Financier | Commitments |
---|---|
Borrowing Country's Fin. Intermediary/ies | 37.50 |
Local Sources of Borrowing Country | 12.58 |
Borrower/Recipient | 0.22 |
Global Environment Facility (GEF) | 12.00 |
P066532
Closed
Alan Townsend
N/A
March 18, 2003
(as of board presentation)
April 29, 2004
November 5, 2004
US$ 62.30 million
N/A
2004
US$ 12.00 million
F
July 16, 2019
December 31, 2013
BANK APPROVED
Financier | Commitments |
---|---|
Borrowing Country's Fin. Intermediary/ies | 37.50 |
Local Sources of Borrowing Country | 12.58 |
Borrower/Recipient | 0.22 |
Global Environment Facility (GEF) | 12.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 12.00 |
Total Project Cost** | 62.30 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2013-12-13 |
Project Management | Satisfactory | 2013-12-13 |
Summary Global Objective Rating | Satisfactory | 2013-12-13 |
Counterpart Funding | Satisfactory | 2013-12-13 |
Monitoring and Evaluation | Satisfactory | 2013-12-13 |
Overall Implementation Progress (IP) | Satisfactory | 2013-12-13 |
Financial Management | Moderately Satisfactory | 2013-12-13 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-24-2014 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 06-17-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
loan guaranteed investments under the project | Value | 0 | $50-million booked and another $20-m. to be booked | at least $24 million of loan guarantee issued and |
Date | April 28, 2005 | November 14, 2013 | December 31, 2013 | |
Comment | The project has exceeded its end-target by as much as 150% (pending final tally of lending as of early 2014). |
commercial banks and other financial institutions providing loans to ECs | Value | zero | 7 banks have made loans under the program. | at least 4 commercial banks and other financial in |
Date | April 28, 2005 | November 14, 2013 | December 31, 2013 | |
Comment | The project has exceeded the target by 3. |
cumulative claim payments | Value | zero | No claims have been made. | not more than $3 million of cumulative guarantee c |
Date | April 28, 2005 | November 14, 2013 | December 31, 2013 | |
Comment | 16 loans are wholly or mostly drawn, and several are now in the principal repayment stage. No claims made. |
IMC transactions supported by the project | Value | zero | IMC's dropped from the project. | at least 6 IMC transactions |
Date | April 28, 2005 | November 14, 2012 | December 31, 2013 | |
Comment | The IMC approach proved unworkable, and has been dropped from the project. |
EC loan guarantees | Value | zero | 23 booked and/or approved guarantees, plus a large | at least 15 loan guarantees issued for ECs |
Date | April 28, 2005 | November 14, 2012 | December 31, 2013 | |
Comment | LGUGC has done a good job developing its capabilities in this area; and can now process much of the work involved in developinganddelivering its pipeline quite efficiently. |
TA and training programs developed and delivered | Value | zero | Technical assistance and trainng has been delivere | Total disbursement for the $2 million capacity bui |
Date | April 28, 2005 | November 14, 2012 | December 31, 2013 | |
Comment | The full $2-million will be used. Relatively less training will be done than originally designed as the operational requirementsof the program demand more resources. |
energy savings | Value | zero | 120 GWh | at least 80 GWh annually by the end of the Project |
Date | April 28, 2005 | November 14, 2013 | December 31, 2013 | |
Comment | With assets now in service, estimates and projections have been made, on a preliminary basis, that indicate that project resultsmay exceed targets by 50%. This result will be verified once the Borrower Completion Report is available in early 2014. |
carbon dioxide emissions avoided | Value | zero | 60,000 | at least 40,000 tons annually by the end of the pr |
Date | April 28, 2005 | November 14, 2013 | December 31, 2013 | |
Comment | Preliminary estimate; results may exceed target by 50%. |