Municipal Program

Abstract*

The development objective of the Municipal Program Project for Kenya is to strengthen local governance and improve service delivery in selected municipalities. There are four components to the project. The first component of the project is institutional strengthening. This component will support institutional strengthening, capacity building, and policy development at the national and municipal levels to facilitate decentralization and build a capable...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed new PDO is “to improve planning and delivery of infrastructure services in urban areas in selected counties.”

Key Details

Project Details

  • P066488

  • Closed

  • Abdu Muwonge , Sheila Kamunyori

  • National Treasury

  • Kenya

  • September 30, 2009

  • (as of board presentation)

    May 4, 2010

  • June 28, 2010

  • US$ 123.66 million

  • Ministry of Transport, Infrastructure, Housing and Urban Development

  • Eastern and Southern Africa

  • 2010

  • US$ 113.66 million

  • B

  • Not Applicable

  • May 31, 2017

  • BANK APPROVED

  • February 5, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
SWEDEN: Swedish Intl. Dev. Cooperation Agency (SIDA) 13.66
IDA Credit 100.00
Borrower/Recipient 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount 13.66
Total Project Cost** 123.66

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 23, 2014 IDA-47140 Int Charges 116,049.38
May 23, 2014 IDA-47140 Int Charges 116,049.38
May 23, 2014 IDA-47140 Int Charges 4,958.23
May 23, 2014 IDA-47140 Int Charges 4,958.23
May 15, 2020 IDA-47140 Loan Repay 887,680.60
May 15, 2020 IDA-47140 Int Charges 332,880.22
May 15, 2020 IDA-47140 Int Charges 332,880.22
May 15, 2020 IDA-47140 Int Charges 324.51
May 15, 2020 IDA-47140 Int Charges 324.51
Nov 15, 2020 IDA-47140 Loan Repay 910,283.80
Nov 15, 2020 IDA-47140 Int Charges 341,353.80
Nov 15, 2020 IDA-47140 Int Charges 341,353.80
Nov 15, 2020 IDA-47140 Loan Repay 16,857.58
May 15, 2021 IDA-47140 Int Charges 336,108.50
May 15, 2021 IDA-47140 Int Charges 2,885.31
May 15, 2021 IDA-47140 Int Charges 2,885.31
May 15, 2021 IDA-47140 Loan Repay 939,470.00
May 15, 2019 IDA-47140 Int Charges 4,994.12
May 15, 2019 IDA-47140 Int Charges 4,994.12
May 24, 2019 IDA-47140 Int Charges 332,897.94
May 24, 2019 IDA-47140 Int Charges 332,897.94
Nov 15, 2019 IDA-47140 Int Charges 3,061.67
Nov 15, 2019 IDA-47140 Int Charges 3,061.67
Nov 15, 2019 IDA-47140 Int Charges 333,192.94
Nov 15, 2019 IDA-47140 Int Charges 333,192.94
May 17, 2018 IDA-47140 Int Charges 346,959.06
May 17, 2018 IDA-47140 Int Charges 346,959.06
May 15, 2018 IDA-47140 Int Charges 1,290.10
May 15, 2018 IDA-47140 Int Charges 1,290.10
Nov 15, 2018 IDA-47140 Int Charges 7,624.79
Nov 15, 2018 IDA-47140 Int Charges 7,624.79
Nov 16, 2018 IDA-47140 Int Charges 330,866.80
Nov 16, 2018 IDA-47140 Int Charges 330,866.80
May 15, 2023 IDA-47140 Int Charges 298,808.70
Nov 15, 2023 IDA-47140 Int Charges 10,123.30
Nov 15, 2023 IDA-47140 Int Charges 10,123.30
Nov 15, 2023 IDA-47140 Loan Repay 866,105.56
Nov 15, 2023 IDA-47140 Int Charges 295,276.06
Nov 15, 2023 IDA-47140 Int Charges 295,276.06
May 15, 2024 IDA-47140 Int Charges 6,762.75
May 15, 2024 IDA-47140 Int Charges 6,762.75
May 15, 2024 IDA-47140 Loan Repay 864,127.00
May 15, 2024 IDA-47140 Int Charges 298,123.84
May 15, 2024 IDA-47140 Int Charges 298,123.84
May 4, 2010 IDA-47140 Loan Commitment 100,000,000.00
Nov 15, 2022 IDA-47140 Loan Repay 43,125.13
Nov 15, 2022 IDA-47140 Loan Repay 816,202.30
Nov 15, 2022 IDA-47140 Int Charges 287,484.03
Nov 15, 2022 IDA-47140 Int Charges 287,484.03
May 15, 2023 IDA-47140 Int Charges 19,029.65
May 15, 2023 IDA-47140 Int Charges 19,029.65
May 15, 2023 IDA-47140 Loan Repay 876,756.00
May 15, 2023 IDA-47140 Int Charges 298,808.70
May 15, 2021 IDA-47140 Int Charges 336,108.50
Nov 15, 2021 IDA-47140 Int Charges 333,710.88
Nov 15, 2021 IDA-47140 Int Charges 333,710.88
Nov 15, 2021 IDA-47140 Int Charges 8,932.03
Nov 15, 2021 IDA-47140 Int Charges 8,932.03
Nov 15, 2021 IDA-47140 Loan Repay 917,418.25
May 15, 2022 IDA-47140 Loan Repay 18,897.36
May 15, 2022 IDA-47140 Loan Repay 850,094.44
May 15, 2022 IDA-47140 Int Charges 312,837.03
May 15, 2022 IDA-47140 Int Charges 312,837.03
Nov 21, 2014 IDA-47140 Loan Disb -4,097.34
Dec 4, 2014 IDA-47140 Loan Disb -10,419.89
Sep 25, 2014 IDA-47140 Loan Disb 14,919,427.00
May 18, 2015 IDA-47140 Int Charges 10,650.24
May 18, 2015 IDA-47140 Int Charges 10,650.24
May 18, 2015 IDA-47140 Int Charges 202,382.69
Nov 15, 2014 IDA-47140 Int Charges 14,066.11
Nov 15, 2014 IDA-47140 Int Charges 14,066.11
Nov 15, 2014 IDA-47140 Int Charges 165,867.55
Nov 15, 2014 IDA-47140 Int Charges 165,867.55
Sep 27, 2013 IDA-47140 Loan Disb 4,369,136.00
May 15, 2017 IDA-47140 Int Charges 9,058.85
Mar 8, 2017 IDA-47140 Loan Disb 426,316.47
May 15, 2017 IDA-47140 Int Charges 320,418.34
