Financier | Commitments |
---|---|
US: Agency for International Development (USAID) | 1.24 |
DENMARK, Govt. of | 11.70 |
FINLAND, Govt. of (Except for Min. for Foreign Affairs) | 5.80 |
IDA Credit | 80.50 |
P051553
Closed
Hung Duy Le
N/A
February 12, 1998
(as of board presentation)
May 18, 1999
January 31, 2000
US$ 119.50 million
N/A
1999
US$ 99.24 million
A
January 15, 2013
June 30, 2008
BANK APPROVED
Financier | Commitments |
---|---|
US: Agency for International Development (USAID) | 1.24 |
DENMARK, Govt. of | 11.70 |
FINLAND, Govt. of (Except for Min. for Foreign Affairs) | 5.80 |
IDA Credit | 80.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 80.50 |
IBRD + IDA Commitment | 80.50 |
Lending Instrument | |
---|---|
Grant Amount | 18.74 |
Total Project Cost** | 119.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 1, 2016 | IDA-32110 | Int Charges | 233,526.77 |
Oct 1, 2016 | IDA-32110 | Int Charges | 233,526.77 |
Oct 1, 2016 | IDA-32110 | Int Charges | 21,424.20 |
Oct 1, 2016 | IDA-32110 | Int Charges | 21,424.20 |
Oct 1, 2016 | IDA-32110 | Loan Repay | 724,112.40 |
Apr 1, 2016 | IDA-32110 | Int Charges | 3,895.13 |
Apr 1, 2016 | IDA-32110 | Int Charges | 3,895.13 |
Apr 1, 2016 | IDA-32110 | Int Charges | 216,867.94 |
Apr 1, 2016 | IDA-32110 | Int Charges | 216,867.94 |
Apr 1, 2016 | IDA-32110 | Loan Repay | 731,022.50 |
Oct 1, 2015 | IDA-32110 | Int Charges | 235,857.25 |
Oct 1, 2015 | IDA-32110 | Int Charges | 235,857.25 |
Oct 1, 2015 | IDA-32110 | Loan Repay | 705,661.70 |
Oct 1, 2015 | IDA-32110 | Loan Repay | 20,785.19 |
Apr 1, 2015 | IDA-32110 | Loan Repay | 33,820.73 |
Apr 1, 2015 | IDA-32110 | Int Charges | 238,894.06 |
Apr 1, 2015 | IDA-32110 | Int Charges | 238,894.06 |
Apr 1, 2015 | IDA-32110 | Loan Repay | 681,965.30 |
Apr 1, 2014 | IDA-32110 | Int Charges | 265,743.94 |
Apr 1, 2014 | IDA-32110 | Int Charges | 265,743.94 |
Apr 1, 2014 | IDA-32110 | Loan Repay | 801,633.06 |
Apr 1, 2014 | IDA-32110 | Int Charges | 18,499.86 |
Apr 1, 2014 | IDA-32110 | Int Charges | 18,499.86 |
Oct 1, 2013 | IDA-32110 | Int Charges | 256,667.88 |
Oct 1, 2013 | IDA-32110 | Int Charges | 256,667.88 |
Oct 1, 2013 | IDA-32110 | Loan Repay | 29,603.37 |
Oct 1, 2013 | IDA-32110 | Loan Repay | 767,692.70 |
Oct 1, 2014 | IDA-32110 | Int Charges | 259,596.55 |
Oct 1, 2014 | IDA-32110 | Int Charges | 259,596.55 |
Oct 1, 2014 | IDA-32110 | Int Charges | 7,497.49 |
Oct 1, 2014 | IDA-32110 | Int Charges | 7,497.49 |
Oct 1, 2014 | IDA-32110 | Loan Repay | 769,173.25 |
May 18, 1999 | IDA-32110 | Loan Commitment | 80,500,000.00 |
Apr 1, 2024 | IDA-32110 | Loan Repay | 2,692,763.20 |
Apr 1, 2024 | IDA-32110 | Int Charges | 133,905.53 |
Apr 1, 2024 | IDA-32110 | Int Charges | 133,905.53 |
Oct 1, 2023 | IDA-32110 | Loan Repay | 2,714,891.00 |
