P064961
Closed
Deo-Marcel Niyungeko
N/A
July 26, 1999
(as of board presentation)
January 23, 2001
June 29, 2001
US$ 41.56 million
N/A
2001
US$ 40.00 million
F
Not Applicable
December 31, 2007
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Borrower/Recipient | 0.24 |
Local Govts. (Prov., District, City) of Borrowing Country | 1.31 |
IDA Credit | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 41.56 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2022 | IDA-34600 | Loan Repay | 260,886.03 |
Mar 15, 2022 | IDA-34600 | Debt Relief Charges | 606.64 |
Sep 15, 2021 | IDA-34600 | Debt Relief Principal | 262,350.97 |
Sep 15, 2021 | IDA-34600 | Loan Repay | 262,350.97 |
Sep 15, 2021 | IDA-34600 | Loan Repay | 281,779.25 |
Sep 15, 2021 | IDA-34600 | Int Charges | 0.01 |
Sep 15, 2021 | IDA-34600 | Int Charges | 0.01 |
Sep 15, 2021 | IDA-34600 | Int Charges | 79,732.49 |
Sep 15, 2021 | IDA-34600 | Int Charges | 79,732.49 |
Sep 15, 2021 | IDA-34600 | Loan Repay | 5,337.55 |
Mar 15, 2021 | IDA-34600 | Int Charges | 7.54 |
Mar 15, 2021 | IDA-34600 | Int Charges | 7.54 |
Mar 15, 2021 | IDA-34600 | Int Charges | 82,563.52 |
Mar 15, 2021 | IDA-34600 | Int Charges | 82,563.52 |
Mar 15, 2021 | IDA-34600 | Debt Relief Charges | 6,651.55 |
Mar 15, 2021 | IDA-34600 | Int Charges | 6,651.55 |
Mar 15, 2021 | IDA-34600 | Int Charges | 6,651.55 |
Mar 15, 2021 | IDA-34600 | Debt Relief Principal | 256,557.69 |
Mar 15, 2021 | IDA-34600 | Loan Repay | 256,557.69 |
Mar 15, 2021 | IDA-34600 | Loan Repay | 293,865.66 |
Sep 15, 2020 | IDA-34600 | Debt Relief Principal | 149,199.60 |
Sep 15, 2020 | IDA-34600 | Loan Repay | 149,199.60 |
Sep 18, 2020 | IDA-34600 | Int Charges | 76,306.24 |
Sep 18, 2020 | IDA-34600 | Int Charges | 76,306.24 |
Sep 18, 2020 | IDA-34600 | Loan Repay | 119,575.58 |
Sep 18, 2020 | IDA-34600 | Int Charges | 21.77 |
Sep 18, 2020 | IDA-34600 | Int Charges | 21.77 |
Sep 15, 2020 | IDA-34600 | Loan Repay | 4,155.40 |
Sep 15, 2019 | IDA-34600 | Loan Repay | 750.16 |
Sep 15, 2019 | IDA-34600 | Debt Relief Principal | 150,057.88 |
Sep 15, 2019 | IDA-34600 | Loan Repay | 150,057.88 |
Mar 24, 2020 | IDA-34600 | Loan Repay | 111,035.83 |
Mar 24, 2020 | IDA-34600 | Int Charges | 80,251.89 |
Mar 24, 2020 | IDA-34600 | Int Charges | 80,251.89 |
Mar 15, 2020 | IDA-34600 | Loan Repay | 2,922.88 |
Mar 15, 2020 | IDA-34600 | Debt Relief Principal | 149,628.75 |
Mar 15, 2020 | IDA-34600 | Loan Repay | 149,628.75 |
Sep 15, 2019 | IDA-34600 | Loan Repay | 113,747.58 |
Sep 15, 2019 | IDA-34600 | Int Charges | 82,342.91 |
Jan 23, 2001 | IDA-34600 | Loan Commitment | 40,000,000.00 |
Jan 5, 2006 | IDA-H1980 | Loan Commitment | 30,600,000.00 |
Mar 15, 2024 | IDA-34600 | Loan Repay | 17,462.20 |
Mar 15, 2024 | IDA-34600 | Debt Relief Principal | 258,059.52 |
Mar 15, 2024 | IDA-34600 | Loan Repay | 258,059.52 |
Apr 11, 2024 | IDA-34600 | Loan Repay | 144,448.47 |
Apr 11, 2024 | IDA-34600 | Int Charges | 85.70 |
Apr 11, 2024 | IDA-34600 | Int Charges | 85.70 |
Apr 11, 2024 | IDA-34600 | Int Charges | 64,850.99 |
