Skip to Main Navigation

Tanzania-Transport Sector Support Project

Abstract*

The objective of the Transport Sector Support Project for Tanzania are to improve the condition of the national paved road network, to lower transport cost on selected roads, and to expand the capacity of selected regional airports. There are five components to the project, the first component being rehabilitation and preparation of designs for the rehabilitation of paved trunk roads. The second component is the improvement of regional airports. This...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objectives of the project are to improve the condition of the national paved road network, to lower transport cost on selected roads, and to expand the capacity of selected regional airports.

Key Details

Project Details

  • P055120

  • Closed

  • Yonas Mchomvu

  • MINISTRY OF FINANCE AND PLANNING

  • Africa

  • July 20, 2009

  • (as of board presentation)

    May 27, 2010

  • December 1, 2010

  • US$ 281.70 million

  • TANROADS

  • Africa

  • 2010

  • US$ 270.00 million

  • B

  • July 15, 2021

  • June 20, 2017

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 11.70
IDA Credit 270.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 270.00
IBRD + IDA Commitment 270.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 281.70

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2022 IDA-47240 Int Charges 328.37
Oct 15, 2022 IDA-47240 Int Charges 328.37
Oct 15, 2022 IDA-47240 Int Charges 817,521.70
Oct 15, 2022 IDA-47240 Int Charges 817,521.70
Oct 15, 2022 IDA-49910 Int Charges 67.18
Oct 15, 2022 IDA-49910 Int Charges 67.18
Oct 15, 2022 IDA-49910 Int Charges 170,747.30
Oct 15, 2022 IDA-49910 Int Charges 170,747.30
Oct 15, 2022 IDA-49910 Loan Repay 20,318.97
Oct 15, 2022 IDA-49910 Loan Repay 444,299.44
Oct 15, 2022 IDA-47240 Loan Repay 98,768.87
Apr 22, 2022 IDA-47240 Loan Repay 2,399,089.20
Apr 22, 2022 IDA-47240 Int Charges 880,129.50
Apr 22, 2022 IDA-47240 Int Charges 880,129.50
Apr 22, 2022 IDA-49910 Loan Repay 490,823.94
Apr 15, 2019 IDA-47240 Int Charges 7,618.47
Apr 15, 2019 IDA-47240 Int Charges 7,618.47
Apr 15, 2019 IDA-47240 Int Charges 924,993.94
Oct 15, 2018 IDA-49910 Int Charges 336.03
Oct 15, 2018 IDA-49910 Int Charges 336.03
Oct 15, 2018 IDA-47240 Int Charges 1,643.28
Oct 15, 2018 IDA-47240 Int Charges 1,643.28
Oct 17, 2018 IDA-47240 Int Charges 921,244.10
Oct 17, 2018 IDA-47240 Int Charges 921,244.10
Oct 17, 2018 IDA-49910 Int Charges 188,484.12
Oct 17, 2018 IDA-49910 Int Charges 188,484.12
Oct 15, 2020 IDA-49910 Int Charges 122.84
Oct 15, 2020 IDA-49910 Int Charges 122.84
Apr 15, 2020 IDA-49910 Int Charges 186,030.20
Apr 15, 2020 IDA-49910 Int Charges 186,030.20
Apr 15, 2020 IDA-47240 Int Charges 909,251.00
Apr 15, 2020 IDA-47240 Int Charges 909,251.00
Apr 15, 2020 IDA-47240 Int Charges 2,448.66
Apr 15, 2020 IDA-47240 Int Charges 2,448.66
Apr 15, 2020 IDA-49910 Int Charges 500.99
Apr 15, 2020 IDA-49910 Int Charges 500.99