Oct 1, 2023 | IDA-32110 | Int Charges | 143,258.12 |
Oct 1, 2023 | IDA-32110 | Int Charges | 143,258.12 |
Oct 1, 2023 | IDA-32110 | Loan Repay | 13,830.43 |
Apr 1, 2024 | IDA-32110 | Loan Repay | 54,011.50 |
Oct 1, 2022 | IDA-32110 | Loan Repay | 2,617,079.20 |
Oct 1, 2022 | IDA-32110 | Int Charges | 159,353.34 |
Oct 1, 2022 | IDA-32110 | Int Charges | 159,353.34 |
Oct 1, 2022 | IDA-32110 | Loan Repay | 38,805.96 |
Apr 1, 2023 | IDA-32110 | Int Charges | 157,021.77 |
Apr 1, 2023 | IDA-32110 | Int Charges | 157,021.77 |
Apr 1, 2023 | IDA-32110 | Loan Repay | 2,692,796.80 |
Apr 1, 2023 | IDA-32110 | Loan Repay | 98,696.57 |
Apr 1, 2022 | IDA-32110 | Int Charges | 182,607.95 |
Apr 1, 2022 | IDA-32110 | Int Charges | 182,607.95 |
Apr 1, 2022 | IDA-32110 | Loan Repay | 37,857.34 |
Apr 1, 2022 | IDA-32110 | Loan Repay | 2,826,576.00 |
Oct 1, 2021 | IDA-32110 | Loan Repay | 25,615.22 |
Oct 1, 2021 | IDA-32110 | Loan Repay | 2,903,768.80 |
Oct 1, 2021 | IDA-32110 | Int Charges | 197,733.77 |
Oct 1, 2021 | IDA-32110 | Int Charges | 197,733.77 |
Apr 1, 2021 | IDA-32110 | Loan Repay | 3,022.78 |
Apr 1, 2021 | IDA-32110 | Loan Repay | 1,466,794.80 |
Apr 1, 2021 | IDA-32110 | Int Charges | 203,937.52 |
Apr 1, 2021 | IDA-32110 | Int Charges | 203,937.52 |
Oct 1, 2020 | IDA-32110 | Int Charges | 208,547.44 |
Oct 1, 2020 | IDA-32110 | Int Charges | 208,547.44 |
Oct 1, 2020 | IDA-32110 | Loan Repay | 13,129.81 |
Oct 1, 2020 | IDA-32110 | Loan Repay | 1,450,358.60 |
Apr 1, 2020 | IDA-32110 | Loan Repay | 1,408,123.10 |
Apr 1, 2020 | IDA-32110 | Int Charges | 207,266.30 |
Apr 1, 2020 | IDA-32110 | Int Charges | 207,266.30 |
Apr 1, 2020 | IDA-32110 | Loan Repay | 9,080.15 |
Oct 1, 2019 | IDA-32110 | Loan Repay | 1,406,200.80 |
Oct 1, 2019 | IDA-32110 | Loan Repay | 6,966.45 |
Oct 1, 2019 | IDA-32110 | Int Charges | 211,975.39 |
Oct 1, 2019 | IDA-32110 | Int Charges | 211,975.39 |
Apr 1, 2019 | IDA-32110 | Loan Repay | 4,965.15 |
Apr 1, 2019 | IDA-32110 | Loan Repay | 715,173.44 |
Apr 1, 2019 | IDA-32110 | Int Charges | 218,742.56 |
Apr 1, 2019 | IDA-32110 | Int Charges | 218,742.56 |
Oct 1, 2018 | IDA-32110 | Loan Repay | 1,108.84 |
Oct 1, 2018 | IDA-32110 | Loan Repay | 722,988.00 |
Oct 1, 2018 | IDA-32110 | Int Charges | 222,660.30 |
Oct 1, 2018 | IDA-32110 | Int Charges | 222,660.30 |
Apr 1, 2018 | IDA-32110 | Loan Repay | 752,350.00 |
Apr 1, 2018 | IDA-32110 | Int Charges | 31.24 |
Apr 1, 2018 | IDA-32110 | Int Charges | 31.24 |
Apr 1, 2018 | IDA-32110 | Int Charges | 234,753.77 |
Apr 1, 2018 | IDA-32110 | Int Charges | 234,753.77 |
Apr 1, 2018 | IDA-32110 | Loan Repay | 1,877.33 |
Oct 3, 2017 | IDA-32110 | Int Charges | 230,275.88 |
Oct 3, 2017 | IDA-32110 | Int Charges | 230,275.88 |
Oct 1, 2017 | IDA-32110 | Loan Repay | 4,200.60 |
Oct 3, 2017 | IDA-32110 | Loan Repay | 726,844.56 |