Apr 11, 2024 | IDA-34600 | Int Charges | 64,850.99 |
Mar 29, 2024 | IDA-34600 | Loan Repay | 56,637.34 |
Mar 28, 2024 | IDA-34600 | Loan Repay | 191.50 |
Mar 28, 2024 | IDA-34600 | Loan Repay | 34,491.29 |
Oct 2, 2023 | IDA-34600 | Int Charges | 66,289.59 |
Oct 2, 2023 | IDA-34600 | Int Charges | 66,289.59 |
Oct 2, 2023 | IDA-34600 | Loan Repay | 240,244.66 |
Sep 15, 2023 | IDA-34600 | Debt Relief Principal | 258,917.80 |
Sep 15, 2023 | IDA-34600 | Loan Repay | 258,917.80 |
Sep 15, 2023 | IDA-34600 | Loan Repay | 7,509.11 |
Mar 15, 2023 | IDA-34600 | Loan Repay | 6,319.37 |
Mar 15, 2023 | IDA-34600 | Loan Repay | 246,859.30 |
Mar 15, 2023 | IDA-34600 | Int Charges | 69,248.87 |
Mar 15, 2023 | IDA-34600 | Int Charges | 69,248.87 |
Mar 15, 2023 | IDA-34600 | Debt Relief Principal | 259,776.08 |
Mar 15, 2023 | IDA-34600 | Loan Repay | 259,776.08 |
Sep 15, 2022 | IDA-34600 | Loan Repay | 226,726.05 |
Sep 15, 2022 | IDA-34600 | Int Charges | 79.39 |
Sep 15, 2022 | IDA-34600 | Int Charges | 79.39 |
Sep 15, 2022 | IDA-34600 | Int Charges | 69,230.16 |
Sep 15, 2022 | IDA-34600 | Int Charges | 69,230.16 |
Sep 15, 2022 | IDA-34600 | Loan Repay | 11,595.61 |
Sep 15, 2022 | IDA-34600 | Debt Relief Principal | 260,634.38 |
Sep 15, 2022 | IDA-34600 | Loan Repay | 260,634.38 |
Mar 30, 2022 | IDA-34600 | Loan Repay | 271,375.66 |
Mar 30, 2022 | IDA-34600 | Int Charges | 75,953.99 |
Mar 30, 2022 | IDA-34600 | Int Charges | 75,953.99 |
Mar 18, 2015 | IDA-34600 | Int Charges | 63.44 |
Mar 18, 2015 | IDA-34600 | Int Charges | 91,107.52 |
Mar 18, 2015 | IDA-34600 | Int Charges | 91,107.52 |
Sep 15, 2014 | IDA-34600 | Debt Relief Charges | 4,210.54 |
Sep 15, 2014 | IDA-34600 | Int Charges | 4,210.54 |
Sep 15, 2014 | IDA-34600 | Int Charges | 4,210.54 |
Sep 15, 2014 | IDA-34600 | Debt Relief Principal | 150,138.81 |
Sep 15, 2014 | IDA-34600 | Loan Repay | 150,138.81 |
Mar 15, 2014 | IDA-34600 | Loan Repay | 149,384.60 |
Mar 15, 2014 | IDA-34600 | Int Charges | 100,968.59 |
Mar 15, 2014 | IDA-34600 | Int Charges | 100,968.59 |
Mar 15, 2014 | IDA-34600 | Debt Relief Charges | 5,375.53 |
Mar 15, 2014 | IDA-34600 | Int Charges | 5,375.53 |
Mar 15, 2014 | IDA-34600 | Int Charges | 5,375.53 |
Mar 15, 2014 | IDA-34600 | Debt Relief Principal | 149,402.95 |
Mar 15, 2014 | IDA-34600 | Loan Repay | 149,402.95 |
Sep 15, 2013 | IDA-34600 | Debt Relief Principal | 155,207.62 |
Sep 15, 2013 | IDA-34600 | Loan Repay | 155,207.62 |
Sep 15, 2013 | IDA-34600 | Loan Repay | 128,560.79 |
Sep 15, 2013 | IDA-34600 | Int Charges | 98,991.92 |
Sep 15, 2013 | IDA-34600 | Int Charges | 98,991.92 |
Sep 15, 2013 | IDA-34600 | Loan Repay | 8,882.88 |
Oct 9, 2014 | IDA-34600 | Loan Repay | 138,107.72 |
Oct 9, 2014 | IDA-34600 | Int Charges | 100,264.14 |
Oct 9, 2014 | IDA-34600 | Int Charges | 100,264.14 |
Mar 15, 2017 | IDA-34600 | Debt Relief Charges | 1,532.61 |
Mar 15, 2017 | IDA-34600 | Int Charges | 1,532.61 |
Mar 15, 2017 | IDA-34600 | Int Charges | 1,532.61 |
Mar 15, 2017 | IDA-34600 | Loan Repay | 109,343.61 |
Mar 15, 2017 | IDA-34600 | Int Charges | 2.40 |