Apr 16, 2021 IDA-47240 Int Charges 52.98
Apr 16, 2021 IDA-47240 Int Charges 52.98
Apr 16, 2021 IDA-47240 Int Charges 944,481.80
Apr 16, 2021 IDA-47240 Int Charges 944,481.80
Apr 16, 2021 IDA-49910 Int Charges 195,190.23
Apr 16, 2021 IDA-49910 Int Charges 195,190.23
Apr 16, 2021 IDA-49910 Int Charges 233.74
Apr 16, 2021 IDA-49910 Int Charges 233.74
Apr 16, 2021 IDA-47240 Int Charges 4,188.73
Apr 16, 2021 IDA-47240 Int Charges 4,188.73
Apr 16, 2021 IDA-47240 Loan Repay 2,544,059.00
Oct 16, 2020 IDA-47240 Loan Repay 2,510,227.00
Oct 16, 2020 IDA-47240 Int Charges 937,426.20
Oct 16, 2020 IDA-47240 Int Charges 937,426.20
Oct 15, 2020 IDA-47240 Loan Repay 600.42
May 5, 2016 IDA-49910 Int Charges 182,539.92
May 5, 2016 IDA-49910 Int Charges 182,539.92
May 5, 2016 IDA-47240 Int Charges 868,331.44
May 5, 2016 IDA-47240 Int Charges 868,331.44
Aug 31, 2016 IDA-47240 Loan Disb 6,609,131.00
Jan 30, 2017 IDA-49910 Loan Disb 1,100,058.10
Jan 22, 2018 IDA-49910 Loan Cancel 3,118.27
Apr 18, 2018 IDA-47240 Int Charges 1,300.46
Apr 18, 2018 IDA-47240 Int Charges 1,300.46
Apr 18, 2018 IDA-47240 Int Charges 971,402.75
Oct 19, 2017 IDA-47240 Loan Disb 208,837.80
Oct 3, 2017 IDA-47240 Loan Disb 1,901,510.90
Oct 20, 2017 IDA-49910 Loan Disb 180,000.00
Oct 12, 2017 IDA-49910 Loan Disb 45,089.73
Oct 24, 2017 IDA-49910 Int Charges 1,499.01
Oct 24, 2017 IDA-49910 Int Charges 190,614.77
Oct 24, 2017 IDA-49910 Int Charges 190,614.77
Oct 17, 2017 IDA-49910 Loan Disb 95,675.19
Oct 24, 2017 IDA-47240 Int Charges 930,974.25
Oct 24, 2017 IDA-47240 Int Charges 930,974.25
Oct 24, 2017 IDA-47240 Int Charges 10,603.54
Oct 24, 2017 IDA-47240 Int Charges 10,603.54
Oct 24, 2017 IDA-49910 Int Charges 1,499.01
Apr 15, 2017 IDA-47240 Int Charges 4,625.20
Apr 18, 2018 IDA-47240 Int Charges 971,402.75
Apr 18, 2018 IDA-49910 Int Charges 175.99
Apr 18, 2018 IDA-49910 Int Charges 175.99
Apr 18, 2018 IDA-49910 Int Charges 198,726.48
Apr 18, 2018 IDA-49910 Int Charges 198,726.48
Oct 15, 2019 IDA-49910 Int Charges 534.48
Oct 15, 2019 IDA-49910 Int Charges 534.48
Oct 15, 2019 IDA-47240 Int Charges 2,612.36
Oct 15, 2019 IDA-47240 Int Charges 2,612.36
Oct 15, 2019 IDA-47240 Int Charges 914,448.25
Oct 15, 2019 IDA-47240 Int Charges 914,448.25
Oct 15, 2019 IDA-49910 Int Charges 187,093.55
Oct 15, 2019 IDA-49910 Int Charges 187,093.55
Apr 15, 2019 IDA-49910 Int Charges 1,558.72
Apr 15, 2019 IDA-49910 Int Charges 1,558.72
Apr 15, 2019 IDA-49910 Int Charges 189,251.16
Apr 15, 2019 IDA-49910 Int Charges 189,251.16
Apr 15, 2019 IDA-47240 Int Charges 924,993.94
Oct 23, 2015 IDA-49910 Int Charges 177,512.23
Oct 23, 2015 IDA-47240 Int Charges 764,639.60
Oct 23, 2015 IDA-47240 Int Charges 764,639.60
Feb 29, 2016 IDA-49910 Loan Disb 469,668.84
Oct 15, 2015 IDA-47240 Int Charges 15,812.01
Oct 15, 2015 IDA-47240 Int Charges 15,812.01
Oct 15, 2015 IDA-49910 Int Charges 2,406.14
Oct 15, 2015 IDA-49910 Int Charges 2,406.14
Apr 21, 2015 IDA-47240 Int Charges 5,313.67
Apr 21, 2015 IDA-47240 Int Charges 5,313.67