May 15, 2017 IDA-47140 Int Charges 320,418.34
Dec 1, 2017 IDA-47140 Int Charges 5,246.62
Dec 1, 2017 IDA-47140 Int Charges 5,246.62
Dec 1, 2017 IDA-47140 Int Charges 347,384.16
Dec 1, 2017 IDA-47140 Int Charges 347,384.16
Nov 30, 2017 IDA-47140 Loan Cancel 106.48
May 15, 2016 IDA-47140 Int Charges 5,137.85
May 15, 2016 IDA-47140 Int Charges 5,137.85
May 17, 2016 IDA-47140 Int Charges 325,680.12
May 17, 2016 IDA-47140 Int Charges 325,680.12
Nov 15, 2016 IDA-47140 Int Charges 332,280.30
Nov 15, 2016 IDA-47140 Int Charges 332,280.30
Nov 15, 2016 IDA-47140 Int Charges 3,742.45
Nov 15, 2016 IDA-47140 Int Charges 3,742.45
May 15, 2017 IDA-47140 Int Charges 9,058.85
May 18, 2015 IDA-47140 Int Charges 202,382.69
Jun 11, 2015 IDA-47140 Loan Disb 18,149,470.00
Nov 15, 2015 IDA-47140 Int Charges 7,161.58
Nov 15, 2015 IDA-47140 Int Charges 7,161.58
Nov 15, 2015 IDA-47140 Int Charges 261,998.61
Nov 15, 2015 IDA-47140 Int Charges 261,998.61
Dec 9, 2015 IDA-47140 Loan Disb 17,570,688.00
Nov 19, 2015 IDA-47140 Loan Disb -25,036.44
Nov 15, 2013 IDA-47140 Int Charges 306.10
Nov 15, 2013 IDA-47140 Int Charges 306.10
Nov 15, 2013 IDA-47140 Int Charges 95,228.05
Nov 15, 2013 IDA-47140 Int Charges 95,228.05
Mar 24, 2014 IDA-47140 Loan Disb 14,634,601.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2017-06-27
Project Management Moderately Satisfactory 2017-06-27
Financial Management Moderately Satisfactory 2017-06-27
Counterpart Funding Moderately Satisfactory 2017-06-27
Monitoring and Evaluation Satisfactory 2017-06-27
Overall Implementation Progress (IP) Moderately Satisfactory 2017-06-27
Overall Safeguards Rating Moderately Satisfactory 2017-06-27
Progress towards achievement of PDO Moderately Satisfactory 2017-06-27
Overall Safeguards Rating Moderately Satisfactory 2017-06-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-22-2017
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-13-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.002000000.002100000.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Number of people in urban areas provided with access to all-season roads within a 500 meter range under the projectValue0.00170000.0069200.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • People in targeted urban areas protected from periodic flooding under the KMP (number)Value0.00525000.00507000.00
    DateSeptember 28, 2009March 11, 2016May 31, 2017
    Comment
  • Integrated strategic urban development plans approved by the county assembly and gazetted.Value0.0012.0014.00
    DateSeptember 28, 2009March 11, 2015November 25, 2016
    Comment
  • Percentage of direct project beneficiaries that are femaleValue0.000.0050.00
    DateSeptember 28, 2009May 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Markets constructed and operatingValue0.005.003.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Street and security lights installed and operatingValue0.00887.001254.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Handbooks for preparation of county integrated development plans with three sections: (a) institutional, (b) spatial, and (c) governance and accountability.Value0.001.001.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Fire engines delivered and providing services (number of urban centers benefiting)Value0.0015.0015.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Feasibility studies and designs prepared under KMP for future investments in urban infrastructureValue0.0012.0012.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Model restructuring guide for establishment of urban boards and town committeesValue0.001.001.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Capacity assessment tool for urban boards and town committeesValue0.001.001.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Policy for transfer of assets from former local authorities to counties.Value0.001.001.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Urban centers with an approved capital investment plan prepared in a participatory mannerValue0.0012.0014.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • RAPs are implemented in a satisfactory manner prior to the start of works.Value0.00100.0090.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Drains constructed or rehabilitated under the KMPValue0.0090.0052.60
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Urban centers with structure plan and land use guidelines approved by the authorities.Value0.0012.0014.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • EMPs implemented in a satisfactory manner.Value0.00100.00100.00
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Roads constructed or rehabilitated under the KMPValue0.0034.6023.74
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment
  • Non-motorized transport links constructed or rehabilitated under the KMPValue0.00137.00202.20
    DateSeptember 28, 2009March 11, 2015May 31, 2017
    Comment