Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 27.00 |
P063383
Closed
Carlos E. Velez
N/A
June 1, 1999
(as of board presentation)
June 6, 2000
July 31, 2001
US$ 48.09 million
N/A
2000
US$ 27.00 million
B
Not Applicable
March 31, 2007
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 27.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 27.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 27.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 48.09 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2014 | IBRD-45560 | Int Charges | 12,013.89 |
Feb 15, 2015 | IBRD-45560 | Loan Repay | 1,350,000.00 |
Feb 15, 2015 | IBRD-45560 | Int Charges | 8,556.00 |
Aug 15, 2015 | IBRD-45560 | Loan Repay | 1,350,000.00 |
Aug 15, 2015 | IBRD-45560 | Int Charges | 4,751.28 |
Aug 15, 2013 | IBRD-45560 | Int Charges | 24,095.64 |
Aug 15, 2013 | IBRD-45560 | Loan Repay | 1,350,000.00 |
Jun 6, 2000 | IBRD-45560 | Loan Commitment | 27,000,000.00 |
Feb 15, 2014 | IBRD-45560 | Loan Repay | 1,350,000.00 |
Feb 15, 2014 | IBRD-45560 | Int Charges | 18,216.00 |
Aug 15, 2014 | IBRD-45560 | Loan Repay | 1,350,000.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2006-12-10 |
Monitoring and Evaluation | Satisfactory | 2006-12-10 |
Progress towards achievement of PDO | Satisfactory | 2006-12-10 |
Procurement | Satisfactory | 2006-12-10 |
Financial Management | Satisfactory | 2006-12-10 |
Overall Safeguards Rating | Satisfactory | 2006-12-10 |
Overall Implementation Progress (IP) | Satisfactory | 2006-12-10 |
Project Management | Satisfactory | 2006-12-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-24-2007 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 12-21-2007 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |