number of visits to PHC facilities (SVPs, FAPs) per capita of rural populationValue4.14.65
    DateSeptember 9, 2004November 30, 2011December 31, 2011
    CommentTarget substantially met.
  • Hospitalization rate among rural populationValue11.0%12.1%10.0%
    DateSeptember 9, 2004November 30, 2011December 31, 2011
    CommentActual includes admissions and specialist consultations and diagnostic tests at hospitals; related data cannot be dissociated fromtreatment care in hospitals registries
  • % of SVPs stocked with (for at least 75% of) essential medicinesValue38.9 %6%at least 50 %
    DateSeptember 9, 2004November 30, 2011December 31, 2011
    CommentTarget not met. Survey coincided with major transition in procurement of medicine since 2010 though the change was aimed atincreasing cost-efficiency, the administration of the new system was not properly implemented; hence delay in the supply of anumber of drugs. However, 64% of SVPs have 50% of the drugs on the list.
  • % of health budget expenditures on PHC and outpatient careValue41.7%43.8%at least 40%
    DateSeptember 9, 2004May 17, 2011December 31, 2011
    CommentTarget on track. Represents the period Jan.-Sept. 2010
  • % of rural PHC facilities converted to per capita financing and management systemValue21.5%100%100%
    DateSeptember 9, 2004May 17, 2011December 31, 2011
    CommentTarget met
  • % of urban PHC facilities converted to per capita financing and management system in pilot areasValue0100%100%
    DateSeptember 9, 2004May 17, 2011December 31, 2011
    CommentTarget met.
  • % of patients referred from SVP to hospitalValue20%12%15%
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget exceeded.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of SVPs fully equipped under the ProjectValue0%100%100%
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget met
  • % of SVPs in pilot oblasts with specialists trained under the program of medical equipment maintenanceValue0%98.3%100%
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget substantially met
  • % of SVPs equipped with modern dental equipmentValue0%7.3%4%
    DateJune 22, 2010November 30, 2011December 31, 2011
    CommentNew indicatorTarget exceeded. Represents 231 SVPs
  • % of central polyclinics equipped with modern dental equipmentValue0%100%100%
    DateJune 22, 2010May 17, 2011December 31, 2011
    CommentNew indicatorTarget met. 310 units delivered
  • % of SVP physicians retrainedValue14.5% or 898 GPs74.9% or 3770 GPs58% or 2700 GPs
    DateDecember 31, 2004November 30, 2011December 31, 2011
    Commenttarget exceeded
  • % of SVPs with one or more GP or staff who has passed a 10-month GP trg. program or has graduated from university as a GPValue14.5%92.6%at least 70%
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget exceeded
  • % of current expenditures not related to salary relateive to actual expenses of urban PHC facilitiesValue10.8%6.1%at least 20%
    DateDecember 31, 2007May 17, 2011December 31, 2011
    Comment
  • % of share of oblast/city health budget allocated for PHC (rural)Value14.6%15.9%at least 20%
    DateDecember 31, 2004May 17, 2011December 31, 2011
    CommentTarget on track
  • % of Ferghana oblast central rayon hospitals involved in pilot case-based financingValue0%0%100% in pilot oblasts
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget not met. Unlikelihood that hospitals in Ferghana will convert to case-based financing scheme by project end
  • Strengthening and improvement of PH StrategyValue0PH Strategy approved by Cabinet of MinistersPH Strategy approved by Cabinet of Ministers
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget met.
  • Establish the School of PH (SPH)Value0SPH established under TMASPH established
    DateDecember 31, 2004December 31, 2006December 31, 2011
    CommentTarget met
  • Develop plan to improve training programs for PH specialistsValue0CompletedMoH decree endorses the plan
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget met
  • No. of specialists trained in two-year PH programValue054at least 50 specialists
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentTarget met
  • Establish Info System for electronic Monitoring of Infectious Diseases (IS EMID)Value0in progressIS EMID established
    DateDecember 31, 2004November 30, 2011December 31, 2011
    CommentComputers expected to be delivered by closing