Apr 21, 2015 IDA-49910 Int Charges 157,825.77
Apr 21, 2015 IDA-49910 Int Charges 157,825.77
Apr 15, 2015 IDA-49910 Int Charges 3,430.00
Aug 12, 2015 IDA-47240 Loan Disb 33,059,914.00
May 11, 2015 IDA-47240 Loan Disb 10,780,957.00
Oct 15, 2016 IDA-49910 Int Charges 1,815.17
Oct 15, 2016 IDA-49910 Int Charges 1,815.17
Oct 15, 2016 IDA-49910 Int Charges 181,309.39
Oct 15, 2016 IDA-49910 Int Charges 181,309.39
Oct 15, 2016 IDA-47240 Int Charges 10,269.31
Oct 15, 2016 IDA-47240 Int Charges 10,269.31
Oct 15, 2016 IDA-47240 Int Charges 871,371.25
Oct 15, 2016 IDA-47240 Int Charges 871,371.25
Apr 15, 2016 IDA-47240 Int Charges 1,609.84
Apr 15, 2016 IDA-47240 Int Charges 1,609.84
Apr 15, 2016 IDA-49910 Int Charges 386.47
Apr 15, 2016 IDA-49910 Int Charges 386.47
Feb 19, 2016 IDA-47240 Loan Disb 3,272,270.20
Dec 2, 2015 IDA-49910 Loan Disb 164,682.20
Mar 1, 2017 IDA-49910 Loan Disb 317,588.53
Oct 10, 2017 IDA-49910 Loan Disb 74,343.63
Apr 15, 2017 IDA-49910 Int Charges 2,248.79
Apr 15, 2017 IDA-49910 Int Charges 2,248.79
Apr 15, 2017 IDA-47240 Int Charges 866,583.06
Apr 15, 2017 IDA-47240 Int Charges 866,583.06
Apr 15, 2017 IDA-49910 Int Charges 176,995.38
Apr 15, 2017 IDA-49910 Int Charges 176,995.38
Apr 15, 2017 IDA-47240 Int Charges 4,625.20
Mar 7, 2017 IDA-47240 Loan Disb 5,798,000.50
Mar 3, 2014 IDA-47240 Loan Disb 22,380,824.00
Oct 15, 2013 IDA-47240 Int Charges 3,158.42
Oct 15, 2013 IDA-47240 Int Charges 3,158.42
Aug 2, 2013 IDA-49910 Loan Disb 19,099,744.00
Dec 2, 2014 IDA-49910 Loan Disb 8,438,920.00
Aug 2, 2013 IDA-47240 Loan Disb 15,238,900.00
Oct 17, 2014 IDA-47240 Int Charges 20,741.50
Oct 17, 2014 IDA-47240 Int Charges 20,741.50
Oct 17, 2014 IDA-47240 Int Charges 627,858.40
Oct 17, 2014 IDA-47240 Int Charges 627,858.40
Oct 17, 2014 IDA-49910 Int Charges 533.93
Oct 17, 2014 IDA-49910 Int Charges 533.93
Oct 17, 2014 IDA-49910 Int Charges 147,571.73
Oct 17, 2014 IDA-49910 Int Charges 147,571.73
Apr 16, 2014 IDA-49910 Int Charges 1,736.33
Apr 16, 2014 IDA-49910 Int Charges 1,736.33
Apr 16, 2014 IDA-49910 Int Charges 142,709.70
Apr 16, 2014 IDA-49910 Int Charges 142,709.70
May 9, 2014 IDA-47240 Loan Disb 15,729,062.00
Apr 16, 2014 IDA-47240 Int Charges 6,897.01
Apr 16, 2014 IDA-47240 Int Charges 6,897.01
Apr 16, 2014 IDA-47240 Int Charges 487,148.16
Apr 16, 2014 IDA-47240 Int Charges 487,148.16
May 7, 2014 IDA-49910 Loan Disb 2,989,300.80
Dec 12, 2013 IDA-47240 Loan Disb 9,850,876.00
Oct 23, 2013 IDA-47240 Int Charges 390,871.53
Oct 23, 2013 IDA-47240 Int Charges 390,871.53
Oct 15, 2013 IDA-49910 Int Charges 517.45
Oct 15, 2013 IDA-49910 Int Charges 517.45
Oct 23, 2013 IDA-49910 Int Charges 96,900.99
Oct 23, 2013 IDA-49910 Int Charges 96,900.99
Jul 31, 2015 IDA-49910 Loan Disb 850,087.70
Apr 15, 2015 IDA-49910 Int Charges 3,430.00
Apr 21, 2015 IDA-47240 Int Charges 668,863.75
Apr 21, 2015 IDA-47240 Int Charges 668,863.75
Mar 5, 2015 IDA-49910 Loan Disb 2,321,233.80
Feb 26, 2015 IDA-47240 Loan Disb 2,328,143.00
Aug 27, 2014 IDA-47240 Loan Disb 20,765,778.00
Dec 29, 2014 IDA-47240 Loan Disb 11,101,448.00
Oct 23, 2015 IDA-49910 Int Charges 177,512.23
Apr 22, 2022 IDA-49910 Int Charges 183,784.84
Apr 22, 2022 IDA-49910 Int Charges 183,784.84
Jun 30, 2011 IDA-49910 Loan Commitment 59,000,000.00
May 27, 2010 IDA-47240 Loan Commitment 270,000,000.00
Apr 15, 2024 IDA-47240 Loan Repay 54,656.34
Apr 16, 2024 IDA-49910 Loan Repay 467,125.06
Apr 16, 2024 IDA-49910 Int Charges 170,412.66
Apr 16, 2024 IDA-49910 Int Charges 170,412.66
Apr 16, 2024 IDA-47240 Loan Repay 2,283,447.80
Apr 16, 2024 IDA-47240 Int Charges 815,382.75
Apr 16, 2024 IDA-47240 Int Charges 815,382.75
Apr 15, 2024 IDA-49910 Loan Repay 11,244.54
Oct 15, 2023 IDA-49910 Int Charges 171,641.70
Oct 15, 2023 IDA-49910 Int Charges 171,641.70
Oct 15, 2023 IDA-47240 Int Charges 40,154.44
Oct 15, 2023 IDA-47240 Int Charges 40,154.44
Oct 15, 2023 IDA-47240 Loan Repay 2,330,347.80
Oct 15, 2023 IDA-47240 Int Charges 821,447.56
Oct 15, 2023 IDA-47240 Int Charges 821,447.56
Oct 15, 2023 IDA-49910 Int Charges 8,260.91
Oct 15, 2023 IDA-49910 Int Charges 8,260.91
Oct 16, 2020 IDA-49910 Int Charges 192,287.05
Oct 16, 2020 IDA-49910 Int Charges 192,287.05
Apr 15, 2022 IDA-49910 Loan Repay 4,238.98
Apr 15, 2022 IDA-47240 Loan Repay 20,605.98
Oct 15, 2021 IDA-49910 Loan Repay 512,431.60
Oct 15, 2021 IDA-49910 Int Charges 192,710.19
Oct 15, 2021 IDA-49910 Int Charges 192,710.19
Oct 15, 2021 IDA-49910 Loan Repay 1,462.21
Oct 15, 2021 IDA-47240 Loan Repay 2,485,600.50
Oct 15, 2021 IDA-47240 Int Charges 52.32
Oct 15, 2021 IDA-47240 Int Charges 52.32
Oct 15, 2021 IDA-47240 Int Charges 923,062.44
Oct 15, 2021 IDA-47240 Int Charges 923,062.44
Oct 15, 2021 IDA-47240 Loan Repay 26,133.90
Oct 15, 2023 IDA-49910 Loan Repay 476,782.56
Apr 15, 2023 IDA-49910 Loan Repay 21,848.14
Apr 15, 2023 IDA-49910 Int Charges 170,801.20
Apr 15, 2023 IDA-49910 Int Charges 170,801.20
Apr 15, 2023 IDA-49910 Loan Repay 471,193.34
Apr 15, 2023 IDA-47240 Loan Repay 106,200.51
Apr 15, 2023 IDA-47240 Loan Repay 2,303,615.00
Apr 15, 2023 IDA-47240 Int Charges 816,973.00
Apr 15, 2023 IDA-47240 Int Charges 816,973.00
Oct 15, 2022 IDA-47240 Loan Repay 2,172,124.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2017-06-30
Procurement Satisfactory 2017-06-30
Counterpart Funding Moderately Satisfactory 2017-06-30
Project Management Satisfactory 2017-06-30
Financial Management Satisfactory 2017-06-30
Monitoring and Evaluation Moderately Satisfactory 2017-06-30
Overall Implementation Progress (IP) Satisfactory 2017-06-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-12-2018
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-25-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • - Bukoba AirportValue26628.0034000.0033138.00
    DateJune 30, 2009June 30, 2009January 2, 2017
    Comment
  • - Kigoma AirportValue28859.0040000.0029781.00
    DateJune 30, 2009June 30, 2009January 2, 2017
    Comment
  • - Tabora AirportValue22912.0030000.0016505.00
