Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 5.00 |
Borrower/Recipient | 2.00 |
International Bank for Reconstruction and Development | 5.00 |
P064910
Closed
Mark A. Austin
N/A
August 27, 2001
(as of board presentation)
June 2, 2005
N/A
US$ 12.00 million
Ministry of Environment and Natural Resources (MARN)
2005
US$ 10.00 million
B
Not Applicable
December 4, 2006
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 5.00 |
Borrower/Recipient | 2.00 |
International Bank for Reconstruction and Development | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 5.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 5.00 |
Lending Instrument | |
---|---|
Grant Amount | 5.00 |
Total Project Cost** | 12.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 2, 2005 | IBRD-73000 | Loan Commitment | 5,000,000.00 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2006-12-17 |
Counterpart Funding | Satisfactory | 2006-12-17 |
Progress towards achievement of PDO | Highly Unsatisfactory | 2006-12-17 |
Procurement | Satisfactory | 2006-12-17 |
Overall Implementation Progress (IP) | Highly Unsatisfactory | 2006-12-17 |
Project Management | Satisfactory | 2006-12-17 |
Financial Management | Satisfactory | 2006-12-17 |
Monitoring and Evaluation | Satisfactory | 2006-12-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PES mechanisms designed for at least two sites for contracting (buying and generating) environmental services in priority areas, including functioning M&E systems. | Value | 0 | 2 | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |
At least 12,000 ha. under environmental service contracts that contribute to biodiversity consrervation as demonstrated by indicators for vegetation cover, land use practices, and habitat restoration | Value | 0 | 12,000 hectares | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |
Increased water services in pilot watersheds measured by reduction of sediment production and transport, biochemical oxygen demand (BOD) and total suspended solids (TSS) | Value | To be determined in baseline studies that will be | Reduced sediment, BOD, and TSS compared to baselin | |
Date | December 1, 2006 | November 30, 2011 | ||
Comment |
Increased biodiversity conservation in the project sites measured by indicators of landform, ecosystems, and habitats in the dimensions of composition and structure. | Value | To be determined in baseline studies that will be | Improvement over indicator values in baseline stud | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PES program is operational in each pilot area | Value | 0 | 2 | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |
Contract compliance monitoring established | Value | None | 100 percent of PES contracts monitored for complia | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |
60-80 percent of stakeholders aware of the importance of environmental services | Value | TBD | 80 percent | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |
Methodologies developed, tested, and implemented to identify and assess environmental services needs of private sector and assessment of landowners environmental services function to provide services | Value | None | Methodolies implemented and assessments completed | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |
Semiannual learning workshops held with project beneficiaries to review lessons learned and identify good/replicable practices | Value | 0 | 2 workshops per year for duration of project | |
Date | December 1, 2006 | July 15, 2012 | ||
Comment |