Coastal Cities Pollution Control Project (APL#1)

Abstract*

The overall project development objective of the Coastal Cities Pollution Control Project for Croatia is to improve the quality of Croatia's Adriatic coastal waters to meet European Union ambient quality standards in the participating municipalities, in a financially and operationally sustainable manner. The project has three main components. The first, Coastal Environmental Infrastructure Component, finances investments in the construction and expansion...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve the quality of Croatia's Adriatic coastal waters to meet EU ambient quality standards in the participating municipalities, in a financially and operationally sustainable manner.

Key Details

Project Details

  • P065416

  • Closed

  • Michael Webster

  • N/A

  • Croatia

  • January 9, 2002

  • (as of board presentation)

    June 1, 2004

  • December 17, 2004

  • US$ 47.54 million

  • F

  • Not Applicable

  • November 30, 2009

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 47.54
Borrower/Recipient 47.51

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 47.54
IDA Commitment N/A
IBRD + IDA Commitment 47.54
Lending Instrument
Grant Amount N/A
Total Project Cost** 95.05

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2014 IBRD-72260 Int Charges 80,884.95
Oct 15, 2013 IBRD-72260 Loan Repay 2,652,280.00
Oct 15, 2013 IBRD-72260 Int Charges 76,050.40
Apr 15, 2014 IBRD-72260 Loan Repay 2,712,248.80
Apr 15, 2014 IBRD-72260 Int Charges 78,442.95
Apr 15, 2015 IBRD-72260 Loan Repay 2,080,809.50
Apr 15, 2015 IBRD-72260 Int Charges 37,877.08
Oct 15, 2015 IBRD-72260 Int Charges 29,259.89
Oct 15, 2015 IBRD-72260 Loan Repay 2,248,033.20
Apr 15, 2016 IBRD-72260 Loan Repay 2,217,557.50
Apr 15, 2016 IBRD-72260 Int Charges 21,309.79
Oct 15, 2016 IBRD-72260 Loan Repay 2,164,962.00
Oct 15, 2016 IBRD-72260 Int Charges 6,604.78
Oct 15, 2017 IBRD-72260 Loan Repay 2,325,205.80
Apr 15, 2017 IBRD-72260 Loan Repay 2,088,576.00
Apr 15, 2017 IBRD-72260 Int Charges 1,584.32
Apr 15, 2018 IBRD-72260 Loan Repay 2,422,925.00
Oct 15, 2018 IBRD-72260 Loan Repay 2,280,377.00
Apr 15, 2019 IBRD-72260 Loan Repay 2,227,297.00
Oct 15, 2014 IBRD-72260 Loan Repay 2,485,842.80
Jun 1, 2004 IBRD-72260 Loan Commitment 47,540,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2009-11-21
Counterpart Funding Moderately Satisfactory 2009-11-21
Project Management Satisfactory 2009-11-21
Financial Management Satisfactory 2009-11-21
Overall Implementation Progress (IP) Moderately Satisfactory 2009-11-21
Overall Safeguards Rating Moderately Satisfactory 2009-11-21
Progress towards achievement of PDO Moderately Satisfactory 2009-11-21
Monitoring and Evaluation Moderately Satisfactory 2009-11-21

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-20-2010
OutcomesModerately Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceModerately Satisfactory
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-24-2011PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a