Apr 1, 2017 | IDA-32110 | Loan Repay | 785.62 |
Apr 1, 2017 | IDA-32110 | Loan Repay | 703,115.25 |
Apr 1, 2017 | IDA-32110 | Int Charges | 224,368.88 |
Apr 1, 2017 | IDA-32110 | Int Charges | 224,368.88 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2009-04-23 |
Monitoring and Evaluation | Moderately Satisfactory | 2009-04-23 |
Progress towards achievement of PDO | Satisfactory | 2009-04-23 |
Counterpart Funding | Satisfactory | 2009-04-23 |
Overall Implementation Progress (IP) | Satisfactory | 2009-04-23 |
Procurement | Satisfactory | 2009-04-23 |
Project Management | Satisfactory | 2009-04-23 |
Financial Management | Satisfactory | 2009-04-23 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2009 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 04-25-2012 | PROJECT PERFORMANCE ASSESSMENT REPORT: 04-14-2010 |
---|---|---|
Outcome Rating | Moderately Satisfactory | Moderately Satisfactory |
Risk To Development Outcome | Significant | Significant |
Bank Performance | Moderately Satisfactory | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory | Moderately Satisfactory |
Government Performance | Moderately Satisfactory | Moderately Satisfactory |
Implementing Agency | Not Rated | Moderately Satisfactory |
Icr Quality | Not Rated | Satisfactory |
M&e Quality | Modest | Modest |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Developing more efficient and financially sustainable utility companies. Cost recovery of operating, maintenance and depreciation of movable assests | Value | Year 1999 Actual. Haiphong: 0%; Halong: 37%; Cam P | Year 2007 Actual: Haiphong: 75%; Danang: 76% Halon | Year 2008 Planned Haiphong: 100%; Halong: 100%; C |
Date | December 31, 1999 | December 31, 2008 | June 30, 2008 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SOLID WASTE MANAGEMENT: Annual weight of waste collected in tonnes | Value | Year 1999: Danang: 100,000 T p.a.; Halong: 25,00 | Year 2007 Actual Danang: 180,145T/p.a; Halong: 12 | Planned by the project end (Year 2008). Danang: |
Date | December 31, 1999 | December 31, 2008 | June 30, 2008 | |
Comment |
SANITATION SUB-LOANS: new or improved septic tanks and toilet facilities | Value | Year 1999. Danang: 0; Haiphong: 0; Quang Ninh: | For 2005 Actual: Cumulative figures: Danang: 13,05 | Planned by the project end (Year 2008). Cumulativ |
Date | December 31, 1999 | December 31, 2008 | June 30, 2008 | |
Comment |
PRIVATE SECTOR PARTICIPATION IN URBAN SANITATION SERVICES: (for solid waste the % by weight and for septic tank emptying the volumeof sludge) | Value | Year 2000. Danang SW: 12% & volume of sludge=25%; | Year 2006 Actual Danang SW=0% & volume of sludge= | Planned by the project end (Year 2008). Danang SW |
Date | December 31, 1999 | December 31, 2008 | June 30, 2008 | |
Comment |