Mar 15, 2017 | IDA-34600 | Int Charges | 2.40 |
Mar 15, 2017 | IDA-34600 | Int Charges | 33,223.76 |
Sep 15, 2016 | IDA-34600 | Debt Relief Charges | 2,663.32 |
Sep 15, 2016 | IDA-34600 | Int Charges | 2,663.32 |
Sep 15, 2016 | IDA-34600 | Int Charges | 2,663.32 |
Sep 16, 2016 | IDA-34600 | Int Charges | 88,423.20 |
Sep 16, 2016 | IDA-34600 | Int Charges | 88,423.20 |
Sep 16, 2016 | IDA-34600 | Loan Repay | 119,778.20 |
Sep 15, 2016 | IDA-34600 | Debt Relief Principal | 149,969.44 |
Sep 15, 2016 | IDA-34600 | Loan Repay | 149,969.44 |
Mar 15, 2016 | IDA-34600 | Loan Repay | 118,876.56 |
Mar 15, 2016 | IDA-34600 | Int Charges | 4.26 |
Mar 15, 2016 | IDA-34600 | Int Charges | 4.26 |
Mar 15, 2016 | IDA-34600 | Int Charges | 87,974.22 |
Mar 15, 2016 | IDA-34600 | Int Charges | 87,974.22 |
Mar 15, 2016 | IDA-34600 | Debt Relief Charges | 3,419.82 |
Mar 15, 2016 | IDA-34600 | Int Charges | 3,419.82 |
Mar 15, 2016 | IDA-34600 | Int Charges | 3,419.82 |
Mar 15, 2016 | IDA-34600 | Debt Relief Principal | 149,642.10 |
Mar 15, 2016 | IDA-34600 | Loan Repay | 149,642.10 |
Sep 15, 2015 | IDA-34600 | Debt Relief Principal | 153,491.03 |
Sep 15, 2015 | IDA-34600 | Loan Repay | 153,491.03 |
Sep 15, 2015 | IDA-34600 | Loan Repay | 14,705.90 |
Sep 17, 2015 | IDA-34600 | Loan Repay | 103,621.91 |
Sep 17, 2015 | IDA-34600 | Int Charges | 6.25 |
Sep 17, 2015 | IDA-34600 | Int Charges | 6.25 |
Sep 17, 2015 | IDA-34600 | Int Charges | 89,334.36 |
Sep 17, 2015 | IDA-34600 | Int Charges | 89,334.36 |
Mar 15, 2015 | IDA-34600 | Debt Relief Principal | 153,920.20 |
Mar 15, 2015 | IDA-34600 | Loan Repay | 153,920.20 |
Mar 15, 2015 | IDA-34600 | Loan Repay | 13,104.36 |
Mar 18, 2015 | IDA-34600 | Loan Repay | 97,080.77 |
Mar 18, 2015 | IDA-34600 | Int Charges | 63.44 |
Sep 15, 2019 | IDA-34600 | Int Charges | 82,342.91 |
Mar 15, 2019 | IDA-34600 | Debt Relief Charges | 84.81 |
Mar 15, 2019 | IDA-34600 | Int Charges | 84.81 |
Mar 15, 2019 | IDA-34600 | Int Charges | 84.81 |
Mar 15, 2019 | IDA-34600 | Debt Relief Principal | 150,402.23 |
Mar 15, 2019 | IDA-34600 | Loan Repay | 150,402.23 |
Mar 15, 2019 | IDA-34600 | Loan Repay | 117,850.55 |
Mar 15, 2019 | IDA-34600 | Int Charges | 84,499.63 |
Mar 15, 2019 | IDA-34600 | Int Charges | 84,499.63 |
Mar 15, 2019 | IDA-34600 | Int Charges | 30.85 |
Mar 15, 2019 | IDA-34600 | Int Charges | 30.85 |
Sep 27, 2018 | IDA-34600 | Loan Repay | 124,268.02 |
Sep 27, 2018 | IDA-34600 | Int Charges | 49.69 |
Sep 27, 2018 | IDA-34600 | Int Charges | 49.69 |
Sep 27, 2018 | IDA-34600 | Int Charges | 86,015.25 |
Sep 27, 2018 | IDA-34600 | Int Charges | 86,015.25 |
Sep 15, 2018 | IDA-34600 | Debt Relief Charges | 4,996.92 |
Sep 15, 2018 | IDA-34600 | Int Charges | 4,996.92 |
Sep 15, 2018 | IDA-34600 | Int Charges | 4,996.92 |
Sep 15, 2018 | IDA-34600 | Debt Relief Principal | 145,919.25 |
Sep 15, 2018 | IDA-34600 | Loan Repay | 145,919.25 |
Apr 3, 2018 | IDA-34600 | Int Charges | 85,071.51 |
Apr 3, 2018 | IDA-34600 | Int Charges | 85,071.51 |
Mar 15, 2018 | IDA-34600 | Debt Relief Charges | 8,695.30 |
Mar 15, 2018 | IDA-34600 | Int Charges | 8,695.30 |
