Solid Waste and Environmental Management Project

Abstract*

The Solid Waste and Environmental Management Project will implement sound solid waste management systems for the Jenin District, in support of the strategic context, which calls for adequate public sector management, and institutional strengthening, to foster private sector development, while improving human resources development, and poverty reduction. The project components will: 1) design, and construct sanitary landfills for the Jenin District...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Implementation of an environmentally sound solid waste management system for Jenin District. This will be achieved through the following activities: Construction of a controlled landfill in Jenin District; rehabilitation and closure of uncontrolled dumps, improvement in SWM services through provision of equipment and training and building capacity within Joint Services Council and the Environmental Quality Authority (the former Ministry of Environmental Affairs).

Key Details

Project Details

  • P054051

  • Closed

  • Ibrahim Dajani

  • N/A

  • West Bank and Gaza

  • August 5, 1999

  • (as of board presentation)

    October 10, 2000

  • December 11, 2000

  • US$ 12.75 million

  • A

  • January 15, 2013

  • April 30, 2010

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Special Financing 9.50
EC: European Commission 3.25
Borrower/Recipient 1.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 12.75
Total Project Cost** 14.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 14, 2000 TF-24696 Loan Commitment 9,500,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2009-06-03
Overall Safeguards Rating Moderately Satisfactory 2009-06-03
Progress towards achievement of PDO Satisfactory 2009-06-03
Project Management Satisfactory 2009-06-03
Financial Management Satisfactory 2009-06-03
Monitoring and Evaluation Moderately Satisfactory 2009-06-03
Counterpart Funding Satisfactory 2009-06-03
Overall Implementation Progress (IP) Satisfactory 2009-06-03

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2009
OutcomesHighly Satisfactory
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-03-2010PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Environmentally sound disposal of solid wasteValue0%A regional sanitary landfill has been constructed 100%
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment
  • Improved quality of collection and transfer servicesValue0%All new equipment for collection and transfer sevi100%
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment
  • Strengthened institutuions and capcity to manage solid waste in Jenin DistrictValue0%JSC and its executive unit are now capable of mana100%
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment
  • Sound and sustainable solid waste management system for Jenin DistrictValue0%FMS in place + business plan developed; municipal 100%
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component 1: Safe disposal of solid waste(a) Construction of new landfill (b) Operations at new landfill (c) Number dumps closed and rehabilitated dumps (d) Population served by rehab dumpsValue(a) 0 -zero (b) 0 - zero (c) 0 - zero (d) 0 zero(a) 100% (b) 100% (c) 58 (d) 600,000(a) 1 (b) 1 (c) 53 (d) 200,000
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment
  • Component 2: Improve collection + transfer (a) number new equipment delivered (b) plan for improved services (c) number new equipment maintained + operated (d) populations served by improvementsValue(a) 0 -zero (b) 1 - one (c) 0 - zero (d) 0- zero(a) 125 (b) 100% (c) 100% (d) 600,000(a) 25 (b) 1 (c) 100% (d) 200,000
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment
  • Sustainable SWM system (a) maintain $50,000 landfill account (b) baselines + plan for financial improvement (c) new tariff structure (d) increase revenue collection efficiency (e) increase tariffsValue(a) 0 -zero (b) 0- zero (c) 0 - zero (d) 60% (e)(a) 50% (b) 100% (c) 50 % (d) 60% (e) 80% (averag(a)$50,000 (b) 2 reports (c) 1 report (d) 70% (e
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment
  • SWM institutions + capacity (a) number of staff trained at EQA + JSC (b) population reached by public awareness (c) international supervision contract new landfill (d) quarterly JSC council meetingsValue(a) 0 -zero (b) 0 - zero (c) 0 - zero (d) 0 in la(a) 100% (b) 95% (c) 95% (d) 100%(a) 50 (b) 200,000 (c) 1 (d) >4 in last 12 months
    DateSeptember 11, 2000May 10, 2009June 30, 2009
    Comment