    DateJune 30, 2009June 30, 2009January 2, 2017
    Comment
  • Annual passenger volume at Zanzibar airportValue500000.00660000.00946905.00
    DateMay 1, 2011June 6, 2011January 2, 2017
    Comment
  • Female beneficiariesValue0.0050.0050.00
    DateMarch 31, 2009June 6, 2011February 28, 2017
    Comment
  • Average vehicle operating costs on (a) Korogwe-SameValue0.340.230.22
    DateJune 30, 2009June 30, 2009December 1, 2017
    Comment
  • Average vehicle operating costs on (b) Arusha - Minjingu RoadsValue0.450.250.27
    DateJune 30, 2009June 30, 2009December 1, 2017
    Comment
  • Roads in good and fair condition as a share of total classified roadsValue66.0070.0086.00
    DateJune 30, 2009June 30, 2009January 2, 2017
    Comment
  • Passenger Volume at airportsValue78399.00764000.001026329.00
    DateJune 30, 2009June 6, 2011January 2, 2017
    Comment
  • Direct project beneficiariesValue0.005700000.006000000.00
    DateMarch 31, 2009June 6, 2011February 28, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • National Road/Bridge sections improvedValue0.00100.00109.00
    DateJune 30, 2009June 30, 2009June 30, 2015
    Comment
  • Songosongo jetty rehabilitatedValueNoYesYes
    DateMay 1, 2011May 1, 2011June 30, 2016
    Comment
  • Korogwe-Same RoadValue0.00172.00172.00
    DateJune 30, 2009June 30, 2009January 2, 2017
    Comment
  • Arusha-Minjingu RoadValue0.0098.0096.40
    DateJune 30, 2009June 30, 2009January 2, 2017
    Comment
  • Bukoba Runway paved, terminal building, access road and car parking constructedValueNoYesYes
    DateJune 30, 2009June 30, 2009June 30, 2015
    Comment
  • Kigoma Runway pavedValueNoYesYes
    DateJune 30, 2009June 30, 2009June 30, 2014
    Comment
  • Tabora Runway pavedValueNoYesYes
    DateJune 30, 2009June 30, 2009June 30, 2014
    Comment
  • Zanzibar taxiways and apron rehabilitated and extendedValueNoYesYes
    DateMay 1, 2011May 11, 2011December 14, 2014
    Comment
  • Roads rehabilitated, Non-ruralValue0.00270.00268.40
    DateJune 30, 2009June 30, 2009January 29, 2016
    Comment
  • Design and bidding documents for rehabilitation preparedValue0.00911.00918.00
    DateJune 30, 2009June 30, 2009June 30, 2015
    Comment
  • Three Regional airport Runways paved and Zanzibar airport taxiways and apron improvedValueNoYesYes
    DateJune 30, 2009June 30, 2009June 30, 2014
    Comment
  • National Road Saftey Agency (NRSA) established and operationalValueNoYesNo
    DateJune 30, 2009June 30, 2009June 30, 2016
    Comment
  • Driver and Vehicle Examination and Licencing Agency (DVELA) established and operationalValueNoYesNo
    DateJune 30, 2009June 30, 2009June 20, 2017
    Comment
  • Road Accident Information System established and operationalValueNoYesYes
    DateJune 30, 2009June 30, 2009December 31, 2014
    Comment
  • Transport Sector PPP transactions which have reaqched bidding stageValue0.002.001.00
    DateJune 30, 2009June 30, 2009June 20, 2017
    Comment