Mar 15, 2018 | IDA-34600 | Int Charges | 8,695.30 |
Mar 15, 2018 | IDA-34600 | Debt Relief Principal | 142,650.02 |
Mar 15, 2018 | IDA-34600 | Loan Repay | 142,650.02 |
Apr 3, 2018 | IDA-34600 | Loan Repay | 137,263.12 |
Sep 15, 2017 | IDA-34600 | Int Charges | 60,518.37 |
Sep 15, 2017 | IDA-34600 | Int Charges | 60,518.37 |
Sep 15, 2017 | IDA-34600 | Loan Repay | 142,569.77 |
Sep 15, 2017 | IDA-34600 | Debt Relief Charges | 20,456.95 |
Sep 15, 2017 | IDA-34600 | Int Charges | 20,456.95 |
Sep 15, 2017 | IDA-34600 | Int Charges | 20,456.95 |
Sep 15, 2017 | IDA-34600 | Debt Relief Principal | 131,317.52 |
Sep 15, 2017 | IDA-34600 | Loan Repay | 131,317.52 |
Sep 15, 2017 | IDA-34600 | Loan Repay | 424.67 |
Mar 15, 2017 | IDA-34600 | Debt Relief Principal | 150,671.00 |
Mar 15, 2017 | IDA-34600 | Loan Repay | 150,671.00 |
Mar 15, 2017 | IDA-34600 | Int Charges | 52,581.05 |
Mar 15, 2017 | IDA-34600 | Int Charges | 52,581.05 |
Mar 15, 2017 | IDA-34600 | Int Charges | 33,223.76 |
Mar 15, 2022 | IDA-34600 | Int Charges | 606.64 |
Mar 15, 2022 | IDA-34600 | Int Charges | 606.64 |
Mar 15, 2022 | IDA-34600 | Debt Relief Principal | 260,886.03 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2007-10-12 |
Procurement | Satisfactory | 2007-10-12 |
Financial Management | Satisfactory | 2007-10-12 |
Overall Implementation Progress (IP) | Satisfactory | 2007-10-12 |
Progress towards achievement of PDO | Satisfactory | 2007-10-12 |
Counterpart Funding | Moderately Satisfactory | 2007-10-12 |
Project Management | Satisfactory | 2007-10-12 |
Monitoring and Evaluation | Satisfactory | 2007-10-12 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2008 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 09-30-2008 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of rehabilitated or constructed infrastructure found to be operational and properly maintained after completion. | Value | There is no baseline information. Progress is agai | 99.9% | 75% |
Date | June 30, 2002 | July 31, 2007 | July 31, 2007 | |
Comment |
Over 750,000 average person/days of employment created. | Value | There is no baseline as the performance is only re | 5,300,000person/days | 2,750,000 person/days |
Date | June 30, 2002 | July 31, 2007 | July 31, 2007 | |
Comment |
Staff and officials of Municipalities trained by Technical Secretariat on sub-project identification, execution, operation and maintenance | Value | There is no specified baseline. Progress will be m | Staff and officials in 129 municipalities e.g 190, | Staff and officials in 129 municipalities. |
Date | June 30, 2002 | July 31, 2007 | July 31, 2007 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Operating costs of ABUTIP not exceeding 8% of the amount of executed works. | Value | There is no baseline as the operator (ABUTIP) was | 6.2 % | 8 % |
Date | June 30, 2002 | July 31, 2007 | July 31, 2007 | |
Comment |
Minimum number of firms participating in bidding for subprojects. | Value | N/A | 8 | 3 |
Date | June 30, 2002 | July 31, 2007 | July 31, 2007 | |
Comment |